14926 W SUTTON ST 91403

Certificate Information: 14926 W SUTTON ST 91403

Application / Permit
22010-10000-06263
Plan Check / Job No.
B22LA25576
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
**ePlan** New 2-Story Single Family Dwelling w/ attached 2-car garage and attached Accessory Dwelling Unit per LAMC 12.22 A.33(c) and (e) - 1 of 2 -
Permit Issued
Issued on 5/12/2024
Issuing Office
Current Status
Issued on 5/12/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/20/2022 APPLICANT
Assigned to Plan Check Engineer 1/5/2023 EDWIN ESPIN
Corrections Issued 1/10/2023 EDWIN ESPIN
Quality Review Completed 1/12/2023 CHIHARU SUZUKI
Applicant returned to address corrections 5/3/2023 EDWIN ESPIN
Applicant returned to address corrections 7/13/2023 EDWIN ESPIN
Plan Check Approved 5/10/2024 EDWIN ESPIN
Issued 5/12/2024 APPLICANT

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/19/2023 COLIN LOREDO
Sewer availability Cleared 1/19/2023 COLIN LOREDO
Hydrant and Access approval Cleared 2/17/2023 RUEL COLE
Low Impact Development Cleared 3/9/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 3/10/2023 COLIN LOREDO
Trees in Parkway Cleared 3/16/2023 RICHARD SANCHEZ
GPI Written Notices Cleared 5/2/2023 EDWIN ESPIN
Grading Pre-Inspection Cleared 5/2/2023 EDWIN ESPIN
Permit Cleared 12/14/2023 COLIN LOREDO
Address approval Cleared 2/26/2024 CARLOS AGUILERA
Sewer availability Cleared 2/27/2024 CARLOS AGUILERA
Low Impact Development (LID) Cleared 2/28/2024 ERNEST TSE
Hydrant and Access approval Cleared 3/19/2024 RUEL COLE
Roof/Waste drainage to street Cleared 3/27/2024 CARLOS AGUILERA
Trees in Parkway Cleared 4/1/2024 ADALBERTO VERA
Permit Cleared 4/2/2024 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Wang,, Hongyu; Lic. No.: C72679 8887 W FALMINGO RD STE 101      LAS VEGAS, NV 89147

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/8/2024 Partial Approval JACK KARGODORIAN
Footing/Foundation/Slab 8/28/2024 Corrections Issued JACK KARGODORIAN
Footing/Foundation/Slab 9/5/2024 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 10/21/2024 Partial Approval JACK KARGODORIAN
Deputy Wood Construction 11/20/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 11/20/2024 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 11/22/2024 Approved JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 1/16/2025 Corrections Issued JACK KARGODORIAN
PLUMBING-Rough 1/16/2025 Approved JACK KARGODORIAN
Shower Pan 3/5/2025 Approved JACK KARGODORIAN
ELECTRICAL-Rough 3/18/2025 Corrections Issued JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 4/23/2025 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 6/9/2025 Approved JACK KARGODORIAN
ELECTRICAL-Rough 6/9/2025 Approved JACK KARGODORIAN
Green Building Rough 6/9/2025 Approved JACK KARGODORIAN
Interior/Exterior Lathing 6/9/2025 Partial Approval JACK KARGODORIAN
Verify Sprinkler Sign Off 6/9/2025 Approved JACK KARGODORIAN
Insulation 6/26/2025 Approved JACK KARGODORIAN
Insulation 6/30/2025 Approved LOUIS ESCOTO
Drywall Nailing 7/10/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 7/10/2025 Approved MICHAEL CORTEZ
HVAC-Rough 2/10/2026 Approved JACK KARGODORIAN
Underground Mechanical 2/10/2026 Approved JACK KARGODORIAN
ELECTRICAL-Final 5/15/2026 Approved JAVIER RAMOS JR
HVAC-Final 5/15/2026 Approved JAVIER RAMOS JR
PLUMBING-Final 5/15/2026 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 5/15/2026 SGSOV Not Required JAVIER RAMOS JR
Smoke Detectors 5/15/2026 Approved JAVIER RAMOS JR