1418 S BURNSIDE AVE 90019

Certificate Information: 1418 S BURNSIDE AVE 90019

Application / Permit
22010-10000-06663
Plan Check / Job No.
B22LA26613
Group
Building
Type
Bldg-New
Sub-Type
Commercial
Primary Use
(18) School - elementary or high
Work Description
ePlan: The construction of a new 4,204 sq ft, one-story school building, new outdoor play areas, new restriping of the existing parking lot and general site work. The new school building will be located on a portion of the parcel that is empty and is currently used for parking. Total site that will be demolished for the new building is 6,956 sq ft.
Permit Issued
Issued on 1/13/2024
Issuing Office
Current Status
CofO Issued on 10/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2022 APPLICANT
Assigned to Plan Check Engineer 2/9/2023 TSE MING HUANG
Corrections Issued 2/15/2023 TSE MING HUANG
Quality Review Completed 2/17/2023 EUGENE BARBEAU
Applicant returned to address corrections 7/19/2023 TSE MING HUANG
Applicant returned to address corrections 9/25/2023 TSE MING HUANG
Plan Check Approved 1/12/2024 TSE MING HUANG
Issued 1/13/2024 APPLICANT
CofO in Progress 10/1/2025 MARTIN TAVITIAN
Permit Finaled 10/10/2025 ERNESTO CORRAL
CofO Issued 10/10/2025 ERNESTO CORRAL
Permit Finaled 10/10/2025 ERNESTO CORRAL

Permit Application Clearance Information

Driveway location Cleared 3/21/2023 COLLINS ALLAN
Internal circulation Cleared 3/21/2023 COLLINS ALLAN
Disturb/Remove Protected Trees Cleared 4/11/2023 ADALBERTO VERA
Address approval Cleared 4/13/2023 WALLIE JONG
Trees in Parkway Cleared 5/3/2023 ADALBERTO VERA
Encroachment in public way Cleared 5/9/2023 KATHERINE MENDOZA
Highway dedication Cleared 5/22/2023 TREVOR QUAN
Construction near power lines Cleared 5/24/2023 RIDWAN HARDY
Construction within easement Cleared 5/24/2023 RIDWAN HARDY
Miscellaneous Cleared 6/1/2023 RUBEN VASQUEZ
Eng Process Fee Ord 176,300 Cleared 6/5/2023 WALLIE JONG
Comm Cor/Mini-Mall Cleared 6/6/2023 RUBEN VASQUEZ
Comm Cor/Mini-Mall Cleared 6/6/2023 RUBEN VASQUEZ
Frnt yard landscape/Water mgmt Cleared 6/6/2023 RUBEN VASQUEZ
Miscellaneous Cleared 6/13/2023 DAVID URITA
Prkng lot landscape/Water mgmt Cleared 7/5/2023 DAVID URITA
Green Code Cleared 8/14/2023 Hernan Arreola
Low Impact Development (LID) Cleared 8/23/2023 MARCO SANCHEZ
Sewer availability Cleared 8/29/2023 WALLIE JONG
Fire Marshal Fire Life Safety Cleared 8/30/2023 ANDREW KO
Roof/Waste drainage to street Cleared 9/11/2023 WALLIE JONG
Drainage to Storm Drain Cleared 9/12/2023 TERRY PHAN
DAS Clearance Cleared 9/22/2023 ELIZABETH TOMS
Bicycle Parking Cleared 9/27/2023 KATHERINE MENDOZA
Permit Cleared 11/4/2023 TERRY PHAN
Work Adjacent to Public Way Cleared 12/19/2023 LARRY LEE

Contact Information

Architect Kluger,, Charles Edward; Lic. No.: NA24283       ,
Contractor E P I Construction Inc; Lic. No.: 865616-B       ,
Engineer Hodali,, Ramzi; Lic. No.: NA3552       ,
Engineer Shakya,, Dharma R; Lic. No.: GE2773 55 EL PRISMA      RANCHO SANTA MARGARITA, CA 92688
Landscape Architect Davis,, Timothy F; Lic. No.: LA3353 2825 LITCHFIELD DRIVE      RIVERSIDE, CA 92503

Inspector Information

MARTIN TAVITIAN, (213) 482-7357 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/7/2024 Conditional Approval MARTIN TAVITIAN
METHANE-Barrier 3/7/2024 Approved MARTIN TAVITIAN
METHANE-Subgrade 3/7/2024 Approved MARTIN TAVITIAN
Deputy Reinf. Concrete 3/11/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Reinf. Concrete 3/13/2024 Conditional Approval MICHAEL ROSENBERG
Deputy Drilled-In Anchors 3/14/2024 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 3/15/2024 Partial Approval JACOB MYERS
Reinforced Concrete Frame 3/15/2024 Partial Approval JACOB MYERS
Deputy Reinf. Concrete 3/18/2024 Conditional Approval MICHAEL ROSENBERG
T-Bar Ceiling 8/21/2024 Partial Approval JACOB MYERS
Special/Order Compliance 8/27/2024 Approved EDWIN GREGORYONA
Final 5/30/2025 OK to Issue CofO MARTIN TAVITIAN
Footing/Foundation/Slab 5/30/2025 Approved MARTIN TAVITIAN
Green Building Final 5/30/2025 Approved MARTIN TAVITIAN
Green Building Rough 5/30/2025 Approved MARTIN TAVITIAN
METHANE-Final 5/30/2025 Approved MARTIN TAVITIAN
METHANE-Rough 5/30/2025 Approved MARTIN TAVITIAN
SGSOV-Seismic Gas S/O Valve 5/30/2025 SGSOV Approved MARTIN TAVITIAN
Smoke Detectors 5/30/2025 Approved MARTIN TAVITIAN
Verify Sprinkler Sign Off 5/30/2025 Approved MARTIN TAVITIAN
Wood Frame 5/30/2025 Approved MARTIN TAVITIAN