1648 3/4 W 254TH ST 90710
Certificate Information: 1648 3/4 W 254TH ST 90710
- Application / Permit
- 22010-10000-06695
- Plan Check / Job No.
- B22LA26647
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE TO ADU PER MULTIPLE ADU STATE LAW (1-STORY)
- Permit Issued
- Issued on 9/26/2023
- Issuing Office
- Current Status
- CofO Issued on 4/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2023 | CARLOS MONTES |
| Corrections Issued | 2/23/2023 | CARLOS MONTES |
| Quality Review Completed | 3/3/2023 | GARO TELMI |
| Applicant returned to address corrections | 5/18/2023 | CARLOS MONTES |
| Plan Check Approved | 8/4/2023 | CARLOS MONTES |
| Issued | 9/26/2023 | APPLICANT |
| CofO in Progress | 4/10/2025 | EUGENE CASSIDY |
| Permit Finaled | 4/11/2025 | ANSON MAGLASANG |
| CofO Issued | 4/11/2025 | ANSON MAGLASANG |
| Permit Finaled | 4/11/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 7/3/2023 | ANA SORIANO |
| Sewer availability | Cleared | 7/3/2023 | ANA SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2023 | ANA SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/9/2024 | Corrections Issued | EUGENE CASSIDY |
| Underground Mechanical | 2/13/2024 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 3/21/2024 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 7/8/2024 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 7/29/2024 | Corrections Issued | EUGENE CASSIDY |
| Green Building Rough | 7/29/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| METHANE-Rough | 7/29/2024 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 8/2/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| HVAC-Rough | 8/2/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 8/2/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 8/20/2024 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 8/20/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Green Building Rough | 8/20/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| PLUMBING-Rough | 8/20/2024 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 9/16/2024 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 9/16/2024 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 9/16/2024 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 9/16/2024 | Conditional Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 9/16/2024 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 9/16/2024 | Corrections Issued | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 10/8/2024 | Approved | EUGENE CASSIDY |
| Insulation | 10/8/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 10/8/2024 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 10/24/2024 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 11/7/2024 | Approved | EUGENE CASSIDY |
| Sewer | 12/17/2024 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 12/23/2024 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 1/27/2025 | Approved | EUGENE CASSIDY |
| Final | 3/19/2025 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 3/19/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 3/19/2025 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 3/19/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 4/7/2025 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 4/7/2025 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 4/7/2025 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 4/7/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 4/9/2025 | Approved | EUGENE CASSIDY |
| Final | 4/9/2025 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 4/9/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 4/9/2025 | Approved | EUGENE CASSIDY |
| Smoke Detectors | 4/9/2025 | Approved | EUGENE CASSIDY |