120 E 65TH ST 90003

Certificate Information: 120 E 65TH ST 90003

Application / Permit
22010-10000-06583
Plan Check / Job No.
B22LA26465
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached ADU at rear of the lot per engineer details (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
Permit Issued
Issued on 10/24/2023
Issuing Office
Current Status
CofO Issued on 9/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/28/2022 APPLICANT
Assigned to Plan Check Engineer 1/5/2023 AUNG SOE
Corrections Issued 1/9/2023 AUNG SOE
Building Plans Picked Up 1/17/2023 APPLICANT
Applicant returned to address corrections 10/3/2023 VICTOR CHEN
Applicant returned to address corrections 10/12/2023 DANIEL SANJUAN
Plan Check Approved 10/13/2023 MICHAEL LANZONE
Issued 10/24/2023 APPLICANT
CofO in Progress 9/16/2024 MICHAEL LEWIS
CofO Issued 9/17/2024 DEROLD HAUFF
Permit Finaled 9/17/2024 DEROLD HAUFF

Permit Application Clearance Information

ZI Cleared 1/18/2023 MAYELA VILLA
Address approval Cleared 8/8/2023 HUGO LOPEZ
Community Plan Implem. Overlay Cleared 8/8/2023 HUGO LOPEZ
Roof/Waste drainage to street Cleared 8/8/2023 HUGO LOPEZ
Eng Process Fee Ord 176,300 Cleared 8/9/2023 HUGO LOPEZ
Sewer availability Cleared 8/9/2023 HUGO LOPEZ
Community Plan Implem. Overlay Cleared 8/14/2023 ADALBERTO VERA
Hold Cleared 8/31/2023 CARMEN MERAZ
Community Plan Implem. Overlay Cleared 9/6/2023 HELEN JADALI
Low Impact Development Cleared 9/6/2023 MARCO SANCHEZ
Community Plan Implem. Overlay Cleared 9/14/2023 TINA MIRANDA
Construction near power lines Cleared 9/14/2023 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 12/11/2023 Approved MICHAEL LEWIS
Underground Mechanical 12/11/2023 Approved MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 12/16/2023 Approved FREDDIE RIVERA
Footing/Foundation/Slab 12/16/2023 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 1/2/2024 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/4/2024 Approved SABAS ALONSO
ELECTRICAL-Rough 1/23/2024 Corrections Issued MICHAEL LEWIS
HVAC-Rough 1/23/2024 Corrections Issued MICHAEL LEWIS
Interior/Exterior Lathing 1/23/2024 Approved MICHAEL LEWIS
PLUMBING-Rough 1/23/2024 Corrections Issued MICHAEL LEWIS
BUILDING-Rough-Frame 1/31/2024 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Rough 1/31/2024 Partial Inspection MICHAEL LEWIS
Green Building Rough 1/31/2024 Approved MICHAEL LEWIS
HVAC-Rough 1/31/2024 Approved MICHAEL LEWIS
PLUMBING-Rough 1/31/2024 Approved MICHAEL LEWIS
Verify Sprinkler Sign Off 1/31/2024 Approved MICHAEL LEWIS
Insulation 2/6/2024 Approved MICHAEL LEWIS
Drywall Nailing 2/14/2024 Approved MICHAEL LEWIS
Interior/Exterior Lathing 2/14/2024 Approved MICHAEL LEWIS
Service/Power Release 3/21/2024 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 3/21/2024 Approved ALEJANDRO DE ARTOLA
Pre-Inspection 5/28/2024 Corrections Issued CRAIG DAVIS
BUILDING-Rough-Frame 7/10/2024 Approved MICHAEL LEWIS
Final 7/10/2024 Corrections Issued MICHAEL LEWIS
Green Building Final 7/10/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 7/10/2024 SGSOV Not Required MICHAEL LEWIS
Service/Power Release 7/10/2024 Not Ready for Inspection MICHAEL LEWIS
Smoke Detectors 7/10/2024 Approved MICHAEL LEWIS
Final 9/13/2024 OK to Issue CofO MICHAEL LEWIS
Service/Power Release 9/13/2024 Approved MICHAEL LEWIS