7434 N PENFIELD AVE 91306

Certificate Information: 7434 N PENFIELD AVE 91306

Application / Permit
22010-20000-00008
Plan Check / Job No.
B22VN00039
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 21'0"X31'0" ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)AND(d). “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 1/20/2023
Issuing Office
Current Status
CofO Issued on 10/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/3/2022 APPLICANT
Assigned to Plan Check Engineer 1/27/2022 COLIN LOREDO
Corrections Issued 2/3/2022 COLIN LOREDO
Quality Review Completed 2/3/2022 OMID HEDAYAT
Building Plans Picked Up 2/3/2022 APPLICANT
Applicant returned to address corrections 12/5/2022 MARVEL DELACRUZ
Plan Check Approved 12/8/2022 MARVEL DELACRUZ
Issued 1/20/2023 APPLICANT
CofO in Progress 9/11/2023 ALEXANDER HANDY
Permit Finaled 10/19/2023 JOHN JANSON
CofO Issued 10/19/2023 JOHN JANSON
Permit Finaled 10/19/2023 JOHN JANSON

Permit Application Clearance Information

Construction near power lines Cleared 3/29/2022 RIDWAN HARDY
Address approval Cleared 7/11/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 7/11/2022 MEGAN GODINEZ
Sewer availability Cleared 7/11/2022 MEGAN GODINEZ
Hydrant and Access approval Cleared 11/9/2022 KURT CORRAL
Roof/Waste drainage to street Cleared 12/7/2022 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 3/6/2023 Approved ALEXANDER HANDY
Underground Mechanical 3/6/2023 Approved ALEXANDER HANDY
Footing/Foundation/Slab 3/8/2023 Approved ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 3/20/2023 Conditional Approval ALEXANDER HANDY
BUILDING-Rough-Frame 4/20/2023 Corrections Issued ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 4/20/2023 Partial Approval ALEXANDER HANDY
Green Building Rough 4/20/2023 Not Ready for Inspection ALEXANDER HANDY
Rough-Elec/Plmb/HVAC 4/20/2023 Approved ALEXANDER HANDY
Verify Sprinkler Sign Off 4/20/2023 Approved ALEXANDER HANDY
Interior/Exterior Lathing 4/26/2023 Approved ALEXANDER HANDY
Shower Pan 4/26/2023 Approved ALEXANDER HANDY
Underground Mechanical 4/26/2023 Partial Approval ALEXANDER HANDY
Insulation 5/1/2023 Approved JEFFREY BULL
Drywall Nailing 5/4/2023 Approved ALEXANDER HANDY
Green Building Rough 5/4/2023 Approved ALEXANDER HANDY
BUILDING-Rough-Frame 8/8/2023 Approved ALEXANDER HANDY
Final 8/8/2023 Corrections Issued ALEXANDER HANDY
Gas Test 8/8/2023 Approved ALEXANDER HANDY
Green Building Final 8/8/2023 Not Ready for Inspection ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 8/8/2023 SGSOV Not Ready ALEXANDER HANDY
Service/Power Release 8/8/2023 Not Ready for Inspection ALEXANDER HANDY
Smoke Detectors 8/8/2023 Approved ALEXANDER HANDY
Final 9/1/2023 Not Ready for Inspection SEAN WIRCH
Green Building Final 9/1/2023 Approved SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 9/1/2023 SGSOV Approved SEAN WIRCH
Service/Power Release 9/1/2023 Approved SEAN WIRCH
ELECTRICAL-Final 9/8/2023 Approved ALEXANDER HANDY
Final 9/8/2023 OK to Issue CofO ALEXANDER HANDY
HVAC-Final 9/8/2023 Approved ALEXANDER HANDY
PLUMBING-Final 9/8/2023 Approved ALEXANDER HANDY