8755 N HAZELTINE AVE 91402
Certificate Information: 8755 N HAZELTINE AVE 91402
- Application / Permit
- 22010-20000-00047
- Plan Check / Job No.
- B22VN00131
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER ORDINANCE (1-STORY)
- Permit Issued
- Issued on 8/3/2022
- Issuing Office
- Current Status
- CofO Issued on 9/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2022 | VIVIAN LAO |
| Corrections Issued | 1/7/2022 | CARLOS MONTES |
| Applicant returned to address corrections | 7/14/2022 | VIVIAN LAO |
| Plan Check Approved | 7/20/2022 | VIVIAN LAO |
| Issued | 8/3/2022 | APPLICANT |
| CofO in Progress | 8/11/2023 | GREGG CUMMINGS |
| Permit Finaled | 9/18/2023 | RUBEN SALAS |
| CofO Issued | 9/18/2023 | RUBEN SALAS |
| Permit Finaled | 9/18/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/3/2022 | AMIR KASHFI |
| Roof/Waste drainage to street | Cleared | 2/3/2022 | AMIR KASHFI |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2022 | AMIR KASHFI |
| Sewer availability | Cleared | 2/8/2022 | AMIR KASHFI |
| ZA Case | Cleared | 6/14/2022 | LOUIS ORTEGA |
| Construction near power lines | Cleared | 7/7/2022 | TINA MIRANDA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vartanian,, Albert; Lic. No.: C39989 | PO BOX 857 VERDUGO CITY, CA 91046 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/5/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 10/14/2022 | Corrections Issued | GREGG CUMMINGS |
| Footing/Foundation/Slab | 10/28/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 11/14/2022 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 11/14/2022 | Approved | GREGG CUMMINGS |
| Wood Frame | 12/1/2022 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 12/7/2022 | Partial Approval | GREGG CUMMINGS |
| PLUMBING-Rough | 12/7/2022 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2022 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 12/30/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 1/30/2023 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 1/30/2023 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 2/2/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 2/2/2023 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 2/2/2023 | Partial Approval | GREGG CUMMINGS |
| PLUMBING-Rough | 2/2/2023 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 3/3/2023 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 3/3/2023 | Approved | GREGG CUMMINGS |
| Verify Sprinkler Sign Off | 3/3/2023 | Approved | GREGG CUMMINGS |
| Insulation | 3/9/2023 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 4/5/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 4/5/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 4/5/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Shower Pan | 4/17/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Sewer | 5/16/2023 | Approved | GREGG CUMMINGS |
| Underground Mechanical | 5/16/2023 | Approved | GREGG CUMMINGS |
| Green Building Final | 7/17/2023 | Approved | THOMAS FINNILA |
| HVAC-Final | 7/17/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Smoke Detectors | 7/17/2023 | Approved | THOMAS FINNILA |
| Final | 8/1/2023 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Final | 8/1/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 8/10/2023 | Approved | GREGG CUMMINGS |
| Final | 8/10/2023 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 8/10/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 8/10/2023 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 8/10/2023 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 8/10/2023 | Approved | GREGG CUMMINGS |