ePlan eplan New 2-story (irregular shaped 90'-4" x x40' - 0 1/2") 4548 sqft Single Family Dwelling with attached garage, carport and rec room. NFPA 13D fire sprinkler system is required.
Permit Issued
Issued on 10/16/2023
Issuing Office
Current Status
Issued on 10/16/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 1/4/2023 APPLICANT
Assigned to Plan Check Engineer 1/26/2023 NGHI SU
Corrections Issued 1/31/2023 NGHI SU
Quality Review Completed 2/3/2023 GARO TELMI
Applicant returned to address corrections 6/5/2023 NGHI SU
Applicant returned to address corrections 8/3/2023 NGHI SU
Plan Check Approved 10/3/2023 NGHI SU
Issued 10/16/2023 APPLICANT

Permit Application Clearance Information

Hydrant and Access approval Cleared 3/11/2023 KURT CORRAL
Eng Process Fee Ord 176,300 Cleared 3/13/2023 JASON NG
Sewer availability Cleared 3/13/2023 JASON NG
Specific Plan Cleared 4/19/2023 FREDDY GARCIA
Permit Cleared 8/15/2023 DARIN LAM
Low Impact Development Cleared 8/31/2023 SAMUEL LINN
Roof/Waste drainage to street Cleared 9/3/2023 AHMED AMARRAGY
Trees in Parkway Cleared 9/20/2023 ADALBERTO VERA
GPI Written Notices Cleared 9/26/2023 NGHI SU
Grading Pre-Inspection Cleared 9/26/2023 NGHI SU

Contact Information

Architect Tichenor,, Michael Brian; Lic. No.: NA21046       ,
Contractor Call Bryce Construction Inc; Lic. No.: 675054-B P O BOX 220053      NEWHALL, CA 91322
Engineer Daugherty,, Daniel Thomas; Lic. No.: C76588 31129 VIA COLINAS STE 707      WESTLAKE VILLAGE, CA 91362
Engineer Hollingsworth,, Robert Alan; Lic. No.: GE2022 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362
Engineer Resnick,, Bruce Daniel; Lic. No.: NA3293       ,
Engineer Yamashita,, Mark Alan; Lic. No.: L7155 6718 BIANCA AVE      LAKE BALBOA, CA 91406
Geologist Hollingsworth,, Robert Alan; Lic. No.: EG1265 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/13/2023 Corrections Issued RICHARD STEINBACH
Footing/Foundation/Slab 11/13/2023 Conditional Approval RICHARD STEINBACH
PLUMBING-Rough 11/13/2023 Corrections Issued RICHARD STEINBACH
Footing/Foundation/Slab 1/9/2024 Not Ready for Inspection CARLOS MATAMOROS
Footing/Foundation/Slab 6/7/2024 Not Ready for Inspection ARAM AVEDISIAN
PLUMBING-Rough 6/7/2024 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 6/10/2024 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 8/15/2024 Corrections Issued CARLOS MATAMOROS
Special/Order Compliance 1/15/2025 Corrections Issued CARLOS MATAMOROS
BUILDING-Rough-Frame 1/30/2025 Corrections Issued CARLOS MATAMOROS
Green Building Rough 1/30/2025 Not Ready for Inspection CARLOS MATAMOROS
Verify Sprinkler Sign Off 1/30/2025 Not Ready for Inspection CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 2/11/2025 Not Ready for Inspection JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/18/2025 Approved CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 2/21/2025 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 2/27/2025 Corrections Issued CARLOS MATAMOROS
PLUMBING-Rough 2/27/2025 Approved CARLOS MATAMOROS
Verify Sprinkler Sign Off 2/27/2025 Approved CARLOS MATAMOROS
HVAC-Rough 3/6/2025 Corrections Issued STEPHANIE SWANSON
Wood Frame 3/6/2025 Not Ready for Inspection STEPHANIE SWANSON
BUILDING-Rough-Frame 4/7/2025 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 4/7/2025 Partial Approval STEPHANIE SWANSON
Final 4/7/2025 Corrections Issued STEPHANIE SWANSON
Green Building Rough 4/7/2025 Approved STEPHANIE SWANSON
HVAC-Rough 4/7/2025 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 4/7/2025 Partial Approval STEPHANIE SWANSON
BUILDING-Rough-Frame 4/11/2025 Approved CARLOS MATAMOROS
Green Building Rough 4/11/2025 Approved CARLOS MATAMOROS
HVAC-Rough 4/11/2025 Approved CARLOS MATAMOROS
Insulation 4/21/2025 Approved DANIEL VERA
Shower Pan 4/21/2025 Approved DANIEL VERA
Drywall Nailing 5/5/2025 Approved CARLOS MATAMOROS
Special/Order Compliance 5/5/2025 Corrections Issued CARLOS MATAMOROS
Interior/Exterior Lathing 6/4/2025 Approved CARLOS MATAMOROS
ELECTRICAL-Final 3/26/2026 Approved EVAN COOPER
Green Building Final 3/26/2026 Not Ready for Inspection EVAN COOPER
HVAC-Final 3/26/2026 Approved EVAN COOPER
PLUMBING-Final 3/26/2026 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 3/26/2026 SGSOV Approved EVAN COOPER
Smoke Detectors 3/26/2026 Approved EVAN COOPER
Structural Steel Frame 3/26/2026 Approved EVAN COOPER
Final 5/11/2026 Corrections Issued EVAN COOPER
Green Building Final 5/11/2026 Approved EVAN COOPER
Service/Power Release 5/11/2026 Not Ready for Inspection EVAN COOPER