2735 E 6TH ST 1-18 90023

Certificate Information: 2735 E 6TH ST 1-18 90023

Application / Permit
22010-10000-06369
Plan Check / Job No.
B22LA25990
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
PROPOSED 3 STORY APARTMENT BUILDING WITH GROUND FLOOR PARKING
Permit Issued
Issued on 6/21/2024
Issuing Office
Metro
Current Status
CofO Issued on 4/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/22/2022 APPLICANT
Green Plans Picked Up 1/24/2023 APPLICANT
Assigned to Plan Check Engineer 2/2/2023 JOE VO
Building Plans Picked Up 2/14/2023 APPLICANT
Corrections Issued 8/16/2023 JOE VO
Quality Review Completed 8/17/2023 JOHN FRANCIA
Applicant returned to address corrections 1/18/2024 JOE VO
Plan Check Approved 6/20/2024 JOE VO
Issued 6/21/2024 APPLICANT
CofO in Progress 4/3/2026 RONALD JIMENEZ
Permit Finaled 4/3/2026 ERNESTO CORRAL
CofO Issued 4/3/2026 ERNESTO CORRAL
Permit Finaled 4/3/2026 ERNESTO CORRAL

Permit Application Clearance Information

Clean Up Green Up Cleared 3/20/2023 DALIA MOKAYED
Highway dedication Cleared 3/22/2023 CINDY QI
Address approval Cleared 3/29/2023 CINDY QI
Eng Process Fee Ord 176,300 Cleared 3/30/2023 CINDY QI
Sewer availability Cleared 3/30/2023 CINDY QI
Trees in Parkway Cleared 6/5/2023 ADALBERTO VERA
Hydrant and Access approval Cleared 6/30/2023 LAVEON RIDER
Driveway location Cleared 7/5/2023 COLLINS ALLAN
Abandoned oil well Cleared 7/24/2023 LAVEON RIDER
Building over 36-ft Cleared 8/22/2023 CALOSHA APPROVED
Green Code Cleared 9/13/2023 MICHAEL MARTINEZ
Permit Cleared 10/4/2023 ALBERT TAM
Stormwater Pollution Mitigatn Cleared 11/22/2023 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 11/27/2023 MATIAS FARFAN
DAS Clearance Cleared 1/9/2024 SHINE LIN
Fire Marshal Fire Life Safety Cleared 4/26/2024 RONILO MULAWIN
Miscellaneous Cleared 5/17/2024 ALBERT TAM

Contact Information

Architect Murnane,, R Mcshane; Lic. No.: C34176 2898 ROWENA AVENUE UNIT 102      LOS ANGELES, CA 90039
Contractor 4site Construction; Lic. No.: 971233-B 1619 W TEMPLE ST      LOS ANGELES, CA 90026
Engineer Kim,, Seung; Lic. No.: S5909 9934 CEDAR CT      CYPRESS, CA 90630
Engineer Salehipour,, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104

