1333-1335 W 37TH DR 90007

Certificate Information: 1333-1335 W 37TH DR 90007

Application / Permit
22010-10000-06616
Plan Check / Job No.
B22LA26559
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
ADDITION TO (E) 1-STORY SFD TO BE CONNECTED TO REAR (E) 1-STORY SFD WITH ATTACHED GARAGE TO CREATE 4-STORY DUPLEX AND MAJOR REMODEL. NFPA 13R COMPLY WITH DEPARTMENT ORDER effective date 09/03/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 3/21/2024
Issuing Office
Current Status
CofO Issued on 7/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2022 APPLICANT
Assigned to Plan Check Engineer 1/19/2023 VIVIAN LAO
Green Plans Picked Up 1/19/2023 APPLICANT
Corrections Issued 1/27/2023 VIVIAN LAO
Quality Review Completed 2/1/2023 KEN GILL
Building Plans Picked Up 2/8/2023 APPLICANT
Applicant returned to address corrections 3/22/2023 VIVIAN LAO
Disabled Access Plans Picked Up 5/30/2023 APPLICANT
Applicant returned to address corrections 7/12/2023 VIVIAN LAO
Applicant returned to address corrections 1/10/2024 VIVIAN LAO
Applicant returned to address corrections 2/27/2024 VIVIAN LAO
Plan Check Approved 2/27/2024 VIVIAN LAO
No Progress 2/29/2024 VIVIAN LAO
Plan Check Approved 3/6/2024 VIVIAN LAO
Issued 3/21/2024 APPLICANT
CofO in Progress 7/21/2025 SABAS ALONSO
CofO Issued 7/21/2025 DEROLD HAUFF
Permit Finaled 7/21/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/24/2023 TREVOR QUAN
Sewer availability Cleared 4/24/2023 TREVOR QUAN
Hydrant and Access approval Cleared 7/6/2023 KURT CORRAL
Permit Cleared 7/6/2023 JESSICA OPINION
Roof/Waste drainage to street Cleared 7/6/2023 JESSICA OPINION
Frnt yard landscape/Water mgmt Cleared 8/8/2023 YINGSHI HUANG
Green Code Cleared 8/18/2023 MICHAEL MARTINEZ
Address approval Cleared 1/10/2024 AMBER CAMPBELL
DAS Clearance Cleared 1/10/2024 SHINE LIN
Miscellaneous Cleared 1/10/2024 YINGSHI HUANG
Tenant Habitability Plan Cleared 1/11/2024 RICARDO BOHORQUEZ
Low Impact Development Cleared 2/6/2024 ROGELIO CORTES

Contact Information

Contractor Tripalink Builders Llc; Lic. No.: 1118224-B 2905 S VERMONT AVE STE 203      LOS ANGELES, CA 90007
Engineer Shubeck,, Christopher Robert; Lic. No.: C66775 23705 VANOWEN ST 101      WEST HILLS, CA 91307
Engineer Xia,, Ji; Lic. No.: S7144 260 S LOS ROBLES AVE, STE 100      PASADENA, CA 91101

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/6/2024 Partial Inspection SABAS ALONSO
Deputy Reinf. Concrete 8/14/2024 Conditional Approval CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 8/16/2024 Partial Approval CRAIG DAVIS
Footing/Foundation/Slab 8/16/2024 Partial Approval CRAIG DAVIS
Deputy Reinf. Concrete 8/19/2024 Conditional Approval SABAS ALONSO
Underground Mechanical 8/21/2024 Approved MICHAEL LEWIS
Underground Mechanical 8/26/2024 Partial Approval SABAS ALONSO
Deputy Drilled-In Anchors 9/5/2024 Conditional Approval SABAS ALONSO
Deputy Reinf. Concrete 9/10/2024 Conditional Approval SABAS ALONSO
Footing/Foundation/Slab 9/11/2024 Approved SABAS ALONSO
Sewer 9/11/2024 Approved SABAS ALONSO
Underground Mechanical 9/11/2024 Partial Approval SABAS ALONSO
Deputy Reinf. Concrete 9/13/2024 Conditional Approval SABAS ALONSO
Deputy Wood Construction 10/8/2024 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 10/9/2024 Corrections Issued SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 10/22/2024 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 11/1/2024 Partial Approval JOAQUIN GREENOUGH
Deputy Wood Construction 11/21/2024 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 11/22/2024 Corrections Issued SABAS ALONSO
Insulation 12/11/2024 Partial Approval SABAS ALONSO
Deputy Wood Construction 12/23/2024 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 1/13/2025 Partial Approval SABAS ALONSO
ELECTRICAL-Rough 2/6/2025 Approved SABAS ALONSO
HVAC-Rough 2/6/2025 Approved SABAS ALONSO
PLUMBING-Rough 2/6/2025 Approved SABAS ALONSO
Verify Sprinkler Sign Off 2/6/2025 Approved SABAS ALONSO
BUILDING-Rough-Frame 2/27/2025 Conditional Approval SABAS ALONSO
Green Building Rough 2/27/2025 Approved SABAS ALONSO
Interior/Exterior Lathing 2/27/2025 Partial Approval SABAS ALONSO
Shower Pan 2/27/2025 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 3/6/2025 Approved SABAS ALONSO
Insulation 3/6/2025 Approved SABAS ALONSO
Shower Pan 3/6/2025 Partial Approval SABAS ALONSO
Drywall Nailing 4/4/2025 Corrections Issued ANTHONY RAMOS
Interior/Exterior Lathing 4/4/2025 Approved ANTHONY RAMOS
Shower Pan 4/4/2025 Approved ANTHONY RAMOS
Drywall Nailing 4/9/2025 Approved ANTHONY RAMOS
Underground Mechanical 5/5/2025 Approved SABAS ALONSO
ELECTRICAL-Final 7/9/2025 Approved SABAS ALONSO
Final 7/9/2025 Corrections Issued SABAS ALONSO
Green Building Final 7/9/2025 Approved SABAS ALONSO
HVAC-Final 7/9/2025 Approved SABAS ALONSO
PLUMBING-Final 7/9/2025 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 7/9/2025 SGSOV Approved SABAS ALONSO
Service/Power Release 7/9/2025 Approved SABAS ALONSO
Smoke Detectors 7/9/2025 Approved SABAS ALONSO
Final 7/11/2025 OK to Issue CofO SABAS ALONSO
Gas Test 7/11/2025 Approved SABAS ALONSO