1337 N RIDGECREST DR 90210

Certificate Information: 1337 N RIDGECREST DR 90210

Application / Permit
22010-10000-06572
Plan Check / Job No.
B22LA26445
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
NEW ONE STORY ACCESSORY LIVING QUARTERS NFPA13D SPRINKLERED THROUGH OUT
Permit Issued
Issued on 8/13/2024
Issuing Office
West Los Angeles
Current Status
Issued on 8/13/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/28/2022 APPLICANT
Assigned to Plan Check Engineer 2/2/2023 JAD BASMA
Corrections Issued 2/6/2023 JAD BASMA
Quality Review Completed 2/21/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 6/13/2023 JAD BASMA
Applicant returned to address corrections 6/13/2024 JAD BASMA
Plan Check Approved 8/8/2024 JAD BASMA
Issued 8/13/2024 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 9/19/2023 LAVEON RIDER
Landscape for retaining wall Cleared 10/12/2023 JAZMIN ROQUE
BHO/Hillside ordinance Cleared 12/4/2023 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 12/4/2023 HISASHI KOBAYAKAWA
BHO/Hillside ordinance Cleared 6/18/2024 DINAH GARIN
Sewer availability Cleared 6/18/2024 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 7/8/2024 DINAH GARIN
Stormwater Pollution Mitigatn Cleared 7/12/2024 LUIS LUVANO
Roof/Waste drainage to street Cleared 7/16/2024 VLADIMIR ARUTYUNYAN
GPI Written Notices Cleared 7/25/2024 JAD BASMA
Grading Pre-Inspection Cleared 7/25/2024 JAD BASMA
Haul Route Cleared 7/25/2024 JAD BASMA
BHO/Hillside ordinance Cleared 7/30/2024 DINAH GARIN
BHO/Hillside ordinance Cleared 7/30/2024 DINAH GARIN

Contact Information

Contractor Mc Coy Peter Construction; Lic. No.: 493592-B 9777 WILSHIRE BLVD #902      BEVERLY HILLS, CA 90212

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/14/2026 Partial Inspection CRAIG VAUGHAN
Deputy Grading 1/20/2026 Conditional Approval BRIAN SULLIVAN
Deputy Grading 1/21/2026 Conditional Approval BRIAN SULLIVAN
Deputy Grading 1/22/2026 Conditional Approval DAVID WILLIAMS
Deputy Grading 1/26/2026 Conditional Approval DAVID WILLIAMS
Piling/Pier/Caisson 2/4/2026 Corrections Issued DAVID WILLIAMS
Piling/Pier/Caisson 2/5/2026 Partial Approval DAVID WILLIAMS
Excavation/Setback/Form/Re-Bar 3/3/2026 Partial Approval DAVID WILLIAMS
Deputy Grading 3/4/2026 Conditional Approval BRIAN SULLIVAN
Deputy Grading 3/5/2026 Conditional Approval DAVID WILLIAMS
Deputy Reinf. Concrete 3/5/2026 Conditional Approval CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 3/5/2026 Partial Approval DAVID WILLIAMS
Excavation/Setback/Form/Re-Bar 3/9/2026 Partial Approval DAVID WILLIAMS
Deputy Grading 3/11/2026 Conditional Approval CRAIG VAUGHAN
Footing/Foundation/Slab 5/8/2026 Not Ready for Inspection BRENDAN MORELLI
Footing/Foundation/Slab 5/13/2026 Partial Approval BRENDAN MORELLI