12740 W LORNE ST 91605

Certificate Information: 12740 W LORNE ST 91605

Application / Permit
22010-20000-00055
Plan Check / Job No.
B22VN00156
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2 STORY ACCESSORY DWELLING UNIT ( 25'-0"X24'-0" ) PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 12/19/2022
Issuing Office
Valley
Current Status
CofO Issued on 3/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/5/2022 APPLICANT
Assigned to Plan Check Engineer 1/27/2022 MOHAMMAD ESMAILI
Corrections Issued 2/1/2022 MOHAMMAD ESMAILI
Quality Review Completed 2/4/2022 OMID HEDAYAT
Building Plans Picked Up 2/4/2022 APPLICANT
Plan Check Approved 10/27/2022 MOHAMMAD ESMAILI
Issued 12/19/2022 APPLICANT
CofO in Progress 2/14/2024 GREGG CUMMINGS
Permit Finaled 3/2/2024 RUBEN SALAS
Permit Finaled 3/2/2024 RUBEN SALAS
CofO Issued 3/2/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 3/2/2022 JOHN LIN
Sewer availability Cleared 3/2/2022 JOHN LIN
Construction near power lines Cleared 4/5/2022 RIDWAN HARDY
Low Impact Development Cleared 8/12/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 8/12/2022 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 10/12/2022 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/6/2023 Partial Approval GREGG CUMMINGS
Pre-Inspection 6/6/2023 Approved GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 6/13/2023 Approved GREGG CUMMINGS
Footing/Foundation/Slab 6/13/2023 Approved GREGG CUMMINGS
Special/Order Compliance 6/13/2023 Corrections Issued GREGG CUMMINGS
Deputy Reinf. Concrete 6/20/2023 Conditional Approval DAVID MATSON
Wood Frame 7/20/2023 Partial Approval DAVID MATSON
BUILDING-Rough-Frame 8/22/2023 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 8/22/2023 Approved MATTHEW NELSON
Green Building Rough 8/22/2023 Approved MATTHEW NELSON
HVAC-Rough 8/22/2023 Corrections Issued MATTHEW NELSON
MERV13>=Rough 8/22/2023 Approved MATTHEW NELSON
PLUMBING-Rough 8/22/2023 Approved MATTHEW NELSON
Verify Sprinkler Sign Off 8/22/2023 Approved MATTHEW NELSON
BUILDING-Rough-Frame 9/14/2023 Corrections Issued GREGG CUMMINGS
HVAC-Rough 9/14/2023 Approved GREGG CUMMINGS
Sewer 9/14/2023 Partial Approval GREGG CUMMINGS
Shower Pan 9/14/2023 Approved GREGG CUMMINGS
Deputy Wood Construction 9/15/2023 Conditional Approval DAVID MATSON
Insulation 9/25/2023 Approved DAVID MATSON
Interior/Exterior Lathing 9/25/2023 Partial Approval DAVID MATSON
BUILDING-Rough-Frame 10/3/2023 Approved GREGG CUMMINGS
Drywall Nailing 10/3/2023 Approved GREGG CUMMINGS
Interior/Exterior Lathing 10/3/2023 Partial Approval GREGG CUMMINGS
Underground Mechanical 10/3/2023 Partial Approval GREGG CUMMINGS
Underground Mechanical 11/21/2023 Approved MEL KHACHATOURIAN
Final 1/23/2024 Corrections Issued GREGG CUMMINGS
Green Building Final 1/23/2024 Approved GREGG CUMMINGS
MERV13>=Final 1/23/2024 Approved GREGG CUMMINGS
PLUMBING-Final 1/23/2024 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 1/23/2024 SGSOV Approved GREGG CUMMINGS
Service/Power Release 1/23/2024 Not Ready for Inspection GREGG CUMMINGS
Smoke Detectors 1/23/2024 Approved GREGG CUMMINGS
ELECTRICAL-Final 2/13/2024 Approved GREGG CUMMINGS
Final 2/13/2024 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 2/13/2024 Approved GREGG CUMMINGS
Service/Power Release 2/13/2024 Approved GREGG CUMMINGS