937 1/4-3/4 S FEDORA ST 90006

Certificate Information: 937 1/4-3/4 S FEDORA ST 90006

Application / Permit
22010-10003-04315
Plan Check / Job No.
B23LA17981
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPPLEMENTAL PERMIT TO PERMIT#22010-10000-04315 TO CHANGE SCOPE OF WORK FROM CONVERSION OF GARAGE TO TWO STORY ACESSORY DWELLING UNT TO NEW TWO STORY 2-UNIT ADUs PER CA Govt. Code 65852.2(e)(1)(D) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 1/23/2024
Issuing Office
Current Status
Permit Finaled on 11/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/26/2023 APPLICANT
Assigned to Plan Check Engineer 9/28/2023 JAD BASMA
Corrections Issued 10/4/2023 JAD BASMA
Quality Review Completed 10/4/2023 GARO TELMI
Applicant returned to address corrections 11/29/2023 JAD BASMA
Applicant returned to address corrections 12/1/2023 JAD BASMA
Applicant returned to address corrections 12/15/2023 JAD BASMA
Plan Check Approved 1/23/2024 JAD BASMA
Issued 1/23/2024 APPLICANT
Permit Finaled 11/19/2025 WILLIAM SIERRA

Permit Application Clearance Information

Address approval Cleared 10/17/2023 JEANIE LAM
Permit Cleared 10/17/2023 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 10/18/2023 JEANIE LAM
Sewer availability Cleared 10/18/2023 JEANIE LAM
Historic Resource Verification Cleared 10/25/2023 ELIZABETH GALLARDO
Redevelopment Project Area Cleared 10/25/2023 ELIZABETH GALLARDO
Low Impact Development (LID) Cleared 11/9/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 11/13/2023 JEANIE LAM
Trees in Parkway Cleared 11/13/2023 ADALBERTO VERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/2/2024 Not Ready for Inspection RONNIE MINDANAO
Pre-Inspection 2/2/2024 Corrections Issued RONNIE MINDANAO
PLUMBING-Rough 2/20/2024 No Access for Inspection ARTHUR NEGRETE
PLUMBING-Rough 2/23/2024 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 9/4/2024 Not Ready for Inspection WILLIAM SIERRA
Green Building Rough 9/4/2024 Not Ready for Inspection WILLIAM SIERRA
Verify Sprinkler Sign Off 9/4/2024 Not Ready for Inspection WILLIAM SIERRA
BUILDING-Rough-Frame 9/9/2024 Not Ready for Inspection WILLIAM SIERRA
Green Building Rough 9/9/2024 Corrections Issued WILLIAM SIERRA
Verify Sprinkler Sign Off 9/9/2024 Approved WILLIAM SIERRA
ELECTRICAL-Rough 9/12/2024 Corrections Issued WILLIAM SIERRA
Floor/Roof Diaphrgm/Shear Wall 9/12/2024 Approved WILLIAM SIERRA
HVAC-Rough 9/12/2024 Not Ready for Inspection WILLIAM SIERRA
PLUMBING-Rough 9/12/2024 Corrections Issued WILLIAM SIERRA
ELECTRICAL-Rough 9/19/2024 Corrections Issued WILLIAM SIERRA
HVAC-Rough 9/19/2024 Corrections Issued WILLIAM SIERRA
PLUMBING-Rough 9/19/2024 Corrections Issued WILLIAM SIERRA
BUILDING-Rough-Frame 10/3/2024 Approved WILLIAM SIERRA
ELECTRICAL-Rough 10/3/2024 Approved WILLIAM SIERRA
Green Building Rough 10/3/2024 Approved WILLIAM SIERRA
HVAC-Rough 10/3/2024 Approved WILLIAM SIERRA
PLUMBING-Rough 10/3/2024 Approved WILLIAM SIERRA
Insulation 10/25/2024 Approved JOHN QUINTANILLA
Drywall Nailing 11/7/2024 Partial Approval WILLIAM SIERRA
Drywall Nailing 11/12/2024 Corrections Issued WILLIAM SIERRA
Drywall Nailing 11/14/2024 Not Ready for Inspection WILLIAM SIERRA
Drywall Nailing 11/18/2024 Approved WILLIAM SIERRA
Pre-Inspection 7/21/2025 Partial Inspection WILLIAM SIERRA
ELECTRICAL-Final 10/30/2025 Corrections Issued WILLIAM SIERRA
HVAC-Final 10/30/2025 Corrections Issued WILLIAM SIERRA