Underground Mechanical
|
11/3/2023
|
Partial Approval
|
SCOTT FINNILA
|
|
Deputy Drilled-In Anchors
|
11/14/2023
|
Conditional Approval
|
SABAS ALONSO
|
|
Excavation/Setback/Form/Re-Bar
|
11/14/2023
|
Partial Approval
|
SABAS ALONSO
|
|
Footing/Foundation/Slab
|
11/14/2023
|
Partial Approval
|
SABAS ALONSO
|
|
Underground Mechanical
|
11/14/2023
|
Partial Approval
|
SABAS ALONSO
|
|
METHANE-Subgrade
|
11/28/2023
|
Corrections Issued
|
SABAS ALONSO
|
|
Footing/Foundation/Slab
|
11/29/2023
|
No Access for Inspection
|
SABAS ALONSO
|
|
Footing/Foundation/Slab
|
12/4/2023
|
Corrections Issued
|
SABAS ALONSO
|
|
METHANE-Barrier
|
12/4/2023
|
Not Ready for Inspection
|
SABAS ALONSO
|
|
METHANE-Subgrade
|
12/4/2023
|
Approved
|
SABAS ALONSO
|
|
Deputy Drilled-In Anchors
|
12/6/2023
|
Conditional Approval
|
SABAS ALONSO
|
|
Footing/Foundation/Slab
|
12/6/2023
|
Corrections Issued
|
SABAS ALONSO
|
|
METHANE-Barrier
|
12/6/2023
|
Not Ready for Inspection
|
SABAS ALONSO
|
|
METHANE-Final
|
12/6/2023
|
Not Ready for Inspection
|
SABAS ALONSO
|
|
Excavation/Setback/Form/Re-Bar
|
12/11/2023
|
Not Ready for Inspection
|
SABAS ALONSO
|
|
Footing/Foundation/Slab
|
12/11/2023
|
Not Ready for Inspection
|
SABAS ALONSO
|
|
METHANE-Barrier
|
12/11/2023
|
Corrections Issued
|
SABAS ALONSO
|
|
Excavation/Setback/Form/Re-Bar
|
12/12/2023
|
Corrections Issued
|
SABAS ALONSO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/26/2023
|
Partial Approval
|
SABAS ALONSO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/3/2024
|
Not Ready for Inspection
|
SABAS ALONSO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/4/2024
|
Corrections Issued
|
SABAS ALONSO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/17/2024
|
Partial Approval
|
SABAS ALONSO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/2/2024
|
Corrections Issued
|
SABAS ALONSO
|
|
Deputy Drilled-In Anchors
|
2/12/2024
|
Conditional Approval
|
SABAS ALONSO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/14/2024
|
Corrections Issued
|
SABAS ALONSO
|
|
Floor/Roof Diaphrgm/Shear Wall
|
2/16/2024
|
Approved
|
SABAS ALONSO
|
|
Pre-Inspection
|
2/16/2024
|
Off-Hour Fees Due
|
|
|
Pre-Inspection
|
2/29/2024
|
Corrections Issued
|
ANTHONY EGSON
|
|
Deputy Steel/Welding
|
3/7/2024
|
Conditional Approval
|
SABAS ALONSO
|
|
Pre-Inspection
|
3/20/2024
|
Partial Inspection
|
SABAS ALONSO
|
|
ELECTRICAL-Rough
|
4/3/2024
|
Corrections Issued
|
SABAS ALONSO
|
|
HVAC-Rough
|
4/3/2024
|
Not Ready for Inspection
|
SABAS ALONSO
|
|
PLUMBING-Rough
|
4/3/2024
|
Not Ready for Inspection
|
SABAS ALONSO
|
|
ELECTRICAL-Rough
|
4/5/2024
|
Conditional Approval
|
JOSE MACIAS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/5/2024
|
Not Ready for Inspection
|
JOSE MACIAS
|
|
HVAC-Rough
|
4/5/2024
|
Not Ready for Inspection
|
JOSE MACIAS
|
|
PLUMBING-Rough
|
4/5/2024
|
Approved
|
JOSE MACIAS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
4/8/2024
|
Partial Approval
|
SABAS ALONSO