Inspector Information

RONALD JIMENEZ, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
LARRY ARNICK, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
JOEY BUCHANAN, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
ERNESTO CORRAL, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL ESPINOZA, (213) 482-0307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/25/2024 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 7/31/2024 Partial Inspection LARRY ARNICK
Piling/Pier/Caisson 7/31/2024 Partial Inspection LARRY ARNICK
Deputy Grading 8/1/2024 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 8/1/2024 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 8/1/2024 Partial Inspection JEFFREY FULTON
METHANE-Barrier 8/1/2024 Not Ready for Inspection JEFFREY FULTON
METHANE-Subgrade 8/1/2024 Not Ready for Inspection JEFFREY FULTON
Deputy Grading 8/2/2024 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 8/2/2024 Conditional Approval JEFFREY FULTON
Piling/Pier/Caisson 8/2/2024 Partial Inspection JEFFREY FULTON
Deputy Grading 8/5/2024 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 8/5/2024 Conditional Approval JEFFREY FULTON
Piling/Pier/Caisson 8/5/2024 Partial Inspection JEFFREY FULTON
Deputy Grading 8/6/2024 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 8/6/2024 Conditional Approval JEFFREY FULTON
Piling/Pier/Caisson 8/6/2024 Partial Inspection JEFFREY FULTON
Deputy Reinf. Concrete 8/13/2024 Conditional Approval LARRY ARNICK
Deputy Grading 8/15/2024 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 8/15/2024 Conditional Approval JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 8/15/2024 Partial Inspection JEFFREY FULTON
Deputy Grading 8/19/2024 Conditional Approval RAFAEL ESPINOZA
Deputy Reinf. Concrete 8/19/2024 Conditional Approval RAFAEL ESPINOZA
Deputy Grading 8/20/2024 Conditional Approval MICHAEL ROSENBERG
Special/Order Compliance 8/20/2024 Partial Inspection RAFAEL ESPINOZA
Deputy Methane Barrier 9/13/2024 Conditional Approval JEFFREY FULTON
METHANE-Barrier 9/13/2024 Partial Inspection JEFFREY FULTON
METHANE-Rough 9/13/2024 Not Ready for Inspection JEFFREY FULTON
METHANE-Subgrade 9/13/2024 Partial Inspection JEFFREY FULTON
METHANE-Final 9/16/2024 Not Ready for Inspection JEFFREY FULTON
METHANE-Barrier 9/18/2024 Partial Inspection JEFFREY FULTON
METHANE-Rough 9/18/2024 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 9/19/2024 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 9/19/2024 Partial Inspection JEFFREY FULTON
METHANE-Subgrade 9/19/2024 Not Ready for Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 9/23/2024 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 9/26/2024 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 9/26/2024 Partial Inspection JEFFREY FULTON
METHANE-Barrier 9/26/2024 Partial Inspection JEFFREY FULTON
METHANE-Subgrade 9/26/2024 Partial Inspection JEFFREY FULTON
Masonry Wall/Backfill 10/4/2024 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 10/8/2024 Partial Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 10/16/2024 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 10/24/2024 Partial Inspection JEFFREY FULTON
Excavation/Setback/Form/Re-Bar 11/27/2024 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 12/17/2024 Partial Inspection JEFFREY FULTON
Green Building Rough 12/17/2024 Approved JEFFREY FULTON
METHANE-Rough 12/17/2024 Not Ready for Inspection JEFFREY FULTON
Verify Sprinkler Sign Off 12/17/2024 Not Ready for Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 1/22/2025 Partial Inspection JEFFREY FULTON
Footing/Foundation/Slab 3/4/2025 Partial Approval RONALD JIMENEZ
METHANE-Barrier 3/4/2025 Not Ready for Inspection RONALD JIMENEZ
METHANE-Subgrade 3/4/2025 Not Ready for Inspection RONALD JIMENEZ
Deputy Wood Construction 3/7/2025 Conditional Approval JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 3/7/2025 Partial Inspection JEFFREY FULTON
Wood Frame 3/7/2025 Partial Inspection JEFFREY FULTON
Deputy Drilled-In Anchors 3/10/2025 Conditional Approval LARRY ARNICK
