1321 N JUNE ST 1-3 90028
Certificate Information: 1321 N JUNE ST 1-3 90028
- Application / Permit
- 22010-10001-05406
- Plan Check / Job No.
- B24LA01409
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- supplemental permit to 22010-10000-05406 to include combo permit for mechanical, electrical, plumbing
- Permit Issued
- Issued on 1/29/2024
- Issuing Office
- Current Status
- Permit Finaled on 12/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Issued | 1/29/2024 | APPLICANT |
| Permit Finaled | 12/12/2024 | BRIAN SULLIVAN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: NA33220 | , |
| Contractor | ; Lic. No.: 398659-B | , |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/31/2024 | Partial Approval | BRIAN SULLIVAN |
| Underground Mechanical | 2/15/2024 | Off-Hour Fees Due | |
| Underground Mechanical | 2/15/2024 | Partial Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 2/16/2024 | Off-Hour Fees Due | |
| Excavation/Setback/Form/Re-Bar | 2/16/2024 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 2/16/2024 | Off-Hour Fees Due | |
| Footing/Foundation/Slab | 2/16/2024 | Partial Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 5/17/2024 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2024 | Corrections Issued | BRIAN SULLIVAN |
| HVAC-Rough | 7/2/2024 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 7/2/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 7/8/2024 | Approved | BRIAN SULLIVAN |
| Shower Pan | 7/8/2024 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 7/10/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 7/10/2024 | Corrections Issued | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 7/18/2024 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 7/18/2024 | Approved | BRIAN SULLIVAN |
| Insulation | 7/30/2024 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 8/5/2024 | Partial Approval | BRIAN SULLIVAN |
| Drywall Nailing | 8/9/2024 | Approved | BRIAN SULLIVAN |
| Sewer | 9/13/2024 | Approved | BRIAN SULLIVAN |
| Underground Mechanical | 9/30/2024 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 10/10/2024 | Corrections Issued | BRIAN SULLIVAN |
| PLUMBING-Final | 10/10/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| Service/Power Release | 10/23/2024 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 12/9/2024 | Approved | BRIAN SULLIVAN |
| Final | 12/9/2024 | Corrections Issued | BRIAN SULLIVAN |
| HVAC-Final | 12/9/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Final | 12/9/2024 | Approved | BRIAN SULLIVAN |
| Smoke Detectors | 12/9/2024 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 12/12/2024 | Approved | BRIAN SULLIVAN |
| Final | 12/12/2024 | Permit Finaled | BRIAN SULLIVAN |
| Gas Test | 12/12/2024 | Approved | BRIAN SULLIVAN |
| HVAC-Final | 12/12/2024 | Approved | BRIAN SULLIVAN |
| PLUMBING-Final | 12/12/2024 | Approved | BRIAN SULLIVAN |