13908 W CALVERT ST 91401
Certificate Information: 13908 W CALVERT ST 91401
- Application / Permit
- 22010-20000-00091
- Plan Check / Job No.
- B22VN00239
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 65'-11" X 38'-0" 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE, 2ND FLOOR DECK, AND ATTACHED TRELLIS. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 6/16/2022
- Issuing Office
- Current Status
- CofO Issued on 1/9/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/7/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2022 | COLIN LOREDO |
| Corrections Issued | 2/17/2022 | COLIN LOREDO |
| Quality Review Completed | 2/24/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 2/24/2022 | APPLICANT |
| Applicant returned to address corrections | 5/24/2022 | COLIN LOREDO |
| Applicant returned to address corrections | 6/14/2022 | COLIN LOREDO |
| Plan Check Approved | 6/16/2022 | COLIN LOREDO |
| Issued | 6/16/2022 | APPLICANT |
| CofO in Progress | 11/15/2023 | RYAN SALAZAR |
| CofO Issued | 1/9/2024 | RUBEN SALAS |
| Permit Finaled | 1/9/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/25/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/25/2022 | CARLOS AGUILERA |
| Permit | Cleared | 2/25/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/25/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 4/13/2022 | JULIAN SUNG |
| Roof/Waste drainage to street | Cleared | 4/18/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 4/27/2022 | RUEL COLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/30/2022 | Partial Approval | RICHARD DOCKUS |
| Sewer | 6/30/2022 | Approved | RICHARD DOCKUS |
| Footing/Foundation/Slab | 7/11/2022 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 8/15/2022 | Partial Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 9/1/2022 | Corrections Issued | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 9/2/2022 | Partial Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2022 | Partial Approval | RICHARD DOCKUS |
| HVAC-Rough | 10/5/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| HVAC-Rough | 10/6/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| ELECTRICAL-Rough | 11/7/2022 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 11/7/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 11/10/2022 | Approved | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2022 | Corrections Issued | JOHN COLEMAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/1/2022 | Partial Approval | JOHN COLEMAN |
| BUILDING-Rough-Frame | 12/14/2022 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2022 | Approved | RYAN SALAZAR |
| Green Building Rough | 12/14/2022 | Not Ready for Inspection | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 12/14/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 12/27/2022 | Not Ready for Inspection | RYAN SALAZAR |
| Insulation | 1/9/2023 | Conditional Approval | RYAN SALAZAR |
| Interior/Exterior Lathing | 1/9/2023 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 1/23/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 1/23/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 1/30/2023 | Approved | RYAN SALAZAR |
| Shower Pan | 1/30/2023 | Approved | RYAN SALAZAR |
| Gas Test | 1/31/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 2/23/2023 | Partial Approval | THOMAS FINNILA |
| Final | 11/14/2023 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 11/14/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 11/14/2023 | SGSOV Approved | RYAN SALAZAR |
| Service/Power Release | 11/14/2023 | Approved | RYAN SALAZAR |
| Smoke Detectors | 11/14/2023 | Approved | RYAN SALAZAR |