1411 W SUMMERLAND ST 90732

Certificate Information: 1411 W SUMMERLAND ST 90732

Application / Permit
22010-10000-06702
Plan Check / Job No.
B22LA26652
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**ePlan** New Detached Accessory Dwelling Unit (ADU) At Rear of The Lot PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 5/2/2023
Issuing Office
Current Status
CofO Corrected on 1/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/1/2023 APPLICANT
Assigned to Plan Check Engineer 1/6/2023 ALFREDO JARA
Corrections Issued 1/8/2023 ALFREDO JARA
Applicant returned to address corrections 2/3/2023 ALFREDO JARA
Applicant returned to address corrections 3/30/2023 EDWIN ESPIN
Plan Check Approved 5/1/2023 EDWIN ESPIN
Issued 5/2/2023 APPLICANT
CofO in Progress 1/13/2025 JOSEPH MCGARRY
Re-Activate Permit 1/14/2025 ANSON MAGLASANG
CofO Issued-Status Void 1/14/2025 ANSON MAGLASANG
Permit Finaled-Status Void 1/14/2025 ANSON MAGLASANG
CofO Corrected 1/14/2025 ANSON MAGLASANG
Permit Finaled 1/14/2025 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 1/31/2023 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 1/31/2023 ERIK BEASLEY
Sewer availability Cleared 1/31/2023 ERIK BEASLEY
Low Impact Development Cleared 3/8/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 3/8/2023 ERIK BEASLEY
Hydrant and Access approval Cleared 3/29/2023 JOHN CONNEALLY
Grading Pre-Inspection Cleared 3/30/2023 KIRK LINKLATER
GPI Written Notices Cleared 5/1/2023 ALFREDO JARA

Contact Information

Contractor Owner-Builder       ,
Engineer Jalalpour,, Mohammad; Lic. No.: S6696 152 DEERFIELD AVE      IRVINE, CA 92606

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/26/2023 Partial Inspection JAMES CHAVEZ
ELECTRICAL-Rough 6/12/2023 Partial Approval JOHN KLARIN
PLUMBING-Rough 6/12/2023 Approved JOHN KLARIN
Pre-Inspection 6/12/2023 Approved JOHN KLARIN
Sewer 6/12/2023 Partial Approval JOHN KLARIN
Underground Mechanical 6/12/2023 Partial Approval JOHN KLARIN
Footing/Foundation/Slab 6/26/2023 Corrections Issued JAMES CHAVEZ
Grounding or Bonding 6/26/2023 Not Ready for Inspection JAMES CHAVEZ
Special/Order Compliance 6/26/2023 Partial Inspection ANSON MAGLASANG
Floor/Roof Diaphrgm/Shear Wall 8/21/2023 Partial Approval JAMES CHAVEZ
ELECTRICAL-Rough 9/6/2023 Corrections Issued ANSON MAGLASANG
Floor/Roof Diaphrgm/Shear Wall 9/6/2023 Corrections Issued ANSON MAGLASANG
PLUMBING-Rough 9/6/2023 Corrections Issued ANSON MAGLASANG
Sewer 9/6/2023 Corrections Issued ANSON MAGLASANG
Wood Frame 9/6/2023 Corrections Issued ANSON MAGLASANG
Floor/Roof Diaphrgm/Shear Wall 9/12/2023 Corrections Issued JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 9/28/2023 Partial Approval JAMES CHAVEZ
Special/Order Compliance 9/28/2023 Corrections Issued JAMES CHAVEZ
Interior/Exterior Lathing 10/11/2023 Not Ready for Inspection JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 10/17/2023 Corrections Issued JAMES CHAVEZ
ELECTRICAL-Rough 10/23/2023 Corrections Issued EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 10/23/2023 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 10/23/2023 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 10/27/2023 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 10/27/2023 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 11/3/2023 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 11/3/2023 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 11/7/2023 Approved JAMES CHAVEZ
PLUMBING-Rough 11/7/2023 Corrections Issued JAMES CHAVEZ
PLUMBING-Rough 11/9/2023 Not Ready for Inspection JAMES CHAVEZ
PLUMBING-Rough 11/14/2023 Approved JAMES CHAVEZ
HVAC-Rough 11/21/2023 Partial Approval JAMES CHAVEZ
HVAC-Rough 12/18/2023 Approved JAMES CHAVEZ
Insulation 12/18/2023 Approved JAMES CHAVEZ
Drywall Nailing 2/8/2024 Approved JAMES CHAVEZ
Interior/Exterior Lathing 2/8/2024 Corrections Issued JAMES CHAVEZ
Interior/Exterior Lathing 2/13/2024 Partial Approval JAMES CHAVEZ
Service/Power Release 3/7/2024 Not Ready for Inspection JAMES CHAVEZ
Drywall Nailing 4/30/2024 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 12/5/2024 Partial Approval ANTHONY EGSON
Final 12/5/2024 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 12/5/2024 Approved ANTHONY EGSON
Green Building Final 12/5/2024 Approved ANTHONY EGSON
Green Building Rough 12/5/2024 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 12/5/2024 SGSOV Not Ready ANTHONY EGSON
Service/Power Release 12/5/2024 Not Ready for Inspection ANTHONY EGSON
Smoke Detectors 12/5/2024 Corrections Issued ANTHONY EGSON
Verify Sprinkler Sign Off 12/5/2024 Not Ready for Inspection ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 12/20/2024 SGSOV Not Ready JOSEPH MCGARRY
BUILDING-Rough-Frame 12/30/2024 Approved JOSEPH MCGARRY
ELECTRICAL-Final 12/30/2024 Approved JOSEPH MCGARRY
Final 12/30/2024 Corrections Issued JOSEPH MCGARRY
HVAC-Final 12/30/2024 Approved JOSEPH MCGARRY
PLUMBING-Final 12/30/2024 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 12/30/2024 SGSOV Not Required JOSEPH MCGARRY
Service/Power Release 12/30/2024 Not Required JOSEPH MCGARRY
Smoke Detectors 12/30/2024 Approved JOSEPH MCGARRY
Verify Sprinkler Sign Off 12/30/2024 Approved JOSEPH MCGARRY
Final 1/13/2025 OK to Issue CofO JOSEPH MCGARRY