7530 S HARVARD BLVD 90047
Certificate Information: 7530 S HARVARD BLVD 90047
- Application / Permit
- 22010-10000-06707
- Plan Check / Job No.
- B22LA26656
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan CONVERT THE EXISTING 331 SF GARAGE INTO A NEW ADU PER CA Govt. Code 65852.2(e)(1)(A).
- Permit Issued
- Issued on 2/27/2023
- Issuing Office
- Current Status
- CofO Issued on 3/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2023 | ADAM HEGAZI |
| Corrections Issued | 1/9/2023 | ADAM HEGAZI |
| Plan Check Approved | 2/18/2023 | KHUONG TRUONG |
| Issued | 2/27/2023 | APPLICANT |
| CofO in Progress | 3/7/2024 | JOSE MACIAS |
| Permit Finaled | 3/12/2024 | RONALD MYRICK |
| CofO Issued | 3/12/2024 | RONALD MYRICK |
| Permit Finaled | 3/12/2024 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 1/20/2023 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 1/20/2023 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2023 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Tamu,, O C; Lic. No.: C29787 | P O BOX 17083 LONG BEACH, CA 90807 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/12/2023 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 5/12/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 5/19/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 5/19/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Deputy Drilled-In Anchors | 6/1/2023 | Approved | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 6/7/2023 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 6/7/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 6/27/2023 | SGSOV Not Ready | ENRIQUE MIRELES |
| Underground Mechanical | 6/27/2023 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 7/10/2023 | Approved | ENRIQUE MIRELES |
| Sewer | 7/12/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 8/9/2023 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 8/16/2023 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 8/16/2023 | Approved | ENRIQUE MIRELES |
| Wood Frame | 8/16/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 8/21/2023 | SGSOV Not Ready | ENRIQUE MIRELES |
| Wood Frame | 8/21/2023 | Approved | ENRIQUE MIRELES |
| Wood Frame | 8/25/2023 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 8/30/2023 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 9/5/2023 | Approved | ENRIQUE MIRELES |
| Pre-Inspection | 9/5/2023 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 9/5/2023 | SGSOV Not Ready | ENRIQUE MIRELES |
| Gas Test | 9/8/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 9/8/2023 | Corrections Issued | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 9/14/2023 | Corrections Issued | DAVID FEILER |
| Interior/Exterior Lathing | 9/15/2023 | Not Ready for Inspection | DAVID FEILER |
| Interior/Exterior Lathing | 9/18/2023 | Approved | DAVID FEILER |
| Underground Mechanical | 9/27/2023 | Corrections Issued | ENRIQUE MIRELES |
| Underground Mechanical | 10/17/2023 | Corrections Issued | ENRIQUE MIRELES |
| Underground Mechanical | 10/23/2023 | Partial Approval | ENRIQUE MIRELES |
| Underground Mechanical | 10/31/2023 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 11/16/2023 | Corrections Issued | ENRIQUE MIRELES |
| Service/Power Release | 11/17/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Service/Power Release | 12/5/2023 | Approved | ENRIQUE MIRELES |
| Final | 2/22/2024 | Not Ready for Inspection | JOSE MACIAS |
| Green Building Final | 2/22/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 2/22/2024 | SGSOV Not Ready | JOSE MACIAS |
| Smoke Detectors | 2/22/2024 | Not Ready for Inspection | JOSE MACIAS |
| Final | 3/1/2024 | Corrections Issued | JOSE MACIAS |
| Gas Test | 3/1/2024 | Approved | JOSE MACIAS |
| SGSOV-Seismic Gas S/O Valve | 3/1/2024 | SGSOV Approved | JOSE MACIAS |
| Smoke Detectors | 3/1/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Final | 3/6/2024 | Approved | JOSE MACIAS |
| Final | 3/6/2024 | OK to Issue CofO | JOSE MACIAS |
| PLUMBING-Final | 3/6/2024 | Approved | JOSE MACIAS |