12740 W LORNE ST 91605
Certificate Information: 12740 W LORNE ST 91605
- Application / Permit
- 22010-20000-00055
- Plan Check / Job No.
- B22VN00156
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2 STORY ACCESSORY DWELLING UNIT ( 25'-0"X24'-0" ) PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 12/19/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/5/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 2/1/2022 | MOHAMMAD ESMAILI |
| Quality Review Completed | 2/4/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 2/4/2022 | APPLICANT |
| Plan Check Approved | 10/27/2022 | MOHAMMAD ESMAILI |
| Issued | 12/19/2022 | APPLICANT |
| CofO in Progress | 2/14/2024 | GREGG CUMMINGS |
| Permit Finaled | 3/2/2024 | RUBEN SALAS |
| Permit Finaled | 3/2/2024 | RUBEN SALAS |
| CofO Issued | 3/2/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 3/2/2022 | JOHN LIN |
| Sewer availability | Cleared | 3/2/2022 | JOHN LIN |
| Construction near power lines | Cleared | 4/5/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 8/12/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 8/12/2022 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 10/12/2022 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/6/2023 | Partial Approval | GREGG CUMMINGS |
| Pre-Inspection | 6/6/2023 | Approved | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 6/13/2023 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 6/13/2023 | Approved | GREGG CUMMINGS |
| Special/Order Compliance | 6/13/2023 | Corrections Issued | GREGG CUMMINGS |
| Deputy Reinf. Concrete | 6/20/2023 | Conditional Approval | DAVID MATSON |
| Wood Frame | 7/20/2023 | Partial Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 8/22/2023 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 8/22/2023 | Approved | MATTHEW NELSON |
| Green Building Rough | 8/22/2023 | Approved | MATTHEW NELSON |
| HVAC-Rough | 8/22/2023 | Corrections Issued | MATTHEW NELSON |
| MERV13>=Rough | 8/22/2023 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 8/22/2023 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 8/22/2023 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 9/14/2023 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 9/14/2023 | Approved | GREGG CUMMINGS |
| Sewer | 9/14/2023 | Partial Approval | GREGG CUMMINGS |
| Shower Pan | 9/14/2023 | Approved | GREGG CUMMINGS |
| Deputy Wood Construction | 9/15/2023 | Conditional Approval | DAVID MATSON |
| Insulation | 9/25/2023 | Approved | DAVID MATSON |
| Interior/Exterior Lathing | 9/25/2023 | Partial Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 10/3/2023 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 10/3/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 10/3/2023 | Partial Approval | GREGG CUMMINGS |
| Underground Mechanical | 10/3/2023 | Partial Approval | GREGG CUMMINGS |
| Underground Mechanical | 11/21/2023 | Approved | MEL KHACHATOURIAN |
| Final | 1/23/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 1/23/2024 | Approved | GREGG CUMMINGS |
| MERV13>=Final | 1/23/2024 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 1/23/2024 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 1/23/2024 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 1/23/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 1/23/2024 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 2/13/2024 | Approved | GREGG CUMMINGS |
| Final | 2/13/2024 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 2/13/2024 | Approved | GREGG CUMMINGS |
| Service/Power Release | 2/13/2024 | Approved | GREGG CUMMINGS |