368 3/4 N AVENUE 53 90042
Certificate Information: 368 3/4 N AVENUE 53 90042
- Application / Permit
- 22010-10002-03815
- Plan Check / Job No.
- B24LA18304
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPPLEMENTAL PERMIT TO PERMIT 22010-10000-03815 1 - New Window Installation: adding a new window on the west side elevation on both the first and second floors, including all necessary structural modifications. Update T-24 accordingly 2 - Sump Pump Installation: Installation of sump pumps for both the sewer and the Low Impact Development (LID) system No Change on the sq.ft. or the footprint of the building
- Permit Issued
- Issued on 10/18/2024
- Issuing Office
- Current Status
- Permit Finaled on 12/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 9/5/2024 | JAD BASMA |
| Corrections Issued | 9/9/2024 | JAD BASMA |
| Quality Review Completed | 9/11/2024 | GARO TELMI |
| Applicant returned to address corrections | 9/26/2024 | JAD BASMA |
| Plan Check Approved | 10/17/2024 | JAD BASMA |
| No Progress | 10/17/2024 | JAD BASMA |
| Plan Check Approved | 10/17/2024 | JAD BASMA |
| Issued | 10/18/2024 | APPLICANT |
| Permit Finaled | 12/13/2024 | THOMAS LOGRASSO |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |