13708 W SUNBURST ST 91331

Certificate Information: 13708 W SUNBURST ST 91331

Application / Permit
22010-20000-00033
Plan Check / Job No.
B22VN00080
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 18'-2" X 47'-6" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 6/17/2022
Issuing Office
Current Status
CofO Issued on 12/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/4/2022 APPLICANT
Assigned to Plan Check Engineer 1/21/2022 RAPHAEL ROSAS
Corrections Issued 1/21/2022 RAPHAEL ROSAS
Applicant returned to address corrections 5/1/2022 RAPHAEL ROSAS
Applicant returned to address corrections 5/17/2022 RAPHAEL ROSAS
Plan Check Approved 5/31/2022 RAPHAEL ROSAS
Building Plans Picked Up 6/2/2022 APPLICANT
Issued 6/17/2022 APPLICANT
CofO in Progress 11/14/2024 VINCENT HANLEY
Permit Finaled 12/17/2024 RUBEN SALAS
CofO Issued 12/17/2024 RUBEN SALAS
Permit Finaled 12/17/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/31/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 1/31/2022 JOSE DUARTE-DIAZ
Construction near power lines Cleared 3/21/2022 RIDWAN HARDY
Sewer availability Cleared 3/29/2022 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 6/2/2022 ABDULLAH SADOZAI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/26/2022 Corrections Issued WILLIAM WREN
PLUMBING-Rough 7/28/2022 Corrections Issued GREGG CUMMINGS
Special/Order Compliance 7/28/2022 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 8/2/2022 No Access for Inspection WILLIAM WREN
PLUMBING-Rough 8/5/2022 Approved WILLIAM WREN
Excavation/Setback/Form/Re-Bar 8/10/2022 Corrections Issued GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 8/15/2022 Approved GREGG CUMMINGS
Footing/Foundation/Slab 8/15/2022 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 11/28/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 12/2/2022 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 12/2/2022 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 3/8/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Rough 3/8/2023 Not Ready for Inspection CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 3/9/2023 Approved GREGG CUMMINGS
PLUMBING-Rough 3/9/2023 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 3/16/2023 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 3/16/2023 Partial Approval MICHEL ABAJAN
Green Building Rough 3/16/2023 Approved MICHEL ABAJAN
HVAC-Rough 3/16/2023 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 3/16/2023 Approved MICHEL ABAJAN
Insulation 3/28/2023 Corrections Issued GREGG CUMMINGS
Interior/Exterior Lathing 3/28/2023 Not Ready for Inspection GREGG CUMMINGS
Insulation 3/31/2023 Approved GREGG CUMMINGS
Drywall Nailing 4/14/2023 Approved GREGG CUMMINGS
Interior/Exterior Lathing 4/14/2023 Approved GREGG CUMMINGS
Shower Pan 4/14/2023 Approved GREGG CUMMINGS
ELECTRICAL-Rough 12/26/2023 No Access for Inspection MATTHEW NELSON
Gas Test 12/26/2023 No Access for Inspection MATTHEW NELSON
PLUMBING-Rough 12/26/2023 No Access for Inspection MATTHEW NELSON
Underground Mechanical 12/26/2023 No Access for Inspection MATTHEW NELSON
ELECTRICAL-Final 12/29/2023 Corrections Issued GREGG CUMMINGS
Gas Test 12/29/2023 Not Ready for Inspection GREGG CUMMINGS
Underground Mechanical 12/29/2023 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Final 1/9/2024 Not Ready for Inspection GREGG CUMMINGS
Gas Test 1/9/2024 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Final 1/9/2024 Not Ready for Inspection GREGG CUMMINGS
Underground Mechanical 1/9/2024 Approved GREGG CUMMINGS
Final 2/23/2024 Corrections Issued GREGG CUMMINGS
Green Building Final 2/23/2024 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 2/23/2024 SGSOV Not Ready GREGG CUMMINGS
Service/Power Release 2/23/2024 Not Ready for Inspection GREGG CUMMINGS
Smoke Detectors 2/23/2024 Not Ready for Inspection GREGG CUMMINGS
Final 3/18/2024 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 3/18/2024 SGSOV Not Ready CHRISTOPHER ROJAS
Service/Power Release 3/18/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Smoke Detectors 3/18/2024 Corrections Issued CHRISTOPHER ROJAS
ELECTRICAL-Final 3/29/2024 Not Ready for Inspection GREGG CUMMINGS
Pre-Inspection 3/29/2024 Not Ready for Inspection GREGG CUMMINGS
Final 5/17/2024 Corrections Issued GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 5/17/2024 SGSOV Not Ready GREGG CUMMINGS
Service/Power Release 5/17/2024 Not Ready for Inspection GREGG CUMMINGS
Smoke Detectors 5/17/2024 Not Ready for Inspection GREGG CUMMINGS
Final 6/18/2024 Corrections Issued GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 6/18/2024 SGSOV Not Ready GREGG CUMMINGS
Service/Power Release 6/18/2024 Not Ready for Inspection GREGG CUMMINGS
Smoke Detectors 6/18/2024 Not Ready for Inspection GREGG CUMMINGS
Final 10/23/2024 Not Ready for Inspection GREGG CUMMINGS
HVAC-Final 10/23/2024 Approved GREGG CUMMINGS
PLUMBING-Final 10/23/2024 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 10/23/2024 SGSOV Approved GREGG CUMMINGS
Service/Power Release 10/23/2024 Not Ready for Inspection GREGG CUMMINGS
Smoke Detectors 10/23/2024 Approved GREGG CUMMINGS
Final 11/5/2024 No Access for Inspection GREGG CUMMINGS
Service/Power Release 11/5/2024 No Access for Inspection GREGG CUMMINGS
ELECTRICAL-Final 11/13/2024 Approved VINCENT HANLEY
Final 11/13/2024 OK to Issue CofO VINCENT HANLEY
Service/Power Release 11/13/2024 Approved VINCENT HANLEY