16704 W ADDISON ST 91436

Certificate Information: 16704 W ADDISON ST 91436

Application / Permit
22010-10000-06477
Plan Check / Job No.
B22LA26294
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPlan: New 2-Story S.F.D w/Attached 2-Car Garage and Rooftop Deck
Permit Issued
Issued on 11/8/2023
Issuing Office
Current Status
CofO Issued on 1/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2022 APPLICANT
Assigned to Plan Check Engineer 1/19/2023 DAVID CASTILLO
Corrections Issued 1/26/2023 DAVID CASTILLO
Quality Review Completed 2/2/2023 KAVIAN REFAHI
Plan Check Approved 8/8/2023 DAVID CASTILLO
Issued 11/8/2023 APPLICANT
CofO in Progress 12/19/2024 THOMAS FINNILA
CofO Issued 1/7/2025 JOHN JANSON
Permit Finaled 1/7/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 3/14/2023 MEGAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 4/26/2023 MEGAN GODINEZ
Hydrant and Access approval Cleared 4/26/2023 KURT CORRAL
Sewer availability Cleared 4/26/2023 MEGAN GODINEZ
Low Impact Development Cleared 6/30/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 6/30/2023 DAGOVERTO GUERRERO
Trees in Parkway Cleared 7/3/2023 ADALBERTO VERA
Permit Cleared 7/6/2023 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/19/2023 Approved VINCENT HANLEY
Footing/Foundation/Slab 12/19/2023 Partial Approval VINCENT HANLEY
PLUMBING-Rough 12/19/2023 Partial Approval VINCENT HANLEY
Deputy Reinf. Concrete 1/10/2024 Approved VINCENT HANLEY
Footing/Foundation/Slab 1/10/2024 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 2/12/2024 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 3/20/2024 Not Ready for Inspection VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/20/2024 Partial Approval VINCENT HANLEY
HVAC-Rough 3/20/2024 Approved VINCENT HANLEY
BUILDING-Rough-Frame 4/11/2024 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Rough 4/11/2024 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/11/2024 Approved VINCENT HANLEY
Gas Test 4/11/2024 Approved VINCENT HANLEY
Green Building Rough 4/11/2024 Not Ready for Inspection VINCENT HANLEY
HVAC-Rough 4/11/2024 Approved VINCENT HANLEY
PLUMBING-Rough 4/11/2024 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 4/11/2024 Approved VINCENT HANLEY
BUILDING-Rough-Frame 4/24/2024 Approved VINCENT HANLEY
Green Building Rough 4/24/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 4/24/2024 Partial Approval VINCENT HANLEY
Insulation 5/6/2024 Approved VINCENT HANLEY
Shower Pan 5/6/2024 Approved VINCENT HANLEY
Drywall Nailing 5/13/2024 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 5/31/2024 Partial Approval ARUTYUN MADATYAN
Sewer 8/19/2024 Partial Approval THOMAS FINNILA
Underground Mechanical 8/19/2024 Partial Approval THOMAS FINNILA
Underground Mechanical 8/21/2024 Partial Approval THOMAS FINNILA
ELECTRICAL-Final 10/21/2024 Corrections Issued THOMAS FINNILA
HVAC-Final 10/21/2024 Approved THOMAS FINNILA
ELECTRICAL-Final 11/25/2024 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 12/2/2024 Approved THOMAS FINNILA
PLUMBING-Final 12/2/2024 Approved THOMAS FINNILA
Final 12/18/2024 OK to Issue CofO THOMAS FINNILA
Green Building Final 12/18/2024 Approved THOMAS FINNILA
SGSOV-Seismic Gas S/O Valve 12/18/2024 SGSOV Approved THOMAS FINNILA
Service/Power Release 12/18/2024 Approved THOMAS FINNILA
Smoke Detectors 12/18/2024 Approved THOMAS FINNILA