1645 1/2 W 223RD ST 90501

Certificate Information: 1645 1/2 W 223RD ST 90501

Application / Permit
22010-10000-06467
Plan Check / Job No.
B22LA26284
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan New single family dwelling per SB-9 with attached JADU per SB9 Two-Unit Development Ca Govt Code 65852.21 Fire sprinklered through out NFPA13D
Permit Issued
Issued on 1/3/2024
Issuing Office
Current Status
CofO Issued on 12/20/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2022 APPLICANT
Assigned to Plan Check Engineer 2/2/2023 JAD BASMA
Corrections Issued 2/8/2023 JAD BASMA
Quality Review Completed 2/24/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 8/1/2023 JAD BASMA
Applicant returned to address corrections 10/12/2023 JAD BASMA
Plan Check Approved 12/14/2023 JAD BASMA
Plan Check Approved 1/3/2024 JAD BASMA
Issued 1/3/2024 APPLICANT
CofO in Progress 12/20/2024 EUGENE CASSIDY
Permit Finaled 12/20/2024 ANSON MAGLASANG
CofO Issued 12/20/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 2/27/2023 KHAING AYE
Eng Process Fee Ord 176,300 Cleared 3/7/2023 KHAING AYE
Hydrant and Access approval Cleared 3/27/2023 KURT CORRAL
Stormwater Pollution Mitigatn Cleared 6/2/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 6/9/2023 KHAING AYE
Sewer availability Cleared 6/9/2023 KHAING AYE

Contact Information

Contractor Sarrafian Payam; Lic. No.: 1019603-B       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/20/2024 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 2/20/2024 Not Ready for Inspection EUGENE CASSIDY
Pre-Inspection 2/20/2024 Approved EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 2/26/2024 Partial Approval EUGENE CASSIDY
METHANE-Subgrade 2/26/2024 Approved EUGENE CASSIDY
PLUMBING-Rough 2/26/2024 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 3/8/2024 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 3/8/2024 Partial Approval EUGENE CASSIDY
Sewer 3/8/2024 Approved EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 3/12/2024 Not Ready for Inspection EUGENE CASSIDY
Footing/Foundation/Slab 3/12/2024 Approved EUGENE CASSIDY
METHANE-Barrier 3/12/2024 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 4/12/2024 Partial Approval EUGENE CASSIDY
Green Building Rough 4/12/2024 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 4/12/2024 Not Ready for Inspection EUGENE CASSIDY
Verify Sprinkler Sign Off 4/12/2024 Not Ready for Inspection EUGENE CASSIDY
Wood Frame 4/12/2024 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 5/13/2024 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 5/13/2024 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 5/13/2024 Approved EUGENE CASSIDY
HVAC-Rough 5/13/2024 Partial Approval EUGENE CASSIDY
METHANE-Rough 5/13/2024 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Rough 5/13/2024 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 5/13/2024 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 5/20/2024 Approved EUGENE CASSIDY
HVAC-Rough 5/20/2024 Approved EUGENE CASSIDY
Insulation 5/20/2024 Corrections Issued EUGENE CASSIDY
Interior/Exterior Lathing 5/20/2024 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 5/24/2024 Approved EUGENE CASSIDY
METHANE-Rough 5/24/2024 Approved EUGENE CASSIDY
Verify Sprinkler Sign Off 5/24/2024 Approved EUGENE CASSIDY
Drywall Nailing 6/10/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 6/10/2024 Approved EUGENE CASSIDY
ELECTRICAL-Final 7/25/2024 Not Ready for Inspection EUGENE CASSIDY
Final 7/25/2024 Corrections Issued EUGENE CASSIDY
Green Building Final 7/25/2024 Not Ready for Inspection EUGENE CASSIDY
HVAC-Final 7/25/2024 Not Ready for Inspection EUGENE CASSIDY
PLUMBING-Final 7/25/2024 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 7/25/2024 SGSOV Not Required EUGENE CASSIDY
Service/Power Release 7/25/2024 Not Ready for Inspection EUGENE CASSIDY
Smoke Detectors 7/25/2024 Approved EUGENE CASSIDY
ELECTRICAL-Final 10/8/2024 Approved EUGENE CASSIDY
Final 10/8/2024 Corrections Issued EUGENE CASSIDY
HVAC-Final 10/8/2024 Approved EUGENE CASSIDY
PLUMBING-Final 10/8/2024 Approved EUGENE CASSIDY
Service/Power Release 10/8/2024 Not Ready for Inspection EUGENE CASSIDY
Final 12/19/2024 OK to Issue CofO EUGENE CASSIDY
Green Building Final 12/19/2024 Approved EUGENE CASSIDY
Service/Power Release 12/19/2024 Approved EUGENE CASSIDY