6211 S RIMPAU BLVD 90043

Certificate Information: 6211 S RIMPAU BLVD 90043

Application / Permit
22010-10002-05739
Plan Check / Job No.
B24LA24581
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan Supplemental 22010-10000-05739 to update plans showing that ADU will be New Construction without using portion (E) garage (demo permit per 22010-10001-05739 . No cahnge to plot plan
Permit Issued
Issued on 10/10/2024
Issuing Office
Current Status
Permit Finaled on 8/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/26/2024 APPLICANT
Assigned to Plan Check Engineer 9/26/2024 FARSHAD ALIMOHAMADI
Corrections Issued 9/27/2024 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 10/7/2024 FARSHAD ALIMOHAMADI
Plan Check Approved 10/10/2024 FARSHAD ALIMOHAMADI
Issued 10/10/2024 APPLICANT
Permit Finaled 8/7/2025 WAYNE REGESTER

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Hernandez, Sotomayor, Daniel; Lic. No.: C93095 15755 SATICOY ST APT#306      VAN NUYS, CA 91406

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/23/2024 Corrections Issued AMIR NAZARIAN
Footing/Foundation/Slab 10/28/2024 Approved AMIR NAZARIAN
Wood Frame 11/8/2024 Corrections Issued AMIR NAZARIAN
Wood Frame 12/5/2024 Approved JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 1/6/2025 Approved JOSE MACIAS
Pre-Inspection 1/6/2025 Corrections Issued JOSE MACIAS
Pre-Inspection 1/21/2025 Corrections Issued BARRY HACHE
Pre-Inspection 1/24/2025 Approved MICHAEL LEWIS
Pre-Inspection 2/3/2025 Partial Approval JOAQUIN GREENOUGH
Final 8/7/2025 Permit Finaled WAYNE REGESTER