7320 S BROADWAY 1-37 90003
Certificate Information: 7320 S BROADWAY 1-37 90003
- Application / Permit
- 22010-10000-06550
- Plan Check / Job No.
- B22LA26375
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 4-STORY 100% AFFORDABLE HOUSING APARTMENT BUILDING - 37 UNITS
- Permit Issued
- Issued on 1/14/2025
- Issuing Office
- Metro
- Current Status
- Issued on 1/15/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/5/2023 | ARSALAN SHABESTARI |
| Green Plans Picked Up | 1/12/2023 | APPLICANT |
| Corrections Issued | 1/19/2023 | ARSALAN SHABESTARI |
| Quality Review Completed | 1/26/2023 | KEN GILL |
| Disabled Access Plans Picked Up | 3/7/2023 | APPLICANT |
| Plan Check Approved | 1/14/2025 | ARSALAN SHABESTARI |
| Issued | 1/14/2025 | APPLICANT |
| Issued | 1/15/2025 | JEANNE LY |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 10/20/2023 | LAVEON RIDER |
| Fire Marshal Fire Life Safety | Cleared | 11/2/2023 | MENOA AGHAJANI |
| Address approval | Cleared | 11/6/2023 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 11/6/2023 | JEANIE LAM |
| Historic Resource Verification | Cleared | 1/29/2024 | YASMINE BASHIRI |
| Redevelopment Project Area | Cleared | 1/29/2024 | YASMINE BASHIRI |
| Miscellaneous | Cleared | 1/30/2024 | RYAN LY |
| Miscellaneous | Cleared | 1/30/2024 | RYAN LY |
| Miscellaneous | Cleared | 1/30/2024 | RYAN LY |
| Miscellaneous | Cleared | 1/30/2024 | RYAN LY |
| Miscellaneous | Cleared | 1/30/2024 | RYAN LY |
| Low Impact Development | Cleared | 2/12/2024 | AMMAR ELTAWIL |
| Highway dedication | Cleared | 2/13/2024 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 2/13/2024 | JEANIE LAM |
| Permit | Cleared | 3/20/2024 | TREVOR QUAN |
| Building over 36-ft | Cleared | 4/9/2024 | CALOSHA APPROVED |
| DAS Clearance | Cleared | 5/22/2024 | ARSALAN SHABESTARI |
| Green Code | Cleared | 6/5/2024 | ARSALAN SHABESTARI |
| SB8 RUD | Cleared | 6/5/2024 | MICHAEL ZIRBES |
| Bicycle Parking | Cleared | 6/6/2024 | MARK REYES |
| Community Plan Implem. Overlay | Cleared | 6/7/2024 | ERIK BEASLEY |
| Density Bonus | Cleared | 6/12/2024 | MICHAEL ZIRBES |
| Community Plan Implem. Overlay | Cleared | 6/18/2024 | ANACANY HURTADO |
| Frnt yard landscape/Water mgmt | Cleared | 6/18/2024 | SPENCER WEJROWSKI |
| Miscellaneous | Cleared | 6/18/2024 | SPENCER WEJROWSKI |
| Opn space landscape/Water mgmt | Cleared | 6/18/2024 | SPENCER WEJROWSKI |
| Community Plan Implem. Overlay | Cleared | 6/20/2024 | ADALBERTO VERA |
| Trees in Parkway | Cleared | 6/20/2024 | ADALBERTO VERA |
| Community Plan Implem. Overlay | Cleared | 6/25/2024 | EILEEN HUNT |
| Community Plan Implem. Overlay | Cleared | 8/5/2024 | RIDWAN HARDY |
| Construction near power lines | Cleared | 8/5/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/5/2024 | RIDWAN HARDY |
| Sewer availability | Cleared | 10/22/2024 | JEANIE LAM |
| Work Adjacent to Public Way | Cleared | 12/11/2024 | LARRY LEE |
Contact Information
| Architect | Rezvani,, Farbod; Lic. No.: C32315 | 9055 ALCOTT STREET #1 LOS ANGELES, CA 90035 |
| Contractor | Di Nalli Construction; Lic. No.: 942979-B | 9055 ALCOTT STREET UNIT 1 LOS ANGELES, CA 90035 |
| Engineer | Monshizadeh,, Ali; Lic. No.: C67674 | 14392 ROSEWOOD TUSTIN, CA 92780 |
| Engineer | Sandoval,, Martin; Lic. No.: C56905 | 12761 DAIRY ST EASTVALE, CA 92880 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/23/2025 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 5/29/2025 | Partial Approval | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 6/5/2025 | Partial Approval | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2025 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2025 | Partial Approval | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2025 | Partial Approval | JOEY BUCHANAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2025 | Partial Approval | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2025 | Partial Approval | RAFAEL CORTES |
| Green Building Rough | 8/27/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Verify Sprinkler Sign Off | 8/27/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 8/27/2025 | Partial Approval | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2025 | Partial Approval | JOEY BUCHANAN |
| Insulation | 10/23/2025 | Partial Approval | JOEY BUCHANAN |
| Interior/Exterior Lathing | 11/25/2025 | Partial Approval | RAFAEL ESPINOZA |
| Wood Frame | 11/25/2025 | Corrections Issued | RAFAEL ESPINOZA |
| Green Building Rough | 3/27/2026 | Approved | JOEY BUCHANAN |
| Verify Sprinkler Sign Off | 3/27/2026 | Approved | JOEY BUCHANAN |
| Light Gage Steel Frame | 3/31/2026 | Not Ready for Inspection | JOEY BUCHANAN |
| Wood Frame | 4/20/2026 | Partial Approval | JOEY BUCHANAN |
| Insulation | 5/1/2026 | Partial Approval | JOEY BUCHANAN |