13708 W SUNBURST ST 91331
Certificate Information: 13708 W SUNBURST ST 91331
- Application / Permit
- 22010-20000-00033
- Plan Check / Job No.
- B22VN00080
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 18'-2" X 47'-6" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER WFPP. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
- Permit Issued
- Issued on 6/17/2022
- Issuing Office
- Current Status
- CofO Issued on 12/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/21/2022 | RAPHAEL ROSAS |
| Corrections Issued | 1/21/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 5/1/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 5/17/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 5/31/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 6/2/2022 | APPLICANT |
| Issued | 6/17/2022 | APPLICANT |
| CofO in Progress | 11/14/2024 | VINCENT HANLEY |
| Permit Finaled | 12/17/2024 | RUBEN SALAS |
| CofO Issued | 12/17/2024 | RUBEN SALAS |
| Permit Finaled | 12/17/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/31/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2022 | JOSE DUARTE-DIAZ |
| Construction near power lines | Cleared | 3/21/2022 | RIDWAN HARDY |
| Sewer availability | Cleared | 3/29/2022 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 6/2/2022 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/26/2022 | Corrections Issued | WILLIAM WREN |
| PLUMBING-Rough | 7/28/2022 | Corrections Issued | GREGG CUMMINGS |
| Special/Order Compliance | 7/28/2022 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 8/2/2022 | No Access for Inspection | WILLIAM WREN |
| PLUMBING-Rough | 8/5/2022 | Approved | WILLIAM WREN |
| Excavation/Setback/Form/Re-Bar | 8/10/2022 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 8/15/2022 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 8/15/2022 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 12/2/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 12/2/2022 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 3/8/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 3/8/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 3/9/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 3/9/2023 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 3/16/2023 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2023 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 3/16/2023 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 3/16/2023 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 3/16/2023 | Approved | MICHEL ABAJAN |
| Insulation | 3/28/2023 | Corrections Issued | GREGG CUMMINGS |
| Interior/Exterior Lathing | 3/28/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Insulation | 3/31/2023 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 4/14/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 4/14/2023 | Approved | GREGG CUMMINGS |
| Shower Pan | 4/14/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 12/26/2023 | No Access for Inspection | MATTHEW NELSON |
| Gas Test | 12/26/2023 | No Access for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 12/26/2023 | No Access for Inspection | MATTHEW NELSON |
| Underground Mechanical | 12/26/2023 | No Access for Inspection | MATTHEW NELSON |
| ELECTRICAL-Final | 12/29/2023 | Corrections Issued | GREGG CUMMINGS |
| Gas Test | 12/29/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Underground Mechanical | 12/29/2023 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Final | 1/9/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Gas Test | 1/9/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Final | 1/9/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Underground Mechanical | 1/9/2024 | Approved | GREGG CUMMINGS |
| Final | 2/23/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 2/23/2024 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 2/23/2024 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 2/23/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 2/23/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 3/18/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 3/18/2024 | SGSOV Not Ready | CHRISTOPHER ROJAS |
| Service/Power Release | 3/18/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 3/18/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 3/29/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Pre-Inspection | 3/29/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 5/17/2024 | Corrections Issued | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 5/17/2024 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 5/17/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 5/17/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 6/18/2024 | Corrections Issued | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 6/18/2024 | SGSOV Not Ready | GREGG CUMMINGS |
| Service/Power Release | 6/18/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 6/18/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 10/23/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Final | 10/23/2024 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 10/23/2024 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 10/23/2024 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 10/23/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 10/23/2024 | Approved | GREGG CUMMINGS |
| Final | 11/5/2024 | No Access for Inspection | GREGG CUMMINGS |
| Service/Power Release | 11/5/2024 | No Access for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 11/13/2024 | Approved | VINCENT HANLEY |
| Final | 11/13/2024 | OK to Issue CofO | VINCENT HANLEY |
| Service/Power Release | 11/13/2024 | Approved | VINCENT HANLEY |