5720 S DENKER AVE 90062

Certificate Information: 5720 S DENKER AVE 90062

Application / Permit
22010-10000-06566
Plan Check / Job No.
B22LA23269
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan PROPOSED 2 STORY 36' X 18' ADU (Middle Building)
Permit Issued
Issued on 6/26/2023
Issuing Office
Current Status
CofO Issued on 12/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/17/2022 APPLICANT
Assigned to Plan Check Engineer 12/15/2022 CRYSTEL MAALOUF
Corrections Issued 12/29/2022 CRYSTEL MAALOUF
Quality Review Completed 1/11/2023 GARO TELMI
Applicant returned to address corrections 6/14/2023 CRYSTEL MAALOUF
Plan Check Approved 6/15/2023 CRYSTEL MAALOUF
Issued 6/26/2023 APPLICANT
CofO in Progress 12/13/2024 SABAS ALONSO
Permit Finaled 12/14/2024 DEROLD HAUFF
CofO Issued 12/14/2024 DEROLD HAUFF
Permit Finaled 12/14/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/9/2023 WALLIE JONG
Sewer availability Cleared 2/13/2023 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 2/22/2023 WALLIE JONG
Community Plan Implem. Overlay Cleared 3/10/2023 RAFAEL FONTES
Low Impact Development Cleared 4/17/2023 ROGELIO CORTES
Roof/Waste drainage to street Cleared 4/18/2023 WALLIE JONG
Hold Cleared 11/28/2023 CARMEN MERAZ

Contact Information

Contractor California Realty & Investment Group Inc; Lic. No.: 929543-B       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 11/28/2023 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 12/8/2023 Approved SABAS ALONSO
Footing/Foundation/Slab 12/8/2023 Approved SABAS ALONSO
HVAC-Rough 12/8/2023 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 12/8/2023 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 12/15/2023 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 12/15/2023 Approved SABAS ALONSO
Green Building Rough 12/15/2023 Not Ready for Inspection SABAS ALONSO
HVAC-Rough 12/15/2023 Approved SABAS ALONSO
PLUMBING-Rough 12/15/2023 Approved SABAS ALONSO
Verify Sprinkler Sign Off 12/15/2023 Not Ready for Inspection SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 1/18/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 1/18/2024 Partial Approval SABAS ALONSO
Shower Pan 1/18/2024 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 1/19/2024 Approved SABAS ALONSO
Green Building Rough 1/19/2024 Approved SABAS ALONSO
Verify Sprinkler Sign Off 1/19/2024 Approved SABAS ALONSO
Insulation 1/24/2024 Approved SABAS ALONSO
Drywall Nailing 2/9/2024 Approved SABAS ALONSO
ELECTRICAL-Final 7/22/2024 Not Ready for Inspection SABAS ALONSO
Final 7/22/2024 Corrections Issued SABAS ALONSO
Gas Test 7/22/2024 Not Ready for Inspection SABAS ALONSO
Green Building Final 7/22/2024 Corrections Issued SABAS ALONSO
HVAC-Final 7/22/2024 Not Ready for Inspection SABAS ALONSO
PLUMBING-Final 7/22/2024 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 7/22/2024 SGSOV Not Ready SABAS ALONSO
Service/Power Release 7/22/2024 Not Ready for Inspection SABAS ALONSO
Smoke Detectors 7/22/2024 Approved SABAS ALONSO
ELECTRICAL-Final 9/6/2024 Not Ready for Inspection SABAS ALONSO
Final 9/6/2024 Corrections Issued SABAS ALONSO
Green Building Final 9/6/2024 Approved SABAS ALONSO
HVAC-Final 9/6/2024 Approved SABAS ALONSO
PLUMBING-Final 9/6/2024 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 9/6/2024 SGSOV Not Ready SABAS ALONSO
Service/Power Release 9/6/2024 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Final 10/3/2024 Approved SABAS ALONSO
Final 10/3/2024 Not Ready for Inspection SABAS ALONSO
HVAC-Final 10/3/2024 Approved SABAS ALONSO
PLUMBING-Final 10/3/2024 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 10/3/2024 SGSOV Not Ready SABAS ALONSO
Service/Power Release 10/3/2024 Not Ready for Inspection SABAS ALONSO
Final 11/1/2024 Not Ready for Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 11/1/2024 SGSOV Not Ready JOAQUIN GREENOUGH
Service/Power Release 11/1/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Final 12/12/2024 OK to Issue CofO SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 12/12/2024 SGSOV Approved SABAS ALONSO
Service/Power Release 12/12/2024 Approved SABAS ALONSO