1648 3/4 W 254TH ST 90710

Certificate Information: 1648 3/4 W 254TH ST 90710

Application / Permit
22010-10000-06695
Plan Check / Job No.
B22LA26647
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO ADU PER MULTIPLE ADU STATE LAW (1-STORY)
Permit Issued
Issued on 9/26/2023
Issuing Office
Current Status
CofO Issued on 4/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/17/2023 APPLICANT
Assigned to Plan Check Engineer 2/16/2023 CARLOS MONTES
Corrections Issued 2/23/2023 CARLOS MONTES
Quality Review Completed 3/3/2023 GARO TELMI
Applicant returned to address corrections 5/18/2023 CARLOS MONTES
Plan Check Approved 8/4/2023 CARLOS MONTES
Issued 9/26/2023 APPLICANT
CofO in Progress 4/10/2025 EUGENE CASSIDY
Permit Finaled 4/11/2025 ANSON MAGLASANG
CofO Issued 4/11/2025 ANSON MAGLASANG
Permit Finaled 4/11/2025 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 7/3/2023 ANA SORIANO
Sewer availability Cleared 7/3/2023 ANA SORIANO
Eng Process Fee Ord 176,300 Cleared 7/25/2023 ANA SORIANO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/9/2024 Corrections Issued EUGENE CASSIDY
Underground Mechanical 2/13/2024 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 3/21/2024 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 7/8/2024 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 7/29/2024 Corrections Issued EUGENE CASSIDY
Green Building Rough 7/29/2024 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 7/29/2024 Approved EUGENE CASSIDY
ELECTRICAL-Rough 8/2/2024 Not Ready for Inspection EUGENE CASSIDY
HVAC-Rough 8/2/2024 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 8/2/2024 Not Ready for Inspection EUGENE CASSIDY
BUILDING-Rough-Frame 8/20/2024 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 8/20/2024 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 8/20/2024 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 8/20/2024 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 9/16/2024 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 9/16/2024 Approved JOSEPH MCGARRY
Green Building Rough 9/16/2024 Approved JOSEPH MCGARRY
HVAC-Rough 9/16/2024 Conditional Approval JOSEPH MCGARRY
Interior/Exterior Lathing 9/16/2024 Partial Approval JOSEPH MCGARRY
PLUMBING-Rough 9/16/2024 Corrections Issued JOSEPH MCGARRY
BUILDING-Rough-Frame 10/8/2024 Approved EUGENE CASSIDY
Insulation 10/8/2024 Approved EUGENE CASSIDY
PLUMBING-Rough 10/8/2024 Approved EUGENE CASSIDY
Drywall Nailing 10/24/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 11/7/2024 Approved EUGENE CASSIDY
Sewer 12/17/2024 Approved EUGENE CASSIDY
Underground Mechanical 12/23/2024 Approved EUGENE CASSIDY
Underground Mechanical 1/27/2025 Approved EUGENE CASSIDY
Final 3/19/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 3/19/2025 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 3/19/2025 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 3/19/2025 Not Ready for Inspection EUGENE CASSIDY
Final 4/7/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 4/7/2025 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 4/7/2025 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 4/7/2025 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 4/9/2025 Approved EUGENE CASSIDY
Final 4/9/2025 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 4/9/2025 Approved EUGENE CASSIDY
PLUMBING-Final 4/9/2025 Approved EUGENE CASSIDY
Smoke Detectors 4/9/2025 Approved EUGENE CASSIDY