6208 N GLIDE AVE 91367

Certificate Information: 6208 N GLIDE AVE 91367

Application / Permit
22010-20000-00119
Plan Check / Job No.
B22VN00364
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan PROPOSED 2 STORY DETACHED ADU PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d)
Permit Issued
Issued on 10/31/2022
Issuing Office
Current Status
CofO Corrected on 1/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/18/2022 APPLICANT
Assigned to Plan Check Engineer 2/17/2022 CRYSTEL MAALOUF
Corrections Issued 3/21/2022 CRYSTEL MAALOUF
Quality Review Completed 3/23/2022 SAI KHUM
Applicant returned to address corrections 10/3/2022 CRYSTEL MAALOUF
Applicant returned to address corrections 10/14/2022 CRYSTEL MAALOUF
Plan Check Approved 10/25/2022 CRYSTEL MAALOUF
Issued 10/31/2022 APPLICANT
CofO in Progress 7/25/2023 TROY SANDERS
CofO Issued-Status Void 9/12/2023 JOHN JANSON
Permit Finaled-Status Void 9/12/2023 JOHN JANSON
Re-Activate Permit 1/4/2024 JOHN JANSON
Permit Finaled 1/4/2024 JOHN JANSON
CofO Corrected 1/4/2024 JOHN JANSON
Permit Finaled 1/4/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 4/15/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/11/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 5/11/2022 DAGOVERTO GUERRERO
Construction near power lines Cleared 7/28/2022 RIDWAN HARDY
Construction within easement Cleared 7/28/2022 RIDWAN HARDY
Low Impact Development Cleared 9/20/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 9/28/2022 DAGOVERTO GUERRERO
Permit Cleared 10/18/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Vartanian,, Albert; Lic. No.: C39989 PO BOX 857      VERDUGO CITY, CA 91046

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/16/2022 Approved TROY SANDERS
Underground Mechanical 12/16/2022 Approved TROY SANDERS
Excavation/Setback/Form/Re-Bar 12/30/2022 Corrections Issued TROY SANDERS
Footing/Foundation/Slab 12/30/2022 Conditional Approval TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 2/10/2023 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 3/1/2023 Approved TROY SANDERS
Rough-Elec/Plmb/HVAC 3/1/2023 Approved TROY SANDERS
Special/Order Compliance 3/1/2023 Partial Inspection JESUS PINEDA
Verify Sprinkler Sign Off 3/1/2023 Approved TROY SANDERS
Wood Frame 3/1/2023 Corrections Issued TROY SANDERS
Deputy Wood Construction 3/2/2023 Partial Approval TROY SANDERS
Insulation 3/20/2023 Conditional Approval TROY SANDERS
Special/Order Compliance 3/20/2023 Partial Inspection JUSTIN HAWLEY
Drywall Nailing 4/14/2023 Approved TROY SANDERS
Gas Test 4/14/2023 Approved TROY SANDERS
Green Building Rough 4/14/2023 Approved TROY SANDERS
Interior/Exterior Lathing 4/14/2023 Partial Approval TROY SANDERS
Underground Mechanical 4/14/2023 Partial Approval TROY SANDERS
ELECTRICAL-Rough 6/6/2023 Partial Approval HORACE FULTZ
Final 7/13/2023 Corrections Issued TROY SANDERS
Footing/Foundation/Slab 7/13/2023 Approved TROY SANDERS
Green Building Final 7/13/2023 Not Ready for Inspection TROY SANDERS
SGSOV-Seismic Gas S/O Valve 7/13/2023 SGSOV Approved TROY SANDERS
Service/Power Release 7/13/2023 Not Ready for Inspection TROY SANDERS
Smoke Detectors 7/13/2023 Approved TROY SANDERS
Final 7/25/2023 OK to Issue CofO TROY SANDERS
Green Building Final 7/25/2023 Approved TROY SANDERS
Service/Power Release 7/25/2023 Approved TROY SANDERS