5115 N GENESTA AVE 91316
Certificate Information: 5115 N GENESTA AVE 91316
- Application / Permit
- 22010-20000-00075
- Plan Check / Job No.
- B22VN00214
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY (48'-0"x92'-7"), 5857 SQFT SFD W/ATT. 2 CAR GARAGE (400 SQFT) W/NFPA 13D SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 5/24/2022
- Issuing Office
- Current Status
- CofO Issued on 12/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2022 | PETER MOSESIAN |
| Corrections Issued | 2/8/2022 | PETER MOSESIAN |
| Quality Review Completed | 2/11/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 2/15/2022 | APPLICANT |
| Plan Check Approved | 5/24/2022 | PETER MOSESIAN |
| Issued | 5/24/2022 | APPLICANT |
| CofO in Progress | 12/15/2023 | SEAN WIRCH |
| CofO Issued | 12/18/2023 | JOHN JANSON |
| Permit Finaled | 12/18/2023 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/24/2022 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 3/28/2022 | DWIGHT SANKEY |
| Low Impact Development | Cleared | 4/7/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 4/12/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/23/2023 | Approved | JON MCHUGH |
| Footing/Foundation/Slab | 1/23/2023 | Not Ready for Inspection | JON MCHUGH |
| Underground Mechanical | 1/23/2023 | Approved | JON MCHUGH |
| Deputy Reinf. Concrete | 1/25/2023 | Conditional Approval | JON MCHUGH |
| Deputy Steel/Welding | 1/26/2023 | Conditional Approval | JON MCHUGH |
| Deputy Reinf. Concrete | 1/27/2023 | Approved | JON MCHUGH |
| Footing/Foundation/Slab | 1/27/2023 | Approved | JON MCHUGH |
| Deputy Reinf. Concrete | 1/30/2023 | Conditional Approval | JON MCHUGH |
| Deputy Steel/Welding | 2/7/2023 | Conditional Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 2/16/2023 | Partial Approval | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 3/17/2023 | Partial Approval | JON MCHUGH |
| Structural Steel Frame | 3/17/2023 | Approved | JON MCHUGH |
| HVAC-Rough | 3/31/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 4/4/2023 | Approved | JON MCHUGH |
| PLUMBING-Rough | 4/4/2023 | Approved | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2023 | Corrections Issued | JON MCHUGH |
| Gas Test | 4/5/2023 | Not Ready for Inspection | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2023 | Approved | JON MCHUGH |
| Green Building Rough | 4/10/2023 | Not Ready for Inspection | JON MCHUGH |
| Shower Pan | 4/10/2023 | Not Ready for Inspection | JON MCHUGH |
| Verify Sprinkler Sign Off | 4/10/2023 | Partial Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 4/12/2023 | Partial Approval | JON MCHUGH |
| Green Building Rough | 4/12/2023 | Approved | JON MCHUGH |
| Interior/Exterior Lathing | 4/12/2023 | Partial Approval | JON MCHUGH |
| Verify Sprinkler Sign Off | 4/12/2023 | Approved | JON MCHUGH |
| Shower Pan | 4/14/2023 | Approved | JON MCHUGH |
| Insulation | 4/17/2023 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 4/20/2023 | Approved | JON MCHUGH |
| Drywall Nailing | 4/25/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Final | 12/1/2023 | Approved | JEFFREY PARD |
| HVAC-Final | 12/1/2023 | Approved | JEFFREY PARD |
| PLUMBING-Final | 12/1/2023 | Approved | JEFFREY PARD |
| Service/Power Release | 12/13/2023 | Corrections Issued | JEFFREY HARTLINE |
| BUILDING-Rough-Frame | 12/14/2023 | Approved | SEAN WIRCH |
| Final | 12/14/2023 | OK to Issue CofO | SEAN WIRCH |
| Green Building Final | 12/14/2023 | Approved | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 12/14/2023 | SGSOV Approved | SEAN WIRCH |
| Service/Power Release | 12/14/2023 | Approved | SEAN WIRCH |
| Smoke Detectors | 12/14/2023 | Approved | SEAN WIRCH |