14615 W GREENLEAF ST 91403

Certificate Information: 14615 W GREENLEAF ST 91403

Application / Permit
22010-10000-06678
Plan Check / Job No.
B22LA26630
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY (38'-0"x56'-0"), 2757 SQFT SINGLE FAMILY DWELLING W/ATTACHED 2 CAR GARAGE (345 SQFT) W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 7/20/2023
Issuing Office
Current Status
CofO Issued on 8/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/5/2023 APPLICANT
Assigned to Plan Check Engineer 1/26/2023 PETER MOSESIAN
Corrections Issued 1/30/2023 PETER MOSESIAN
Quality Review Completed 1/31/2023 OMID HEDAYAT
Plan Check Approved 4/27/2023 PETER MOSESIAN
Issued 7/20/2023 APPLICANT
CofO in Progress 7/24/2024 VINCENT HANLEY
Permit Finaled 8/13/2024 DANIEL ORRANTE
CofO Issued 8/13/2024 DANIEL ORRANTE
Permit Finaled 8/13/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/9/2023 CARLOS AGUILERA
Sewer availability Cleared 2/9/2023 CARLOS AGUILERA
Trees in Parkway Cleared 3/1/2023 ADALBERTO VERA
Hydrant and Access approval Cleared 3/23/2023 JOHN CONNEALLY
Stormwater Pollution Mitigatn Cleared 3/30/2023 TOMMY YIN
Permit Cleared 4/1/2023 JOHN LIN
Roof/Waste drainage to street Cleared 4/1/2023 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/22/2023 Not Ready for Inspection MISAEL ESPARZA
Underground Mechanical 8/22/2023 Not Ready for Inspection MISAEL ESPARZA
Footing/Foundation/Slab 8/28/2023 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 8/28/2023 Partial Approval MISAEL ESPARZA
Deputy Reinf. Concrete 8/29/2023 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 9/5/2023 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 9/29/2023 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 11/6/2023 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 12/5/2023 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 12/5/2023 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 12/5/2023 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Rough 12/6/2023 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 12/6/2023 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 12/6/2023 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 12/12/2023 Approved MISAEL ESPARZA
HVAC-Rough 12/12/2023 Approved MISAEL ESPARZA
PLUMBING-Rough 12/12/2023 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 12/22/2023 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 12/22/2023 Approved MISAEL ESPARZA
Green Building Rough 12/22/2023 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 12/22/2023 Approved MISAEL ESPARZA
Wood Frame 12/22/2023 Approved MISAEL ESPARZA
Insulation 1/4/2024 Conditional Approval JOHN COLEMAN
Shower Pan 1/4/2024 Approved JOHN COLEMAN
Drywall Nailing 1/11/2024 Approved MISAEL ESPARZA
Green Building Rough 1/11/2024 Approved MISAEL ESPARZA
Interior/Exterior Lathing 1/11/2024 Not Ready for Inspection MISAEL ESPARZA
Shower Pan 1/11/2024 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 1/12/2024 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 1/16/2024 Partial Approval MISAEL ESPARZA
Interior/Exterior Lathing 1/24/2024 Approved MISAEL ESPARZA
Shower Pan 1/24/2024 Approved MISAEL ESPARZA
ELECTRICAL-Final 6/13/2024 Corrections Issued MISAEL ESPARZA
Gas Test 6/13/2024 Corrections Issued MISAEL ESPARZA
HVAC-Final 6/13/2024 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 6/13/2024 Not Ready for Inspection MISAEL ESPARZA
Service/Power Release 6/13/2024 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 6/26/2024 SGSOV Not Ready JOHN COLEMAN
Gas Test 7/5/2024 Approved JOSE AVILA
HVAC-Final 7/5/2024 Approved JOSE AVILA
PLUMBING-Final 7/5/2024 Corrections Issued JOSE AVILA
Final 7/9/2024 Not Ready for Inspection MISAEL ESPARZA
Gas Test 7/9/2024 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 7/9/2024 Partial Inspection MISAEL ESPARZA
PLUMBING-Final 7/9/2024 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 7/9/2024 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 7/9/2024 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 7/9/2024 Not Ready for Inspection MISAEL ESPARZA
Final 7/18/2024 Corrections Issued MISAEL ESPARZA
Green Building Final 7/18/2024 Approved MISAEL ESPARZA
PLUMBING-Final 7/18/2024 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 7/18/2024 SGSOV Approved MISAEL ESPARZA
Service/Power Release 7/18/2024 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 7/18/2024 Approved MISAEL ESPARZA
ELECTRICAL-Final 7/23/2024 Approved VINCENT HANLEY
Final 7/23/2024 OK to Issue CofO VINCENT HANLEY
Gas Test 7/23/2024 Approved VINCENT HANLEY
HVAC-Final 7/23/2024 Approved VINCENT HANLEY
PLUMBING-Final 7/23/2024 Approved VINCENT HANLEY
Service/Power Release 7/23/2024 Approved VINCENT HANLEY
Wood Frame 7/23/2024 Approved VINCENT HANLEY