3406 E MANITOU AVE 90031

Certificate Information: 3406 E MANITOU AVE 90031

Application / Permit
22010-10000-06474
Plan Check / Job No.
B22LA26292
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(22) Storage Building
Work Description
ePlan (N) DETACHED STORAGE BUIDLING (NO MEP)
Permit Issued
Issued on 2/5/2024
Issuing Office
Current Status
CofO Issued on 1/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/29/2022 APPLICANT
Assigned to Plan Check Engineer 1/6/2023 FERNANDO FLORES
Corrections Issued 1/9/2023 FERNANDO FLORES
Applicant returned to address corrections 1/3/2024 FERNANDO FLORES
Plan Check Approved 1/27/2024 FERNANDO FLORES
Issued 2/5/2024 APPLICANT
CofO in Progress 1/8/2026 ALIZAH MAYAGOITIA
Permit Finaled 1/9/2026 DEROLD HAUFF
CofO Issued 1/9/2026 DEROLD HAUFF
Permit Finaled 1/9/2026 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/27/2023 AMAAN MALIK
Construction near power lines Cleared 4/15/2023 RIDWAN HARDY
Roof/Waste drainage to street Cleared 1/6/2024 ADRIAN SANCHEZ

Contact Information

Contractor Tuff Shed Inc; Lic. No.: 661664-B 1777 S HARRISON STREET   SUITE 600    DENVER, CO 80210
Engineer Cahalan,, Timothy Donald; Lic. No.: C80850 14818 FAIRWAY CIRCLE      LEAWOOD, KS 66224

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 5/17/2024 Approved OSVALDO PARAMO
Verify Sprinkler Sign Off 5/17/2024 Approved OSVALDO PARAMO
Wood Frame 5/17/2024 Approved OSVALDO PARAMO
Final 5/23/2024 No Access for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 5/23/2024 Approved OSVALDO PARAMO
Green Building Final 5/23/2024 No Access for Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 5/23/2024 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 5/23/2024 No Access for Inspection OSVALDO PARAMO
Final 5/29/2024 Conditional Approval OSVALDO PARAMO
Green Building Final 5/29/2024 Approved OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 5/29/2024 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 5/29/2024 Approved OSVALDO PARAMO
Special/Order Compliance 7/5/2024 Corrections Issued OSVALDO PARAMO
Final 5/29/2025 Corrections Issued ALIZAH MAYAGOITIA
Final 1/2/2026 Conditional Approval ALIZAH MAYAGOITIA