8111 S WESTERN AVE 1-45 90047
Certificate Information: 8111 S WESTERN AVE 1-45 90047
- Application / Permit
- 22010-10000-06496
- Plan Check / Job No.
- B22LA26332
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW CONSTRUCTION OF A FOUR-STORY APARTMENT BUILDING 100% ALL AFFORDABLE HOUSING CONSISTING OF 45 UNITS( 35 low income +10 moderate income ) AND A MANAGER'S OFFICE per AB 1763/2345
- Permit Issued
- Issued on 10/11/2024
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 10/11/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/5/2023 | ARSALAN SHABESTARI |
| Corrections Issued | 1/10/2023 | ARSALAN SHABESTARI |
| Green Plans Picked Up | 1/12/2023 | APPLICANT |
| Quality Review Completed | 1/18/2023 | KEN GILL |
| Building Plans Picked Up | 1/24/2023 | APPLICANT |
| Disabled Access Plans Picked Up | 3/7/2023 | APPLICANT |
| Applicant returned to address corrections | 1/16/2024 | ARSALAN SHABESTARI |
| Plan Check Approved | 10/10/2024 | ARSALAN SHABESTARI |
| Issued | 10/11/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/2/2023 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 2/13/2023 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 3/1/2023 | LAVEON RIDER |
| Construction near power lines | Cleared | 4/19/2023 | RIDWAN HARDY |
| Construction within easement | Cleared | 4/19/2023 | RIDWAN HARDY |
| Bicycle Parking | Cleared | 5/18/2023 | KATHERINE MENDOZA |
| Sewer availability | Cleared | 6/26/2023 | WALLIE JONG |
| Highway dedication | Cleared | 7/14/2023 | WALLIE JONG |
| Community Plan Implem. Overlay | Cleared | 10/4/2023 | RAFAEL FONTES |
| Miscellaneous | Cleared | 10/4/2023 | RAFAEL FONTES |
| Miscellaneous | Cleared | 10/4/2023 | RAFAEL FONTES |
| Site Plan review | Cleared | 10/27/2023 | MARITZA PRZEKOP |
| Fire Marshal Fire Life Safety | Cleared | 11/2/2023 | MENOA AGHAJANI |
| Green Code | Cleared | 12/11/2023 | MICHAEL MARTINEZ |
| Density Bonus 12.22.A.31 | Cleared | 12/12/2023 | MICHAEL ZIRBES |
| SB8 RUD | Cleared | 12/12/2023 | MICHAEL ZIRBES |
| Low Impact Development | Cleared | 12/27/2023 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 12/27/2023 | CELINA MORENO |
| DAS Clearance | Cleared | 1/3/2024 | ARSALAN SHABESTARI |
| Frnt yard landscape/Water mgmt | Cleared | 1/4/2024 | BRENNEN OBETO |
| Miscellaneous | Cleared | 1/4/2024 | BRENNEN OBETO |
| Opn space landscape/Water mgmt | Cleared | 1/4/2024 | BRENNEN OBETO |
| Work Adjacent to Public Way | Cleared | 5/29/2024 | LARRY LEE |
| Community Plan Implem. Overlay | Cleared | 6/3/2024 | CHRISTINA BRACO |
| Community Plan Implem. Overlay | Cleared | 6/4/2024 | OSCAR CASTRO |
| Community Plan Implem. Overlay | Cleared | 6/5/2024 | DYNL MIRANDA |
| Community Plan Implem. Overlay | Cleared | 6/5/2024 | EILEEN HUNT |
| Zoning Plan Check | Cleared | 6/5/2024 | ARSALAN SHABESTARI |
| Building over 36-ft | Cleared | 6/28/2024 | CALOSHA APPROVED |
Contact Information
| Contractor | Di Nalli Consulting Llc; Lic. No.: 942979-B | 9055 ALCOTT STREET UNIT 1 LOS ANGELES, CA 90035 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/23/2025 | Partial Approval | RAFAEL ESPINOZA |
| Footing/Foundation/Slab | 2/11/2025 | Approved | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2025 | Partial Approval | RAFAEL ESPINOZA |
| Green Building Rough | 4/2/2025 | Approved | RAFAEL ESPINOZA |
| Special/Order Compliance | 4/2/2025 | Partial Inspection | RAFAEL ESPINOZA |
| Verify Sprinkler Sign Off | 4/2/2025 | Not Ready for Inspection | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2025 | Corrections Issued | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/12/2025 | Partial Approval | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 5/29/2025 | Partial Approval | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2025 | Partial Approval | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2025 | Partial Approval | JOEY BUCHANAN |
| Insulation | 8/28/2025 | Partial Approval | RAFAEL CORTES |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2025 | Partial Approval | RAFAEL CORTES |
| Interior/Exterior Lathing | 10/29/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Interior/Exterior Lathing | 11/25/2025 | Partial Approval | RAFAEL ESPINOZA |
| Insulation | 12/19/2025 | Partial Approval | JOEY BUCHANAN |
| Verify Sprinkler Sign Off | 1/8/2026 | Partial Approval | RAFAEL CORTES |
| Wood Frame | 1/8/2026 | Partial Approval | RAFAEL CORTES |
| Insulation | 1/16/2026 | Partial Approval | JOEY BUCHANAN |
| Insulation | 5/28/2026 | Corrections Issued | RAFAEL CORTES |