7827 N CLEON AVE 91352
Certificate Information: 7827 N CLEON AVE 91352
- Application / Permit
- 22010-20000-00097
- Plan Check / Job No.
- B22VN00276
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 27'-9" X 44'-9" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK DONE PER WFPP. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
- Permit Issued
- Issued on 4/8/2022
- Issuing Office
- Current Status
- CofO Issued on 12/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/20/2022 | ARTIN ZARUKIAN |
| Corrections Issued | 1/22/2022 | ARTIN ZARUKIAN |
| Applicant returned to address corrections | 3/25/2022 | ARTIN ZARUKIAN |
| Plan Check Approved | 4/8/2022 | ARTIN ZARUKIAN |
| Issued | 4/8/2022 | APPLICANT |
| Building Plans Picked Up | 4/11/2022 | APPLICANT |
| CofO in Progress | 12/1/2022 | MATTHEW NELSON |
| Permit Finaled | 12/10/2022 | MICHAEL SMITH |
| CofO Issued | 12/10/2022 | MICHAEL SMITH |
| Permit Finaled | 12/10/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/25/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/25/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/25/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 1/31/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 3/10/2022 | LARRY REDDEN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/13/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 4/18/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 4/18/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 5/3/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Sewer | 5/3/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Gas Test | 5/12/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 5/12/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 5/12/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 5/18/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 5/20/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 5/20/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 5/20/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 5/20/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 5/20/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Verify Sprinkler Sign Off | 5/20/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 5/24/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 5/24/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 5/24/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 5/26/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 5/26/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 5/26/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Insulation | 5/26/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/26/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 5/31/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Insulation | 5/31/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/31/2022 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 6/2/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 6/2/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 6/2/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 6/2/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 6/2/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 6/15/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 6/24/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 6/24/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 6/24/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 6/24/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 6/24/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 6/24/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 6/24/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 6/24/2022 | SGSOV Not Ready | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 6/24/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 6/24/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 8/3/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Green Building Final | 8/3/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 8/3/2022 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 8/3/2022 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 8/8/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 8/8/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 8/8/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 8/8/2022 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 8/8/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Final | 8/30/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 8/30/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 9/8/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 9/8/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Final | 10/31/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Service/Power Release | 10/31/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 11/28/2022 | Partial Inspection | MATTHEW NELSON |
| Service/Power Release | 11/28/2022 | Partial Inspection | MATTHEW NELSON |
| Final | 11/30/2022 | OK to Issue CofO | MATTHEW NELSON |
| Service/Power Release | 11/30/2022 | Approved | MATTHEW NELSON |