4035 W MARATHON ST 1-2 90029
Certificate Information: 4035 W MARATHON ST 1-2 90029
- Application / Permit
- 22010-10000-06319
- Plan Check / Job No.
- B22LA25827
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- ePlan - NEW 3 STORY DUPLEXES WITH ATT. GARAGE (Building #1) per ab2097 no parking required
- Permit Issued
- Issued on 8/20/2025
- Issuing Office
- Current Status
- Issued on 8/20/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/21/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/2/2023 | TSE MING HUANG |
| Corrections Issued | 2/10/2023 | TSE MING HUANG |
| Quality Review Completed | 2/13/2023 | EUGENE BARBEAU |
| Applicant returned to address corrections | 7/21/2023 | TSE MING HUANG |
| Applicant returned to address corrections | 10/11/2023 | TSE MING HUANG |
| Plan Check Approved | 3/19/2024 | TSE MING HUANG |
| Issued | 8/20/2025 | APPLICANT |
Permit Application Clearance Information
| SB8 RUD | Cleared | 6/16/2023 | CHARLOTTE KINGS |
| Eng Process Fee Ord 176,300 | Cleared | 6/26/2023 | NEIL TUANO |
| Permit | Cleared | 6/26/2023 | NEIL TUANO |
| Grading Pre-Inspection | Cleared | 6/30/2023 | ALEXANDER HELFER |
| Hydrant and Access approval | Cleared | 6/30/2023 | LAVEON RIDER |
| Address approval | Cleared | 7/3/2023 | NEIL TUANO |
| Sewer availability | Cleared | 7/3/2023 | NEIL TUANO |
| Low Impact Development (LID) | Cleared | 9/25/2023 | ERNEST TSE |
| Roof/Waste drainage to street | Cleared | 9/27/2023 | JEANIE LAM |
| Miscellaneous | Cleared | 4/10/2025 | YINGSHI HUANG |
| Miscellaneous | Cleared | 4/24/2025 | YINGSHI HUANG |
| Miscellaneous | Cleared | 4/24/2025 | YINGSHI HUANG |
| Specific Plan | Cleared | 4/24/2025 | YINGSHI HUANG |
| Zoning Plan Check | Cleared | 7/3/2025 | NEVRIK NAVASARTIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lopez,, Mauricio; Lic. No.: C36801 | 1391 N THIRD AVE UPLAND, CA 91786 |
| Engineer | Markov,, George P; Lic. No.: C55855 | 1623 THOMPSON AVE GLENDALE, CA 91201 |
| Geologist | Miller,, Jonathan Steven; Lic. No.: EG2391 | 24736 CALVERT STREET WOODLAND HILLS, CA 91367 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/29/2025 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 8/29/2025 | Partial Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 9/19/2025 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 9/19/2025 | Partial Inspection | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 9/19/2025 | Partial Inspection | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 9/23/2025 | Approved | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 9/24/2025 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Rough | 10/8/2025 | Partial Approval | FREDDIE RIVERA |
| Deputy Steel/Welding | 10/14/2025 | Conditional Approval | FREDDIE RIVERA |
| Deputy Steel/Welding | 10/17/2025 | Conditional Approval | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 2/5/2026 | Not Ready for Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 2/5/2026 | Partial Approval | FREDDIE RIVERA |
| Green Building Rough | 2/5/2026 | Not Ready for Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 2/5/2026 | Partial Inspection | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 2/11/2026 | Partial Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 2/19/2026 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 2/19/2026 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 2/19/2026 | Corrections Issued | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 3/5/2026 | Partial Approval | FREDDIE RIVERA |
| Interior/Exterior Lathing | 3/19/2026 | Not Ready for Inspection | GEM DE OCAMPO |
| Interior/Exterior Lathing | 4/15/2026 | Not Ready for Inspection | OSVALDO PARAMO |
| HVAC-Final | 4/16/2026 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Rough | 4/16/2026 | Partial Inspection | FREDDIE RIVERA |
| ELECTRICAL-Rough | 4/30/2026 | Partial Inspection | FREDDIE RIVERA |
| HVAC-Rough | 4/30/2026 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 4/30/2026 | Corrections Issued | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 5/15/2026 | Partial Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 5/19/2026 | Corrections Issued | FREDDIE RIVERA |
| Green Building Rough | 5/19/2026 | Not Ready for Inspection | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 5/19/2026 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 7/20/2026 | Approved | FREDDIE RIVERA |