10200 N BRADLEY AVE 91331

Certificate Information: 10200 N BRADLEY AVE 91331

Application / Permit
22010-20000-00114
Plan Check / Job No.
B22VN00343
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d).
Permit Issued
Issued on 8/8/2022
Issuing Office
Metro
Current Status
Issued on 8/8/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/10/2022 APPLICANT
Assigned to Plan Check Engineer 1/21/2022 GURUNATH NESARAJAH
Corrections Issued 1/22/2022 GURUNATH NESARAJAH
Applicant returned to address corrections 4/18/2022 GURUNATH NESARAJAH
Applicant returned to address corrections 6/25/2022 GURUNATH NESARAJAH
Building Plans Picked Up 6/28/2022 APPLICANT
Issued 8/8/2022 APPLICANT

Permit Application Clearance Information

ZI Cleared 4/8/2022 DANG NGUYEN
Clean Up Green Up Cleared 5/19/2022 DANG NGUYEN
Address approval Cleared 6/22/2022 DAGOVERTO GUERRERO
Miscellaneous Cleared 6/22/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 6/23/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 6/23/2022 DAGOVERTO GUERRERO
Hydrant and Access approval Cleared 7/11/2022 LAVEON RIDER
Low Impact Development Cleared 7/11/2022 LONDY ALVARADO
Roof/Waste drainage to street Cleared 7/12/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Raab,, Andres Gustavo; Lic. No.: C52713 13645 SHABLOW AVE      SYLMAR, CA 91342

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/13/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 10/31/2022 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 11/14/2022 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 11/18/2022 Approved MICHEL ABAJAN
Green Building Rough 11/18/2022 Approved MICHEL ABAJAN
Rough-Elec/Plmb/HVAC 11/18/2022 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 11/18/2022 Approved MICHEL ABAJAN
Insulation 12/5/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 12/5/2022 Approved MICHEL ABAJAN
PLUMBING-Rough 12/5/2022 Approved MICHEL ABAJAN
Drywall Nailing 12/8/2022 Approved MICHEL ABAJAN
Interior/Exterior Lathing 12/27/2022 Approved MICHEL ABAJAN
Shower Pan 12/27/2022 Approved MICHEL ABAJAN
Underground Mechanical 2/6/2023 Approved MICHEL ABAJAN