360 E GAGE AVE 90003
Certificate Information: 360 E GAGE AVE 90003
- Application / Permit
- 22010-20000-00059
- Plan Check / Job No.
- B22VN00177
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePlan* CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 1/13/2022
- Issuing Office
- Current Status
- CofO Issued on 2/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2022 | SELLA BENYAMIN |
| Corrections Issued | 1/6/2022 | SELLA BENYAMIN |
| Plan Check Approved | 1/11/2022 | SELLA BENYAMIN |
| Issued | 1/13/2022 | APPLICANT |
| CofO in Progress | 2/12/2025 | JOHN QUINTANILLA |
| Permit Finaled | 2/14/2025 | DEROLD HAUFF |
| CofO Issued | 2/14/2025 | DEROLD HAUFF |
| Permit Finaled | 2/14/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/7/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2022 | CINDY QI |
| Sewer availability | Cleared | 1/7/2022 | CINDY QI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/4/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 3/29/2022 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 4/13/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 4/13/2022 | Partial Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 11/17/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 11/17/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 4/5/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2023 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 4/5/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 4/5/2023 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 4/7/2023 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2023 | Partial Approval | LILIANA PORTILLO |
| HVAC-Rough | 4/7/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 4/7/2023 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 4/25/2023 | No Access for Inspection | LILIANA PORTILLO |
| Interior/Exterior Lathing | 4/25/2023 | No Access for Inspection | LILIANA PORTILLO |
| HVAC-Rough | 5/4/2023 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 5/4/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 5/10/2023 | Corrections Issued | MICHAEL LEWIS |
| Green Building Rough | 5/10/2023 | Corrections Issued | MICHAEL LEWIS |
| Shower Pan | 5/10/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 5/19/2023 | Approved | MICHAEL LEWIS |
| Green Building Rough | 5/19/2023 | Approved | MICHAEL LEWIS |
| Insulation | 5/25/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 6/26/2023 | Approved | MICHAEL LEWIS |
| Service/Power Release | 5/29/2024 | Corrections Issued | CRAIG DAVIS |
| Sewer | 7/5/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Sewer | 7/16/2024 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 7/16/2024 | Approved | MICHAEL LEWIS |
| Final | 8/8/2024 | Corrections Issued | MICHAEL LEWIS |
| Green Building Final | 8/8/2024 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 8/8/2024 | SGSOV Not Ready | MICHAEL LEWIS |
| Smoke Detectors | 8/8/2024 | Corrections Issued | MICHAEL LEWIS |
| Service/Power Release | 8/23/2024 | Corrections Issued | MICHAEL LEWIS |
| Gas Test | 11/5/2024 | Approved | ANTHONY RAMOS |
| SGSOV-Seismic Gas S/O Valve | 11/5/2024 | SGSOV Not Ready | ANTHONY RAMOS |
| ELECTRICAL-Final | 12/13/2024 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 12/13/2024 | Partial Inspection | MICHAEL LEWIS |
| Final | 1/21/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 1/21/2025 | SGSOV Approved | JOHN QUINTANILLA |
| Smoke Detectors | 1/21/2025 | Approved | JOHN QUINTANILLA |
| Final | 2/11/2025 | OK to Issue CofO | JOHN QUINTANILLA |