740 N MICHELTORENA ST 90026
Certificate Information: 740 N MICHELTORENA ST 90026
- Application / Permit
- 22010-10002-00788
- Plan Check / Job No.
- B24LA29399
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan. Supplemental to 22010-10000-00788 to revise scope from CONVERT EXISTING DETACHED GARAGE TO A PORTION OF THE PROPOSED TWO STORY DETACHED ADU WITH A STORAGE ROOM.
- Permit Issued
- Issued on 4/10/2025
- Issuing Office
- Current Status
- Issued on 4/10/2025
Permit Application Status History
| Submitted | 10/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2024 | CRYSTEL MAALOUF |
| Corrections Issued | 11/18/2024 | CRYSTEL MAALOUF |
| Quality Review Completed | 11/27/2024 | HERNAN ARREOLA |
| Applicant returned to address corrections | 3/11/2025 | CRYSTEL MAALOUF |
| Applicant returned to address corrections | 3/20/2025 | CRYSTEL MAALOUF |
| Plan Check Approved | 3/27/2025 | CRYSTEL MAALOUF |
| Issued | 4/10/2025 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/6/2025 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 2/6/2025 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2025 | WALLIE JONG |
| GPI Written Notices | Cleared | 3/24/2025 | CRYSTEL MAALOUF |
| Grading Pre-Inspection | Cleared | 3/24/2025 | RUSSELL BONVOULOIR |
Contact Information
| Architect | Avila,, Tom A; Lic. No.: NA28086 | , |
| Contractor | Owner-Builder | , |
| Engineer | Sadjadi,, Abdulreza; Lic. No.: NA51812 | , |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/20/2025 | Conditional Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 7/11/2025 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 9/3/2025 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Rough | 9/3/2025 | Partial Inspection | FREDDIE RIVERA |
| Insulation | 9/3/2025 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 9/3/2025 | Partial Inspection | FREDDIE RIVERA |
| Sewer | 9/3/2025 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/9/2025 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 9/9/2025 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 9/9/2025 | Partial Approval | FREDDIE RIVERA |
| Insulation | 9/9/2025 | Approved | FREDDIE RIVERA |
| METHANE-Rough | 9/9/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 9/9/2025 | Approved | FREDDIE RIVERA |