|
|
HVAC-Rough
|
4/8/2024
|
Approved
|
SABAS ALONSO
|
|
HVAC-Rough
|
4/9/2024
|
Approved
|
SABAS ALONSO
|
|
METHANE-Rough
|
4/16/2024
|
Corrections Issued
|
SABAS ALONSO
|
|
METHANE-Rough
|
4/18/2024
|
Approved
|
SABAS ALONSO
|
|
BUILDING-Rough-Frame
|
4/19/2024
|
Approved
|
SABAS ALONSO
|
|
Green Building Rough
|
4/19/2024
|
Approved
|
SABAS ALONSO
|
|
Interior/Exterior Lathing
|
4/19/2024
|
Partial Approval
|
SABAS ALONSO
|
|
METHANE-Rough
|
4/19/2024
|
Approved
|
SABAS ALONSO
|
|
Verify Sprinkler Sign Off
|
4/19/2024
|
Approved
|
SABAS ALONSO
|
|
Insulation
|
4/23/2024
|
Corrections Issued
|
CRAIG DAVIS
|
|
Insulation
|
4/24/2024
|
Corrections Issued
|
SABAS ALONSO
|
|
Insulation
|
4/26/2024
|
Approved
|
SABAS ALONSO
|
|
Drywall Nailing
|
5/9/2024
|
Approved
|
SABAS ALONSO
|
|
PLUMBING-Rough
|
8/28/2024
|
Partial Approval
|
ALEJANDRO DE ARTOLA
|
|
Pre-Inspection
|
8/28/2024
|
Not Ready for Inspection
|
ALEJANDRO DE ARTOLA
|
|
Sewer
|
8/28/2024
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Underground Mechanical
|
8/28/2024
|
Approved
|
ALEJANDRO DE ARTOLA
|
|
Pre-Inspection
|
9/10/2024
|
Partial Inspection
|
SABAS ALONSO
|
|
HVAC-Final
|
10/21/2024
|
Corrections Issued
|
SABAS ALONSO
|
|
Interior/Exterior Lathing
|
10/21/2024
|
Corrections Issued
|
SABAS ALONSO
|
|
Interior/Exterior Lathing
|
10/23/2024
|
Approved
|
SABAS ALONSO
|
|
Interior/Exterior Lathing
|
10/24/2024
|
Approved
|
JOSH MEISTER
|
|
ELECTRICAL-Final
|
10/25/2024
|
Corrections Issued
|
CRAIG DAVIS
|
|
ELECTRICAL-Final
|
10/29/2024
|
Not Ready for Inspection
|
SABAS ALONSO
|
|
Interior/Exterior Lathing
|
10/29/2024
|
Approved
|
SABAS ALONSO
|
|
HVAC-Final
|
10/30/2024
|
Approved
|
SABAS ALONSO
|
|
ELECTRICAL-Final
|
11/5/2024
|
Not Ready for Inspection
|
SABAS ALONSO
|
|
Gas Test
|
11/5/2024
|
Not Ready for Inspection
|
SABAS ALONSO
|
|
PLUMBING-Final
|
11/5/2024
|
Not Ready for Inspection
|
SABAS ALONSO
|
|
SGSOV-Seismic Gas S/O Valve
|
11/5/2024
|
SGSOV Not Ready
|
SABAS ALONSO
|
|
Gas Test
|
11/7/2024
|
Approved
|
SABAS ALONSO
|
|
HVAC-Final
|
11/7/2024
|
Approved
|
SABAS ALONSO
|
|
PLUMBING-Final
|
11/7/2024
|
Approved
|
SABAS ALONSO
|
|
ELECTRICAL-Final
|
11/20/2024
|
Approved
|
SABAS ALONSO
|
|
Final
|
11/20/2024
|
Corrections Issued
|
SABAS ALONSO
|
|
Footing/Foundation/Slab
|
11/20/2024
|
Approved
|
SABAS ALONSO
|
|
Green Building Final
|
11/20/2024
|
Corrections Issued
|
SABAS ALONSO
|
|
SGSOV-Seismic Gas S/O Valve
|
11/20/2024
|
SGSOV Not Ready
|
SABAS ALONSO
|
|
Service/Power Release
|
11/20/2024
|
Not Ready for Inspection
|
SABAS ALONSO
|
|
Smoke Detectors
|
11/20/2024
|
Approved
|
SABAS ALONSO
|
|
Final
|
12/26/2024
|
Not Ready for Inspection
|
SABAS ALONSO
|
|
Green Building Final
|
12/26/2024
|
Approved
|
SABAS ALONSO
|
|
SGSOV-Seismic Gas S/O Valve
|
12/26/2024
|
SGSOV Approved
|
SABAS ALONSO
|
|
Service/Power Release
|
12/26/2024
|
Approved
|
SABAS ALONSO
|
|
Final
|
1/22/2025
|
OK to Issue CofO
|
SABAS ALONSO
|