1936 S THAYER AVE 90025
Certificate Information: 1936 S THAYER AVE 90025
- Application / Permit
- 22010-20000-00173
- Plan Check / Job No.
- B22VN00429
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (62'-9"x 40'-5") 2-STORY IRR SHAPE SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE, NFPA-13D AUTO FIRE SPRINKLER THROUGHOUT.
- Permit Issued
- Issued on 11/10/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2022 | TROY DEGUZMAN |
| Corrections Issued | 2/9/2022 | TROY DEGUZMAN |
| Quality Review Completed | 2/11/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 2/14/2022 | APPLICANT |
| Applicant returned to address corrections | 4/27/2022 | TROY DEGUZMAN |
| Applicant returned to address corrections | 7/19/2022 | TROY DEGUZMAN |
| Applicant returned to address corrections | 9/2/2022 | MOHAMMAD ESMAILI |
| Plan Check Approved | 11/10/2022 | MOHAMMAD ESMAILI |
| Issued | 11/10/2022 | APPLICANT |
| CofO in Progress | 3/20/2025 | DANIEL VERA |
| Permit Finaled | 4/9/2025 | RICHARD STEINBACH |
| CofO Issued | 4/9/2025 | RICHARD STEINBACH |
| Permit Finaled | 4/9/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 4/27/2022 | AL GAMBLE |
| Grading Pre-Inspection | Cleared | 4/27/2022 | AL GAMBLE |
| Low Impact Development | Cleared | 7/22/2022 | ANTHONY VARGAS |
| Hydrant and Access approval | Cleared | 7/26/2022 | KURT CORRAL |
| Address approval | Cleared | 7/27/2022 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/28/2022 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 7/28/2022 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 7/28/2022 | ANTHONY MAINEZ |
| Green Code | Cleared | 8/2/2022 | TROY DEGUZMAN |
Contact Information
| Contractor | Cas Construction; Lic. No.: 766810-B | PO BOX 572349 TARZANA, CA 91357 |
| Engineer | Baraty,, Patrick; Lic. No.: S5900 | 1819 SUNSHINE COURT GLENDALE, CA 91208 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/22/2023 | Approved | BRENDAN LOONEY |
| Footing/Foundation/Slab | 6/12/2023 | Corrections Issued | STEPHANIE SWANSON |
| METHANE-Barrier | 6/12/2023 | No Access for Inspection | STEPHANIE SWANSON |
| METHANE-Subgrade | 6/12/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 7/3/2023 | Partial Approval | BRENDAN LOONEY |
| METHANE-Barrier | 7/3/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| METHANE-Subgrade | 7/3/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Deputy Reinf. Concrete | 7/7/2023 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Concrete | 7/13/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 7/20/2023 | Partial Approval | STEPHANIE SWANSON |
| METHANE-Barrier | 7/20/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| METHANE-Subgrade | 7/20/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Deputy Methane Barrier | 8/16/2023 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 8/16/2023 | Corrections Issued | STEPHANIE SWANSON |
| METHANE-Barrier | 8/16/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| METHANE-Subgrade | 8/16/2023 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 8/21/2023 | Corrections Issued | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 8/24/2023 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 8/31/2023 | Partial Approval | STEPHANIE SWANSON |
| Deputy Methane Barrier | 9/8/2023 | Conditional Approval | MICHAEL PELHAM |
| ELECTRICAL-Rough | 9/18/2023 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 9/18/2023 | Partial Approval | STEPHANIE SWANSON |
| METHANE-Barrier | 9/18/2023 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 9/25/2023 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/2/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 10/2/2023 | Corrections Issued | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 10/2/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2023 | Partial Approval | MICHAEL PELHAM |
| Deputy Wood Construction | 10/6/2023 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2023 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 10/26/2023 | Partial Approval | STEPHANIE SWANSON |
| Deputy Reinf. Concrete | 12/12/2023 | Approved | STEPHANIE SWANSON |
| Deputy Wood Construction | 12/12/2023 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2023 | Partial Inspection | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 2/1/2024 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 2/1/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 2/1/2024 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 2/14/2024 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2024 | Partial Approval | STEPHANIE SWANSON |
| Green Building Rough | 2/14/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 2/14/2024 | Corrections Issued | STEPHANIE SWANSON |
| METHANE-Rough | 2/14/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 2/14/2024 | Approved | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 2/14/2024 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 3/4/2024 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Rough | 3/4/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 3/4/2024 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 3/4/2024 | Partial Approval | STEPHANIE SWANSON |
| METHANE-Rough | 3/4/2024 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 3/12/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 3/12/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 3/12/2024 | Approved | STEPHANIE SWANSON |
| Insulation | 3/12/2024 | Approved | STEPHANIE SWANSON |
| METHANE-Rough | 3/12/2024 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 3/19/2024 | Approved | STEPHANIE SWANSON |
| Shower Pan | 3/19/2024 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 3/21/2024 | Approved | STEPHANIE SWANSON |
| Shower Pan | 3/21/2024 | Approved | STEPHANIE SWANSON |
| Sewer | 5/28/2024 | Partial Approval | HERBERT GIRON |
| Sewer | 9/11/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 1/24/2025 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 1/29/2025 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 1/31/2025 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 2/3/2025 | Corrections Issued | JESUS RODRIGUEZ |
| Final | 2/7/2025 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 2/7/2025 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 2/7/2025 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 2/7/2025 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 2/7/2025 | Corrections Issued | STEPHANIE SWANSON |
| Final | 3/11/2025 | Partial Approval | DANIEL VERA |
| Footing/Foundation/Slab | 3/11/2025 | Approved | DANIEL VERA |
| HVAC-Final | 3/11/2025 | Approved | DANIEL VERA |
| SUSMP-Std. Urban Storm Water | 3/11/2025 | Approved | DANIEL VERA |
| Smoke Detectors | 3/11/2025 | Approved | DANIEL VERA |
| Final | 3/14/2025 | Not Ready for Inspection | DANIEL VERA |
| Final | 3/19/2025 | OK to Issue CofO | DANIEL VERA |