5720 S DENKER AVE 90062
Certificate Information: 5720 S DENKER AVE 90062
- Application / Permit
- 22010-10000-06566
- Plan Check / Job No.
- B22LA23269
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan PROPOSED 2 STORY 36' X 18' ADU (Middle Building)
- Permit Issued
- Issued on 6/26/2023
- Issuing Office
- Current Status
- CofO Issued on 12/14/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2022 | CRYSTEL MAALOUF |
| Corrections Issued | 12/29/2022 | CRYSTEL MAALOUF |
| Quality Review Completed | 1/11/2023 | GARO TELMI |
| Applicant returned to address corrections | 6/14/2023 | CRYSTEL MAALOUF |
| Plan Check Approved | 6/15/2023 | CRYSTEL MAALOUF |
| Issued | 6/26/2023 | APPLICANT |
| CofO in Progress | 12/13/2024 | SABAS ALONSO |
| Permit Finaled | 12/14/2024 | DEROLD HAUFF |
| CofO Issued | 12/14/2024 | DEROLD HAUFF |
| Permit Finaled | 12/14/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/9/2023 | WALLIE JONG |
| Sewer availability | Cleared | 2/13/2023 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2023 | WALLIE JONG |
| Community Plan Implem. Overlay | Cleared | 3/10/2023 | RAFAEL FONTES |
| Low Impact Development | Cleared | 4/17/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 4/18/2023 | WALLIE JONG |
| Hold | Cleared | 11/28/2023 | CARMEN MERAZ |
Contact Information
| Contractor | California Realty & Investment Group Inc; Lic. No.: 929543-B | , |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2023 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 12/8/2023 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 12/8/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 12/8/2023 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 12/8/2023 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 12/15/2023 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 12/15/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 12/15/2023 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Rough | 12/15/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 12/15/2023 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 12/15/2023 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 1/18/2024 | Partial Approval | SABAS ALONSO |
| Shower Pan | 1/18/2024 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 1/19/2024 | Approved | SABAS ALONSO |
| Green Building Rough | 1/19/2024 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 1/19/2024 | Approved | SABAS ALONSO |
| Insulation | 1/24/2024 | Approved | SABAS ALONSO |
| Drywall Nailing | 2/9/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 7/22/2024 | Not Ready for Inspection | SABAS ALONSO |
| Final | 7/22/2024 | Corrections Issued | SABAS ALONSO |
| Gas Test | 7/22/2024 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Final | 7/22/2024 | Corrections Issued | SABAS ALONSO |
| HVAC-Final | 7/22/2024 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Final | 7/22/2024 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 7/22/2024 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 7/22/2024 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 7/22/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 9/6/2024 | Not Ready for Inspection | SABAS ALONSO |
| Final | 9/6/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 9/6/2024 | Approved | SABAS ALONSO |
| HVAC-Final | 9/6/2024 | Approved | SABAS ALONSO |
| PLUMBING-Final | 9/6/2024 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 9/6/2024 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 9/6/2024 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Final | 10/3/2024 | Approved | SABAS ALONSO |
| Final | 10/3/2024 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Final | 10/3/2024 | Approved | SABAS ALONSO |
| PLUMBING-Final | 10/3/2024 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 10/3/2024 | SGSOV Not Ready | SABAS ALONSO |
| Service/Power Release | 10/3/2024 | Not Ready for Inspection | SABAS ALONSO |
| Final | 11/1/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 11/1/2024 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Service/Power Release | 11/1/2024 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 12/12/2024 | OK to Issue CofO | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 12/12/2024 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 12/12/2024 | Approved | SABAS ALONSO |