7827 N CLEON AVE 91352

Certificate Information: 7827 N CLEON AVE 91352

Application / Permit
22010-20000-00097
Plan Check / Job No.
B22VN00276
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 27'-9" X 44'-9" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER WFPP. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 4/8/2022
Issuing Office
Current Status
CofO Issued on 12/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/9/2022 APPLICANT
Assigned to Plan Check Engineer 1/20/2022 ARTIN ZARUKIAN
Corrections Issued 1/22/2022 ARTIN ZARUKIAN
Applicant returned to address corrections 3/25/2022 ARTIN ZARUKIAN
Plan Check Approved 4/8/2022 ARTIN ZARUKIAN
Issued 4/8/2022 APPLICANT
Building Plans Picked Up 4/11/2022 APPLICANT
CofO in Progress 12/1/2022 MATTHEW NELSON
Permit Finaled 12/10/2022 MICHAEL SMITH
CofO Issued 12/10/2022 MICHAEL SMITH
Permit Finaled 12/10/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/25/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/25/2022 CARLOS AGUILERA
Sewer availability Cleared 1/25/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 1/31/2022 CARLOS AGUILERA
Hydrant and Access approval Cleared 3/10/2022 LARRY REDDEN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/13/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 4/18/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 4/18/2022 Partial Approval CHRISTOPHER DELLEFIELD
PLUMBING-Rough 5/3/2022 Partial Approval CHRISTOPHER DELLEFIELD
Sewer 5/3/2022 Approved CHRISTOPHER DELLEFIELD
Gas Test 5/12/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 5/12/2022 Partial Approval CHRISTOPHER DELLEFIELD
Underground Mechanical 5/12/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 5/18/2022 Partial Approval CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 5/20/2022 Corrections Issued CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 5/20/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Rough 5/20/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Rough 5/20/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Rough 5/20/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Verify Sprinkler Sign Off 5/20/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 5/24/2022 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 5/24/2022 Corrections Issued CHRISTOPHER DELLEFIELD
HVAC-Rough 5/24/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 5/24/2022 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 5/26/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 5/26/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 5/26/2022 Conditional Approval CHRISTOPHER DELLEFIELD
HVAC-Rough 5/26/2022 Conditional Approval CHRISTOPHER DELLEFIELD
Insulation 5/26/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 5/26/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Drywall Nailing 5/31/2022 No Access for Inspection CHRISTOPHER DELLEFIELD
Insulation 5/31/2022 No Access for Inspection CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 5/31/2022 No Access for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 6/2/2022 Conditional Approval CHRISTOPHER DELLEFIELD
Drywall Nailing 6/2/2022 Conditional Approval CHRISTOPHER DELLEFIELD
Green Building Rough 6/2/2022 Approved CHRISTOPHER DELLEFIELD
Insulation 6/2/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 6/2/2022 Approved CHRISTOPHER DELLEFIELD
Insulation 6/15/2022 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 6/24/2022 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 6/24/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 6/24/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Final 6/24/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 6/24/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Final 6/24/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 6/24/2022 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 6/24/2022 SGSOV Not Ready CHRISTOPHER DELLEFIELD
Service/Power Release 6/24/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Smoke Detectors 6/24/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 8/3/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Green Building Final 8/3/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Final 8/3/2022 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 8/3/2022 SGSOV Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 8/8/2022 Not Ready for Inspection JENNIFER RABUCHIN
Final 8/8/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Final 8/8/2022 Approved JENNIFER RABUCHIN
HVAC-Final 8/8/2022 Approved JENNIFER RABUCHIN
Service/Power Release 8/8/2022 Not Ready for Inspection JENNIFER RABUCHIN
Final 8/30/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Service/Power Release 8/30/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Final 9/8/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Service/Power Release 9/8/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Final 10/31/2022 Corrections Issued CHRISTOPHE COCHRAN
Service/Power Release 10/31/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 11/28/2022 Partial Inspection MATTHEW NELSON
Service/Power Release 11/28/2022 Partial Inspection MATTHEW NELSON
Final 11/30/2022 OK to Issue CofO MATTHEW NELSON
Service/Power Release 11/30/2022 Approved MATTHEW NELSON