19514 W RINALDI ST 91326
Certificate Information: 19514 W RINALDI ST 91326
- Application / Permit
- 22010-20000-00064
- Plan Check / Job No.
- B22VN00188
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (6) Church
- Work Description
- New 1-story classroom building per ZA-1997-0195-CUZ. Classroom building is accesory to church building on site.
- Permit Issued
- Issued on 5/11/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/5/2022 | APPLICANT |
| Disabled Access Plans Picked Up | 2/9/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2022 | LAMAR DAVIS |
| Corrections Issued | 2/18/2022 | LAMAR DAVIS |
| Quality Review Completed | 3/1/2022 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 3/7/2022 | APPLICANT |
| Applicant returned to address corrections | 4/12/2023 | TU HUA |
| Applicant returned to address corrections | 4/21/2023 | TU HUA |
| Plan Check Approved | 5/8/2023 | TU HUA |
| Issued | 5/11/2023 | APPLICANT |
| CofO in Progress | 1/9/2025 | GREGORY POMISH |
| Permit Finaled | 1/13/2025 | JEFFREY DURAN |
| CofO Issued | 1/13/2025 | JEFFREY DURAN |
| Permit Finaled | 1/13/2025 | JEFFREY DURAN |
Permit Application Clearance Information
| Address approval | Cleared | 3/9/2022 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2022 | LEE GUILBEAUX |
| Highway dedication | Cleared | 3/9/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 3/9/2022 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 6/25/2022 | GILBERT URREA |
| DAS Clearance | Cleared | 7/14/2022 | OLLIE CARTER |
| ZA Case | Cleared | 8/22/2022 | JASON CHAN |
| ZA Case | Cleared | 8/22/2022 | JASON CHAN |
| Fire Marshal Fire Life Safety | Cleared | 8/24/2022 | DOMINIQUE MEDINA |
| Green Code | Cleared | 11/15/2022 | MICHAEL AYERS |
| Low Impact Development | Cleared | 12/22/2022 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 3/29/2023 | RYAN KIM |
| Watercourse | Cleared | 3/29/2023 | RYAN KIM |
| GPI Written Notices | Cleared | 5/8/2023 | LAMAR DAVIS |
| Grading Pre-Inspection | Cleared | 5/8/2023 | LAMAR DAVIS |
Contact Information
| Architect | , ; Lic. No.: C38316 | RESEDA, CA 91335 |
| Contractor | Do Right Management Inc.; Lic. No.: 737068-B | 1220 LINDA LANE FULLERTON, CA 92831 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| GREGORY POMISH, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDWIN GREGORYONA, (818) 374-3303 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/9/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Footing/Foundation/Slab | 8/14/2023 | Partial Inspection | JEFFREY FULTON |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2023 | Partial Inspection | JEFFREY FULTON |
| Green Building Rough | 10/31/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Verify Sprinkler Sign Off | 10/31/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Green Building Rough | 11/7/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Verify Sprinkler Sign Off | 11/7/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Wood Frame | 11/7/2023 | Partial Inspection | JEFFREY FULTON |
| Insulation | 11/14/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Insulation | 11/28/2023 | Partial Inspection | JEFFREY FULTON |
| Wood Frame | 11/28/2023 | Partial Inspection | JEFFREY FULTON |
| Green Building Rough | 12/5/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Verify Sprinkler Sign Off | 12/5/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Wood Frame | 12/5/2023 | Partial Approval | JEFFREY FULTON |
| Green Building Rough | 12/12/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Verify Sprinkler Sign Off | 12/12/2023 | Not Ready for Inspection | JEFFREY FULTON |
| Wood Frame | 12/12/2023 | Partial Inspection | JEFFREY FULTON |
| Insulation | 12/19/2023 | Conditional Approval | JEFFREY FULTON |
| Insulation | 1/2/2024 | Partial Inspection | JEFFREY FULTON |
| Insulation | 1/8/2024 | Partial Inspection | JEFFREY FULTON |
| Insulation | 1/8/2024 | Partial Inspection | MELVIN GIRTON |
| Deputy Wood Construction | 1/26/2024 | Conditional Approval | JEFFREY FULTON |
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2024 | Partial Inspection | JEFFREY FULTON |
| Green Building Rough | 1/30/2024 | Not Ready for Inspection | JEFFREY FULTON |
| Verify Sprinkler Sign Off | 1/30/2024 | Not Ready for Inspection | JEFFREY FULTON |
| Interior/Exterior Lathing | 2/29/2024 | Not Ready for Inspection | GREGORY POMISH |
| Interior/Exterior Lathing | 3/1/2024 | Approved | GREGORY POMISH |
| Green Building Rough | 3/28/2024 | Approved | GREGORY POMISH |
| Verify Sprinkler Sign Off | 3/28/2024 | Partial Inspection | GREGORY POMISH |
| Wood Frame | 3/28/2024 | Partial Approval | GREGORY POMISH |
| Insulation | 4/2/2024 | Approved | GREGORY POMISH |
| Drywall Nailing | 4/5/2024 | Partial Approval | GREGORY POMISH |
| Drywall Nailing | 4/11/2024 | Partial Approval | GREGORY POMISH |
| Drywall Nailing | 4/19/2024 | Partial Approval | GREGORY POMISH |
| Interior/Exterior Lathing | 4/25/2024 | Partial Approval | GREGORY POMISH |
| Drywall Nailing | 9/12/2024 | Approved | GREGORY POMISH |
| Final | 9/12/2024 | Corrections Issued | GREGORY POMISH |
| Footing/Foundation/Slab | 9/12/2024 | Approved | GREGORY POMISH |
| Green Building Final | 9/12/2024 | Approved | GREGORY POMISH |
| SGSOV-Seismic Gas S/O Valve | 9/12/2024 | SGSOV Approved | GREGORY POMISH |
| Smoke Detectors | 9/12/2024 | Approved | GREGORY POMISH |
| Verify Sprinkler Sign Off | 9/12/2024 | Approved | GREGORY POMISH |
| Wood Frame | 9/12/2024 | Approved | GREGORY POMISH |
| Final | 9/16/2024 | Partial Inspection | GREGORY POMISH |
| Final | 10/4/2024 | Conditional Approval | GREGORY POMISH |
| Final | 1/8/2025 | OK to Issue CofO | GREGORY POMISH |