3400 N COLVILLE PL 91436

Certificate Information: 3400 N COLVILLE PL 91436

Application / Permit
22010-20000-00101
Plan Check / Job No.
B22VN00294
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY _X46'0" SINGLE FAMILY DWELLING WITH 2-CAR ATTACHED GARAGE. NFPA 13 D FIRE SPRINKLERS REQUIRED THROUGHOUT.
Permit Issued
Issued on 2/22/2023
Issuing Office
Valley
Current Status
CofO Issued on 9/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/10/2022 APPLICANT
Assigned to Plan Check Engineer 2/4/2022 MARVEL DELACRUZ
Corrections Issued 2/10/2022 MARVEL DELACRUZ
Quality Review Completed 2/15/2022 STEVEN KIM
Building Plans Picked Up 2/16/2022 APPLICANT
Applicant returned to address corrections 10/21/2022 MARVEL DELACRUZ
Plan Check Approved 12/5/2022 MARVEL DELACRUZ
Issued 2/22/2023 APPLICANT
CofO in Progress 8/15/2024 THOMAS FINNILA
Permit Finaled 9/24/2024 JOHN JANSON
CofO Issued 9/24/2024 JOHN JANSON
Permit Finaled 9/24/2024 JOHN JANSON

Permit Application Clearance Information

Construction near power lines Cleared 3/29/2022 RIDWAN HARDY
Construction within easement Cleared 3/29/2022 RIDWAN HARDY
Trees in Parkway Cleared 5/24/2022 ADALBERTO VERA
Miscellaneous Cleared 6/24/2022 STEVEN WECHSLER
Specific Plan Cleared 6/24/2022 STEVEN WECHSLER
Specific Plan Cleared 6/24/2022 STEVEN WECHSLER
ZI Cleared 6/24/2022 STEVEN WECHSLER
ZI Cleared 6/24/2022 STEVEN WECHSLER
Address approval Cleared 8/30/2022 MEGAN GODINEZ
BHO/Hillside ordinance Cleared 8/30/2022 MEGAN GODINEZ
BHO/Hillside ordinance Cleared 8/30/2022 MEGAN GODINEZ
BHO/Hillside ordinance Cleared 8/30/2022 MEGAN GODINEZ
BHO/Hillside ordinance Cleared 8/30/2022 MEGAN GODINEZ
BHO/Hillside ordinance Cleared 8/30/2022 MEGAN GODINEZ
Permit Cleared 8/30/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 8/31/2022 MEGAN GODINEZ
Sewer availability Cleared 8/31/2022 MEGAN GODINEZ
Miscellaneous Cleared 9/23/2022 STEVEN WECHSLER
Low Impact Development Cleared 9/29/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 9/29/2022 DAGOVERTO GUERRERO
Distance to fire station Cleared 10/14/2022 GILBERT URREA
Hydrant and Access approval Cleared 10/14/2022 GILBERT URREA
GPI Written Notices Cleared 10/21/2022 MARVEL DELACRUZ
Grading Pre-Inspection Cleared 10/21/2022 MARVEL DELACRUZ
Green Code Cleared 12/5/2022 MARVEL DELACRUZ

Contact Information

Architect Janev,, Valentine S; Lic. No.: C19379 19261 WELLS DRIVE      TARZANA, CA 91356
Contractor Owner-Builder       ,
Engineer Henderson,, Allan Phillip; Lic. No.: GE391 1965 AIRPORT DR      BAKERSFIELD, CA 93308
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/8/2023 Partial Approval VINCENT HANLEY
Sewer 6/8/2023 Approved VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 6/12/2023 Approved VINCENT HANLEY
Footing/Foundation/Slab 6/12/2023 Approved VINCENT HANLEY
Underground Mechanical 6/12/2023 Partial Approval VINCENT HANLEY
Deputy Reinf. Concrete 6/13/2023 Approved VINCENT HANLEY
Deputy Wood Construction 7/6/2023 Approved VINCENT HANLEY
BUILDING-Rough-Frame 7/17/2023 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 7/17/2023 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 7/17/2023 Approved VINCENT HANLEY
Green Building Rough 7/17/2023 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 7/17/2023 Approved VINCENT HANLEY
PLUMBING-Rough 7/17/2023 Approved VINCENT HANLEY
Structural Steel Frame 7/17/2023 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 7/17/2023 Not Ready for Inspection VINCENT HANLEY
Insulation 8/18/2023 Conditional Approval JOHN KIDWELL
Drywall Nailing 8/25/2023 Conditional Approval JOHN KIDWELL
Green Building Rough 8/25/2023 Partial Approval JOHN KIDWELL
Shower Pan 8/25/2023 Approved JOHN KIDWELL
BUILDING-Rough-Frame 9/20/2023 Approved VINCENT HANLEY
Green Building Rough 9/20/2023 Approved VINCENT HANLEY
Interior/Exterior Lathing 9/20/2023 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 9/20/2023 Approved VINCENT HANLEY
Drywall Nailing 1/31/2024 Approved VINCENT HANLEY
Final 1/31/2024 Corrections Issued VINCENT HANLEY
Green Building Final 1/31/2024 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 1/31/2024 SGSOV Approved VINCENT HANLEY
Service/Power Release 1/31/2024 Approved VINCENT HANLEY
Smoke Detectors 1/31/2024 Approved VINCENT HANLEY
Final 7/29/2024 Not Ready for Inspection THOMAS FINNILA
Final 8/8/2024 Corrections Issued THOMAS FINNILA
Final 8/14/2024 OK to Issue CofO THOMAS FINNILA