13114 W HOYT ST 91331

Certificate Information: 13114 W HOYT ST 91331

Application / Permit
22010-20000-00004
Plan Check / Job No.
B21VN18180
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* NEW 1-STORY DETACHED (38'-10" X 39'-11") ADU (1200 SF) WITH ATTACHED PORCH (120 SF) PER LAMC 12.22.A.33(c)-(d). ALL CONSTRUCTION PER WFPP.
Permit Issued
Issued on 10/14/2022
Issuing Office
Current Status
CofO Issued on 9/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/10/2022 APPLICANT
Assigned to Plan Check Engineer 2/10/2022 VIVIAN LAO
Corrections Issued 2/12/2022 VIVIAN LAO
Quality Review Completed 2/14/2022 LIPING TENG
Applicant returned to address corrections 5/5/2022 VIVIAN LAO
Applicant returned to address corrections 8/3/2022 VIVIAN LAO
Plan Check Approved 10/4/2022 VIVIAN LAO
Issued 10/14/2022 APPLICANT
CofO in Progress 9/4/2024 MATTHEW NELSON
Permit Finaled 9/5/2024 DANIEL ORRANTE
CofO Issued 9/5/2024 DANIEL ORRANTE
Permit Finaled 9/5/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 5/23/2022 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 5/23/2022 MEGAN GODINEZ
Sewer availability Cleared 5/23/2022 MEGAN GODINEZ
Low Impact Development Cleared 8/19/2022 ROGELIO CORTES
GPI Written Notices Cleared 9/13/2022 VIVIAN LAO
Grading Pre-Inspection Cleared 9/13/2022 VIVIAN LAO
Roof/Waste drainage to street Cleared 9/15/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Aboufadel,, Nicholas Fadlo; Lic. No.: C50588 4000 PARK NEWPORT SUITE 303      NEWPORT BEACH, CA 92660

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/6/2023 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 1/20/2023 Not Ready for Inspection DAVID ANDERSON
METHANE-Barrier 1/20/2023 Not Ready for Inspection DAVID ANDERSON
METHANE-Subgrade 1/20/2023 Not Ready for Inspection DAVID ANDERSON
Excavation/Setback/Form/Re-Bar 1/23/2023 Approved JOHN COLEMAN
METHANE-Rough 1/23/2023 Approved JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 2/17/2023 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 3/15/2023 Approved MICHEL ABAJAN
ELECTRICAL-Rough 3/15/2023 Approved MICHEL ABAJAN
Green Building Rough 3/15/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 3/15/2023 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 3/15/2023 Approved MICHEL ABAJAN
Interior/Exterior Lathing 4/13/2023 Approved MICHEL ABAJAN
HVAC-Rough 5/23/2023 Approved MICHEL ABAJAN
Insulation 5/30/2023 Approved MICHEL ABAJAN
Drywall Nailing 6/6/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 10/10/2023 SGSOV Not Ready MICHEL ABAJAN
Final 10/12/2023 Not Ready for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 10/12/2023 Conditional Approval MICHEL ABAJAN
Green Building Final 10/12/2023 Approved MICHEL ABAJAN
METHANE-Barrier 10/12/2023 Approved MICHEL ABAJAN
METHANE-Subgrade 10/12/2023 Corrections Issued MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 10/12/2023 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 10/12/2023 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 10/12/2023 Approved MICHEL ABAJAN
Final 11/21/2023 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 11/21/2023 Approved MICHEL ABAJAN
METHANE-Subgrade 11/21/2023 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 11/21/2023 SGSOV Approved MICHEL ABAJAN
Service/Power Release 11/21/2023 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Final 2/22/2024 Approved MICHEL ABAJAN
Final 2/22/2024 Corrections Issued MICHEL ABAJAN
HVAC-Final 2/22/2024 Approved MICHEL ABAJAN
PLUMBING-Final 2/22/2024 Approved MICHEL ABAJAN
Service/Power Release 2/22/2024 Not Ready for Inspection MICHEL ABAJAN
Final 7/26/2024 Not Ready for Inspection MICHEL ABAJAN
Service/Power Release 7/26/2024 Not Ready for Inspection MICHEL ABAJAN
Service/Power Release 8/28/2024 Approved MATTHEW NELSON
Final 9/4/2024 OK to Issue CofO MATTHEW NELSON