1425 N HAZELWOOD AVE 90041
Certificate Information: 1425 N HAZELWOOD AVE 90041
- Application / Permit
- 22010-10000-06247
- Plan Check / Job No.
- B22LA25545
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: (N) 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 6/8/2023
- Issuing Office
- Current Status
- CofO Issued on 7/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/27/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2023 | DANIEL YIP |
| Corrections Issued | 1/4/2023 | DANIEL YIP |
| Applicant returned to address corrections | 1/23/2023 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 5/4/2023 | JOSEPH RAFOLS |
| Plan Check Approved | 6/1/2023 | DANIEL YIP |
| Issued | 6/8/2023 | APPLICANT |
| CofO in Progress | 7/9/2026 | RONNIE MEDINA |
| Permit Finaled | 7/9/2026 | DEROLD HAUFF |
| CofO Issued | 7/9/2026 | DEROLD HAUFF |
| Permit Finaled | 7/9/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/6/2023 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 1/9/2023 | CINDY QI |
| Sewer availability | Cleared | 1/9/2023 | CINDY QI |
| Miscellaneous | Cleared | 1/12/2023 | KIRK LINKLATER |
| Grading Pre-Inspection | Cleared | 1/20/2023 | KIRK LINKLATER |
| GPI Written Notices | Cleared | 5/4/2023 | DANIEL YIP |
| Low Impact Development (LID) | Cleared | 5/9/2023 | MELINEH AGHAKHABIAN |
| Roof/Waste drainage to street | Cleared | 5/10/2023 | JEREMY CHOK |
Contact Information
| Architect | Hizon,, Vicente Ruiz; Lic. No.: C18744 | 16736 ALMADEN DRIVE FONTANA, CA 92336 |
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/19/2023 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 8/30/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 9/6/2023 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 9/15/2023 | No Access for Inspection | ROY SPAULDING |
| Green Building Rough | 9/15/2023 | No Access for Inspection | ROY SPAULDING |
| Verify Sprinkler Sign Off | 9/15/2023 | No Access for Inspection | ROY SPAULDING |
| BUILDING-Rough-Frame | 9/20/2023 | Partial Approval | ROY SPAULDING |
| Green Building Rough | 9/20/2023 | Not Ready for Inspection | ROY SPAULDING |
| Verify Sprinkler Sign Off | 9/20/2023 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 10/10/2023 | Corrections Issued | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2023 | Approved | ROY SPAULDING |
| Green Building Rough | 10/10/2023 | Not Ready for Inspection | ROY SPAULDING |
| BUILDING-Rough-Frame | 10/17/2023 | Not Ready for Inspection | ROY SPAULDING |
| Green Building Rough | 10/17/2023 | Corrections Issued | ROY SPAULDING |
| BUILDING-Rough-Frame | 10/24/2023 | Corrections Issued | SCOTT FINNILA |
| Green Building Rough | 10/24/2023 | Not Ready for Inspection | SCOTT FINNILA |
| Rough-Elec/Plmb/HVAC | 10/24/2023 | Corrections Issued | SCOTT FINNILA |
| BUILDING-Rough-Frame | 10/31/2023 | Not Ready for Inspection | ROY SPAULDING |
| Green Building Rough | 10/31/2023 | Corrections Issued | ROY SPAULDING |
| BUILDING-Rough-Frame | 11/3/2023 | Corrections Issued | ROY SPAULDING |
| Green Building Rough | 11/3/2023 | Not Ready for Inspection | ROY SPAULDING |
| PLUMBING-Rough | 11/3/2023 | Partial Approval | ROY SPAULDING |
| ELECTRICAL-Rough | 11/7/2023 | Approved | ROY SPAULDING |
| Insulation | 11/17/2023 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 11/17/2023 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 11/21/2023 | Approved | ROY SPAULDING |
| Gas Test | 11/21/2023 | Approved | ROY SPAULDING |
| Green Building Rough | 11/21/2023 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 11/21/2023 | Approved | ROY SPAULDING |
| Sewer | 11/21/2023 | Approved | ROY SPAULDING |
| Underground Mechanical | 11/21/2023 | Approved | ROY SPAULDING |
| Underground Mechanical | 11/28/2023 | Approved | ROY SPAULDING |
| ELECTRICAL-Final | 1/19/2024 | Approved | ROY SPAULDING |
| PLUMBING-Final | 1/19/2024 | Corrections Issued | ROY SPAULDING |
| BUILDING-Rough-Frame | 1/25/2024 | Partial Approval | ROY SPAULDING |
| Final | 1/25/2024 | Corrections Issued | ROY SPAULDING |
| Green Building Final | 1/25/2024 | Corrections Issued | ROY SPAULDING |
| PLUMBING-Final | 1/25/2024 | Partial Approval | ROY SPAULDING |
| SGSOV-Seismic Gas S/O Valve | 1/25/2024 | SGSOV Not Ready | ROY SPAULDING |
| Service/Power Release | 1/25/2024 | Not Ready for Inspection | ROY SPAULDING |
| Smoke Detectors | 1/25/2024 | Approved | ROY SPAULDING |
| BUILDING-Rough-Frame | 6/16/2026 | Approved | RONNIE MEDINA |
| Final | 6/16/2026 | Corrections Issued | RONNIE MEDINA |
| Green Building Final | 6/16/2026 | Not Ready for Inspection | RONNIE MEDINA |
| SGSOV-Seismic Gas S/O Valve | 6/16/2026 | SGSOV Approved | RONNIE MEDINA |
| Service/Power Release | 6/16/2026 | Not Ready for Inspection | RONNIE MEDINA |
| Final | 7/8/2026 | OK to Issue CofO | RONNIE MEDINA |
| Green Building Final | 7/8/2026 | Approved | RONNIE MEDINA |
| Service/Power Release | 7/8/2026 | Approved | RONNIE MEDINA |