Deputy Reinf. Concrete 3/10/2025 Conditional Approval LARRY ARNICK
Excavation/Setback/Form/Re-Bar 3/14/2025 Partial Inspection JEFFREY FULTON
Deputy Wood Construction 3/24/2025 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 3/25/2025 Partial Inspection JEFFREY FULTON
Wood Frame 3/27/2025 Partial Inspection JEFFREY FULTON
Special/Order Compliance 4/2/2025 Partial Inspection JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 4/17/2025 Partial Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 4/24/2025 Partial Inspection JEFFREY FULTON
Drywall Nailing 6/12/2025 Corrections Issued JEFFREY FULTON
Floor/Roof Diaphrgm/Shear Wall 6/12/2025 Partial Inspection JEFFREY FULTON
Wood Frame 6/12/2025 Partial Inspection JEFFREY FULTON
Interior/Exterior Lathing 6/25/2025 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 7/3/2025 Corrections Issued JEFFREY FULTON
Light Gage Steel Frame 7/9/2025 Partial Approval LARRY ARNICK
Wood Frame 7/17/2025 Corrections Issued LARRY ARNICK
Wood Frame 7/18/2025 Partial Approval LARRY ARNICK
Wood Frame 7/22/2025 Partial Approval LARRY ARNICK
Insulation 7/23/2025 Not Ready for Inspection LARRY ARNICK
Insulation 7/28/2025 Partial Approval LARRY ARNICK
Insulation 7/31/2025 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 8/1/2025 Partial Inspection LARRY ARNICK
Interior/Exterior Lathing 8/6/2025 Partial Approval LARRY ARNICK
Wood Frame 8/6/2025 Partial Approval LARRY ARNICK
Insulation 8/8/2025 Partial Approval LARRY ARNICK
Drywall Nailing 8/25/2025 Not Ready for Inspection LARRY ARNICK
Interior/Exterior Lathing 8/28/2025 Approved LARRY ARNICK
Drywall Nailing 8/29/2025 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 9/2/2025 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 9/2/2025 Partial Inspection JEFFREY FULTON
Drywall Nailing 9/3/2025 Partial Inspection JEFFREY FULTON
Special/Order Compliance 9/4/2025 Conditional Approval LARRY ARNICK
Light Gage Steel Frame 9/9/2025 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 9/10/2025 Not Ready for Inspection LARRY ARNICK
Light Gage Steel Frame 9/10/2025 Partial Approval LARRY ARNICK
Drywall Nailing 9/22/2025 Partial Approval LARRY ARNICK
Insulation 10/3/2025 Partial Approval LARRY ARNICK
Drywall Nailing 10/8/2025 Partial Approval LARRY ARNICK
Light Gage Steel Frame 10/20/2025 Partial Approval LARRY ARNICK
Drywall Nailing 12/11/2025 Not Ready for Inspection LARRY ARNICK
Final 1/13/2026 Not Ready for Inspection LARRY ARNICK
Footing/Foundation/Slab 1/13/2026 Not Ready for Inspection LARRY ARNICK
Green Building Final 1/13/2026 Not Ready for Inspection LARRY ARNICK
METHANE-Barrier 1/13/2026 Not Ready for Inspection LARRY ARNICK
METHANE-Final 1/13/2026 Not Ready for Inspection LARRY ARNICK
METHANE-Rough 1/13/2026 Not Ready for Inspection LARRY ARNICK
METHANE-Subgrade 1/13/2026 Not Ready for Inspection LARRY ARNICK
Reinforced Concrete Frame 1/13/2026 Not Ready for Inspection LARRY ARNICK
Reinforced Masonry Frame 1/13/2026 Not Ready for Inspection LARRY ARNICK
SGSOV-Seismic Gas S/O Valve 1/13/2026 SGSOV Not Ready LARRY ARNICK
Smoke Detectors 1/13/2026 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 1/13/2026 Not Ready for Inspection LARRY ARNICK
SGSOV-Seismic Gas S/O Valve 2/6/2026 SGSOV Not Ready RONALD JIMENEZ
Final 2/24/2026 Partial Inspection RONALD JIMENEZ
Footing/Foundation/Slab 2/24/2026 Approved RONALD JIMENEZ
METHANE-Barrier 2/24/2026 Approved RONALD JIMENEZ
METHANE-Rough 2/24/2026 Approved RONALD JIMENEZ
METHANE-Subgrade 2/24/2026 Approved RONALD JIMENEZ
Reinforced Concrete Frame 2/24/2026 Approved RONALD JIMENEZ
Reinforced Masonry Frame 2/24/2026 Approved RONALD JIMENEZ
Verify Sprinkler Sign Off 2/24/2026 Approved RONALD JIMENEZ
Final 3/24/2026 Not Ready for Inspection RONALD JIMENEZ
Green Building Final 3/24/2026 Approved RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 3/24/2026 SGSOV Approved RONALD JIMENEZ
Smoke Detectors 3/24/2026 Approved RONALD JIMENEZ
Final 3/31/2026 OK to Issue CofO RONALD JIMENEZ