503 W 148TH ST 90248

Certificate Information: 503 W 148TH ST 90248

Application / Permit
22010-10000-06679
Plan Check / Job No.
B22LA26631
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Addition of ADU (825sf) above existing garage (361sf) with new patio cover (276sf). PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 7/12/2023
Issuing Office
Current Status
CofO Issued on 5/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2022 APPLICANT
Assigned to Plan Check Engineer 1/27/2023 SAMUEL GONZALEZ
Corrections Issued 1/28/2023 SAMUEL GONZALEZ
Applicant returned to address corrections 4/27/2023 SAMUEL GONZALEZ
Applicant returned to address corrections 6/1/2023 RICARDO RAMIREZ
Plan Check Approved 7/10/2023 RICARDO RAMIREZ
Issued 7/12/2023 APPLICANT
CofO in Progress 5/14/2024 JAMES CHAVEZ
Permit Finaled 5/14/2024 ANSON MAGLASANG
CofO Issued 5/14/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 1/31/2023 KHAING AYE
Roof/Waste drainage to street Cleared 1/31/2023 KHAING AYE
Construction near power lines Cleared 4/11/2023 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 4/20/2023 DAVID VO
Sewer availability Cleared 4/20/2023 DAVID VO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/17/2023 Approved JAMES CHAVEZ
Footing/Foundation/Slab 7/17/2023 Conditional Approval JAMES CHAVEZ
Deputy Drilled-In Anchors 7/18/2023 Conditional Approval JAMES CHAVEZ
ELECTRICAL-Rough 8/7/2023 Not Ready for Inspection JAMES CHAVEZ
Excavation/Setback/Form/Re-Bar 8/7/2023 Approved JAMES CHAVEZ
Footing/Foundation/Slab 8/7/2023 Approved JAMES CHAVEZ
Gas Test 8/7/2023 Partial Approval JAMES CHAVEZ
METHANE-Barrier 8/7/2023 Approved JAMES CHAVEZ
METHANE-Subgrade 8/7/2023 Approved JAMES CHAVEZ
Sewer 8/7/2023 Approved JAMES CHAVEZ
Underground Mechanical 8/7/2023 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 9/18/2023 Partial Approval JAMES CHAVEZ
Green Building Rough 9/18/2023 Not Ready for Inspection JAMES CHAVEZ
MERV13>=Rough 9/18/2023 Not Ready for Inspection JAMES CHAVEZ
METHANE-Rough 9/18/2023 Approved JAMES CHAVEZ
ELECTRICAL-Rough 10/23/2023 Corrections Issued JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 10/23/2023 Partial Approval JAMES CHAVEZ
Gas Test 10/23/2023 Approved JAMES CHAVEZ
PLUMBING-Rough 10/23/2023 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 11/2/2023 Approved JAMES CHAVEZ
ELECTRICAL-Rough 11/2/2023 Approved JAMES CHAVEZ
Green Building Rough 11/2/2023 Approved JAMES CHAVEZ
HVAC-Rough 11/2/2023 Approved JAMES CHAVEZ
Interior/Exterior Lathing 11/2/2023 Partial Approval JAMES CHAVEZ
MERV13>=Rough 11/2/2023 Approved JAMES CHAVEZ
Special/Order Compliance 11/2/2023 Corrections Issued JAMES CHAVEZ
Insulation 11/17/2023 Corrections Issued JAMES CHAVEZ
Insulation 12/12/2023 Approved JOHN KLARIN
Special/Order Compliance 12/12/2023 Approved JOHN KLARIN
Drywall Nailing 12/20/2023 Approved JOHN KLARIN
Final 2/22/2024 Corrections Issued JAMES CHAVEZ
Green Building Final 2/22/2024 Not Ready for Inspection JAMES CHAVEZ
MERV13>=Final 2/22/2024 Approved JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 2/22/2024 SGSOV Not Ready JAMES CHAVEZ
Smoke Detectors 2/22/2024 Approved JAMES CHAVEZ
Final 3/26/2024 Corrections Issued EUGENE CASSIDY
Green Building Final 3/26/2024 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 3/26/2024 SGSOV Approved EUGENE CASSIDY
Final 4/15/2024 Not Ready for Inspection JAMES CHAVEZ
Green Building Final 4/15/2024 Not Ready for Inspection JAMES CHAVEZ
Final 5/13/2024 OK to Issue CofO JAMES CHAVEZ
Green Building Final 5/13/2024 Approved JAMES CHAVEZ