5086 N VALJEAN AVE 91436

Certificate Information: 5086 N VALJEAN AVE 91436

Application / Permit
22010-20000-00109
Plan Check / Job No.
B22VN00327
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 49'-9" X 17'-5" ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c)¹, (d)¹, and (g)
Permit Issued
Issued on 7/20/2022
Issuing Office
Current Status
CofO Issued on 12/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/13/2022 APPLICANT
Assigned to Plan Check Engineer 2/4/2022 SELLA BENYAMIN
Corrections Issued 2/8/2022 SELLA BENYAMIN
Quality Review Completed 2/10/2022 STEVEN KIM
Building Plans Picked Up 2/17/2022 APPLICANT
Plan Check Approved 6/16/2022 SELLA BENYAMIN
Issued 7/20/2022 APPLICANT
CofO in Progress 11/22/2023 VINCENT HANLEY
Permit Finaled 12/11/2023 JOHN JANSON
CofO Issued 12/11/2023 JOHN JANSON
Permit Finaled 12/11/2023 JOHN JANSON

Permit Application Clearance Information

Hydrant and Access approval Cleared 4/23/2022 GILBERT URREA
Address approval Cleared 4/26/2022 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/27/2022 LEE GUILBEAUX
Sewer availability Cleared 4/27/2022 LEE GUILBEAUX
Low Impact Development Cleared 5/23/2022 KHAING AYE
Roof/Waste drainage to street Cleared 6/30/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/26/2022 Partial Approval VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 10/12/2022 Approved VINCENT HANLEY
Footing/Foundation/Slab 10/12/2022 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 12/1/2022 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 1/17/2023 Approved VINCENT HANLEY
HVAC-Rough 1/17/2023 Approved VINCENT HANLEY
PLUMBING-Rough 1/17/2023 Approved VINCENT HANLEY
BUILDING-Rough-Frame 2/7/2023 Approved VINCENT HANLEY
Green Building Rough 2/7/2023 Approved VINCENT HANLEY
Shower Pan 2/7/2023 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 2/7/2023 Approved VINCENT HANLEY
Interior/Exterior Lathing 2/10/2023 Partial Approval JESUS PINEDA
Insulation 3/16/2023 Approved VINCENT HANLEY
Drywall Nailing 3/29/2023 Approved VINCENT HANLEY
Gas Test 3/29/2023 Partial Approval VINCENT HANLEY
Interior/Exterior Lathing 4/3/2023 Approved VINCENT HANLEY
Pre-Inspection 4/3/2023 Partial Inspection JUSTIN HAWLEY
Gas Test 6/22/2023 Partial Approval JOHN KIDWELL
Underground Mechanical 6/22/2023 Partial Approval JOHN KIDWELL
ELECTRICAL-Final 11/21/2023 Approved VINCENT HANLEY
Final 11/21/2023 OK to Issue CofO VINCENT HANLEY
Green Building Final 11/21/2023 Approved VINCENT HANLEY
HVAC-Final 11/21/2023 Approved VINCENT HANLEY
PLUMBING-Final 11/21/2023 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 11/21/2023 SGSOV Approved VINCENT HANLEY
Service/Power Release 11/21/2023 Approved VINCENT HANLEY
Smoke Detectors 11/21/2023 Approved VINCENT HANLEY