360 E GAGE AVE 90003

Certificate Information: 360 E GAGE AVE 90003

Application / Permit
22010-20000-00059
Plan Check / Job No.
B22VN00177
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePlan* CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 1/13/2022
Issuing Office
Current Status
CofO Issued on 2/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/5/2022 APPLICANT
Assigned to Plan Check Engineer 1/6/2022 SELLA BENYAMIN
Corrections Issued 1/6/2022 SELLA BENYAMIN
Plan Check Approved 1/11/2022 SELLA BENYAMIN
Issued 1/13/2022 APPLICANT
CofO in Progress 2/12/2025 JOHN QUINTANILLA
Permit Finaled 2/14/2025 DEROLD HAUFF
CofO Issued 2/14/2025 DEROLD HAUFF
Permit Finaled 2/14/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/7/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 1/7/2022 CINDY QI
Sewer availability Cleared 1/7/2022 CINDY QI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/4/2022 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 3/29/2022 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 4/13/2022 Approved LILIANA PORTILLO
PLUMBING-Rough 4/13/2022 Partial Approval LILIANA PORTILLO
ELECTRICAL-Rough 11/17/2022 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 11/17/2022 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Rough 4/5/2023 Not Ready for Inspection LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 4/5/2023 Corrections Issued LILIANA PORTILLO
HVAC-Rough 4/5/2023 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 4/5/2023 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 4/7/2023 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 4/7/2023 Partial Approval LILIANA PORTILLO
HVAC-Rough 4/7/2023 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 4/7/2023 Approved LILIANA PORTILLO
HVAC-Rough 4/25/2023 No Access for Inspection LILIANA PORTILLO
Interior/Exterior Lathing 4/25/2023 No Access for Inspection LILIANA PORTILLO
HVAC-Rough 5/4/2023 Approved MICHAEL LEWIS
Interior/Exterior Lathing 5/4/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 5/10/2023 Corrections Issued MICHAEL LEWIS
Green Building Rough 5/10/2023 Corrections Issued MICHAEL LEWIS
Shower Pan 5/10/2023 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 5/19/2023 Approved MICHAEL LEWIS
Green Building Rough 5/19/2023 Approved MICHAEL LEWIS
Insulation 5/25/2023 Approved MICHAEL LEWIS
Drywall Nailing 6/26/2023 Approved MICHAEL LEWIS
Service/Power Release 5/29/2024 Corrections Issued CRAIG DAVIS
Sewer 7/5/2024 Not Ready for Inspection JUSTIN HAWLEY
Sewer 7/16/2024 Approved MICHAEL LEWIS
Underground Mechanical 7/16/2024 Approved MICHAEL LEWIS
Final 8/8/2024 Corrections Issued MICHAEL LEWIS
Green Building Final 8/8/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 8/8/2024 SGSOV Not Ready MICHAEL LEWIS
Smoke Detectors 8/8/2024 Corrections Issued MICHAEL LEWIS
Service/Power Release 8/23/2024 Corrections Issued MICHAEL LEWIS
Gas Test 11/5/2024 Approved ANTHONY RAMOS
SGSOV-Seismic Gas S/O Valve 11/5/2024 SGSOV Not Ready ANTHONY RAMOS
ELECTRICAL-Final 12/13/2024 Approved MICHAEL LEWIS
PLUMBING-Final 12/13/2024 Partial Inspection MICHAEL LEWIS
Final 1/21/2025 Not Ready for Inspection JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 1/21/2025 SGSOV Approved JOHN QUINTANILLA
Smoke Detectors 1/21/2025 Approved JOHN QUINTANILLA
Final 2/11/2025 OK to Issue CofO JOHN QUINTANILLA