11745 W CHENAULT ST 90049
Certificate Information: 11745 W CHENAULT ST 90049
- Application / Permit
- 22010-10000-06389
- Plan Check / Job No.
- B22LA26027
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan eplan New 2-story (irregular shaped 90'-4" x x40' - 0 1/2") 4548 sqft Single Family Dwelling with attached garage, carport and rec room. NFPA 13D fire sprinkler system is required.
- Permit Issued
- Issued on 10/16/2023
- Issuing Office
- Current Status
- Issued on 10/16/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/4/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/26/2023 | NGHI SU |
| Corrections Issued | 1/31/2023 | NGHI SU |
| Quality Review Completed | 2/3/2023 | GARO TELMI |
| Applicant returned to address corrections | 6/5/2023 | NGHI SU |
| Applicant returned to address corrections | 8/3/2023 | NGHI SU |
| Plan Check Approved | 10/3/2023 | NGHI SU |
| Issued | 10/16/2023 | APPLICANT |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 3/11/2023 | KURT CORRAL |
| Eng Process Fee Ord 176,300 | Cleared | 3/13/2023 | JASON NG |
| Sewer availability | Cleared | 3/13/2023 | JASON NG |
| Specific Plan | Cleared | 4/19/2023 | FREDDY GARCIA |
| Permit | Cleared | 8/15/2023 | DARIN LAM |
| Low Impact Development | Cleared | 8/31/2023 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 9/3/2023 | AHMED AMARRAGY |
| Trees in Parkway | Cleared | 9/20/2023 | ADALBERTO VERA |
| GPI Written Notices | Cleared | 9/26/2023 | NGHI SU |
| Grading Pre-Inspection | Cleared | 9/26/2023 | NGHI SU |
Contact Information
| Architect | Tichenor,, Michael Brian; Lic. No.: NA21046 | , |
| Contractor | Call Bryce Construction Inc; Lic. No.: 675054-B | P O BOX 220053 NEWHALL, CA 91322 |
| Engineer | Daugherty,, Daniel Thomas; Lic. No.: C76588 | 31129 VIA COLINAS STE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Hollingsworth,, Robert Alan; Lic. No.: GE2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Resnick,, Bruce Daniel; Lic. No.: NA3293 | , |
| Engineer | Yamashita,, Mark Alan; Lic. No.: L7155 | 6718 BIANCA AVE LAKE BALBOA, CA 91406 |
| Geologist | Hollingsworth,, Robert Alan; Lic. No.: EG1265 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/13/2023 | Corrections Issued | RICHARD STEINBACH |
| Footing/Foundation/Slab | 11/13/2023 | Conditional Approval | RICHARD STEINBACH |
| PLUMBING-Rough | 11/13/2023 | Corrections Issued | RICHARD STEINBACH |
| Footing/Foundation/Slab | 1/9/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 6/7/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 6/7/2024 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 6/10/2024 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2024 | Corrections Issued | CARLOS MATAMOROS |
| Special/Order Compliance | 1/15/2025 | Corrections Issued | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 1/30/2025 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Rough | 1/30/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 1/30/2025 | Not Ready for Inspection | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2025 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 2/21/2025 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 2/27/2025 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Rough | 2/27/2025 | Approved | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 2/27/2025 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 3/6/2025 | Corrections Issued | STEPHANIE SWANSON |
| Wood Frame | 3/6/2025 | Not Ready for Inspection | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 4/7/2025 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 4/7/2025 | Partial Approval | STEPHANIE SWANSON |
| Final | 4/7/2025 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Rough | 4/7/2025 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 4/7/2025 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 4/7/2025 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 4/11/2025 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 4/11/2025 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 4/11/2025 | Approved | CARLOS MATAMOROS |
| Insulation | 4/21/2025 | Approved | DANIEL VERA |
| Shower Pan | 4/21/2025 | Approved | DANIEL VERA |
| Drywall Nailing | 5/5/2025 | Approved | CARLOS MATAMOROS |
| Special/Order Compliance | 5/5/2025 | Corrections Issued | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 6/4/2025 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 3/26/2026 | Approved | EVAN COOPER |
| Green Building Final | 3/26/2026 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Final | 3/26/2026 | Approved | EVAN COOPER |
| PLUMBING-Final | 3/26/2026 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 3/26/2026 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 3/26/2026 | Approved | EVAN COOPER |
| Structural Steel Frame | 3/26/2026 | Approved | EVAN COOPER |
| Final | 5/11/2026 | Corrections Issued | EVAN COOPER |
| Green Building Final | 5/11/2026 | Approved | EVAN COOPER |
| Service/Power Release | 5/11/2026 | Not Ready for Inspection | EVAN COOPER |