522 N CHAPALA DR 90272
Certificate Information: 522 N CHAPALA DR 90272
- Application / Permit
- 22010-10000-06552
- Plan Check / Job No.
- B22LA26397
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan New (2) STORY GROUND UP CONSTRUCTION WITH BASEMENT. NEW CURB CUT, EXTERIOR HARDSCAPE, AND LANDSCAPING.
- Permit Issued
- Issued on 8/17/2023
- Issuing Office
- Current Status
- Issued on 8/17/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/28/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/2/2023 | NGHI SU |
| Corrections Issued | 2/4/2023 | NGHI SU |
| Quality Review Completed | 2/24/2023 | FARUK SEZER |
| Applicant returned to address corrections | 3/28/2023 | NGHI SU |
| Applicant returned to address corrections | 7/28/2023 | NGHI SU |
| Plan Check Approved | 8/11/2023 | NGHI SU |
| Issued | 8/17/2023 | APPLICANT |
Permit Application Clearance Information
| ZI | Cleared | 2/14/2023 | LOUIS ORTEGA |
| Eng Process Fee Ord 176,300 | Cleared | 2/21/2023 | JENSON LEE |
| Sewer availability | Cleared | 2/21/2023 | JENSON LEE |
| Hydrant and Access approval | Cleared | 4/1/2023 | JOHN CONNEALLY |
| Stormwater Pollution Mitigatn | Cleared | 6/20/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 7/13/2023 | DARIN LAM |
| Low Impact Development (LID) | Cleared | 7/17/2023 | ORVAL HERNANDEZ-MARCI |
| GPI Written Notices | Cleared | 7/28/2023 | NGHI SU |
| Grading Pre-Inspection | Cleared | 7/28/2023 | NGHI SU |
| Excavation more than 5-ft deep | Cleared | 8/8/2023 | CALOSHA APPROVED |
Contact Information
| Architect | , ; Lic. No.: C40514 | LOS ANGELES, CA 90037 |
| Contractor | Grossman Construction & Development Inc; Lic. No.: 1052191-B | , |
| Engineer | Barr,, Joseph Daniel; Lic. No.: C70708 | 1185 HERITAGE FARM RD HICKORY, NC 28601 |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22814 DOLOROSA ST WOODLAND HILLS, CA 91367 |
| Engineer | White,, William Michael; Lic. No.: C62111 | 19619 MATHILDE LN SAUGUS, CA 91350 |
| Engineer | Yamashita,, Mark Alan; Lic. No.: L7155 | 6718 BIANCA AVE LAKE BALBOA, CA 91406 |
| Geologist | Miller,, Jonathan Steven; Lic. No.: EG2391 | 24736 CALVERT STREET WOODLAND HILLS, CA 91367 |
| Landscape Architect | Biesecker,, Craig Roy; Lic. No.: LA6522 | 520 S CORONADO ST APT B LOS ANGELES, CA 90057 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/8/2023 | Partial Approval | EVAN COOPER |
| Pre-Inspection | 9/8/2023 | Approved | EVAN COOPER |
| PLUMBING-Rough | 9/20/2023 | Partial Approval | EVAN COOPER |
| Sewer | 9/20/2023 | Not Ready for Inspection | EVAN COOPER |
| Footing/Foundation/Slab | 10/3/2023 | Partial Approval | EVAN COOPER |
| Deputy Reinf. Concrete | 10/10/2023 | No Access for Inspection | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 10/25/2023 | Partial Approval | EVAN COOPER |
| Reinforced Concrete Frame | 10/25/2023 | Partial Approval | EVAN COOPER |
| Deputy Shotcrete | 10/27/2023 | Conditional Approval | EVAN COOPER |
| Deputy Shotcrete | 10/30/2023 | Conditional Approval | EVAN COOPER |
| Footing/Foundation/Slab | 11/14/2023 | Partial Approval | EVAN COOPER |
| Deputy Reinf. Concrete | 11/16/2023 | Conditional Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 12/6/2023 | Partial Approval | ARAM AVEDISIAN |
| Deputy Drilled-In Anchors | 12/13/2023 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 12/14/2023 | Approved | EVAN COOPER |
| Deputy Reinf. Concrete | 12/15/2023 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2024 | Partial Approval | EVAN COOPER |
| Wood Frame | 1/23/2024 | Not Ready for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 3/4/2024 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2024 | Partial Approval | EVAN COOPER |
| Green Building Rough | 3/4/2024 | Not Ready for Inspection | EVAN COOPER |
| Verify Sprinkler Sign Off | 3/4/2024 | Not Ready for Inspection | EVAN COOPER |
| Wood Frame | 3/4/2024 | Not Ready for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 6/25/2024 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 7/1/2024 | Corrections Issued | EVAN COOPER |
| Green Building Rough | 7/1/2024 | Not Ready for Inspection | EVAN COOPER |
| Verify Sprinkler Sign Off | 7/1/2024 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 8/16/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2024 | Partial Approval | CARLOS MATAMOROS |
| Green Building Rough | 8/16/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 8/16/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 8/26/2024 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2024 | Partial Approval | EVAN COOPER |
| Green Building Rough | 8/26/2024 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 8/26/2024 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 8/26/2024 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 9/3/2024 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 10/1/2024 | Not Ready for Inspection | EVAN COOPER |
| Interior/Exterior Lathing | 10/1/2024 | Partial Approval | EVAN COOPER |
| Shower Pan | 10/1/2024 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 10/4/2024 | Corrections Issued | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 10/4/2024 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 10/7/2024 | Partial Approval | EVAN COOPER |
| ELECTRICAL-Rough | 10/18/2024 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 10/18/2024 | Not Ready for Inspection | EVAN COOPER |
| Insulation | 10/18/2024 | Partial Approval | EVAN COOPER |
| Drywall Nailing | 10/24/2024 | Partial Approval | EVAN COOPER |
| Special/Order Compliance | 10/24/2024 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Rough | 10/29/2024 | Approved | EVAN COOPER |
| HVAC-Rough | 10/29/2024 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 10/30/2024 | Corrections Issued | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2024 | Conditional Approval | EVAN COOPER |
| Green Building Rough | 10/30/2024 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 10/30/2024 | Approved | EVAN COOPER |
| Sewer | 11/5/2024 | Approved | ARAM AVEDISIAN |
| Shower Pan | 11/12/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Shower Pan | 11/14/2024 | Partial Approval | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 11/20/2024 | Partial Approval | ARAM AVEDISIAN |
| Drywall Nailing | 11/25/2024 | Partial Approval | EVAN COOPER |