1425 N HAZELWOOD AVE 90041

Certificate Information: 1425 N HAZELWOOD AVE 90041

Application / Permit
22010-10000-06247
Plan Check / Job No.
B22LA25545
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 6/8/2023
Issuing Office
Current Status
CofO Issued on 7/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2022 APPLICANT
Assigned to Plan Check Engineer 1/3/2023 DANIEL YIP
Corrections Issued 1/4/2023 DANIEL YIP
Applicant returned to address corrections 1/23/2023 JOSEPH RAFOLS
Applicant returned to address corrections 5/4/2023 JOSEPH RAFOLS
Plan Check Approved 6/1/2023 DANIEL YIP
Issued 6/8/2023 APPLICANT
CofO in Progress 7/9/2026 RONNIE MEDINA
Permit Finaled 7/9/2026 DEROLD HAUFF
CofO Issued 7/9/2026 DEROLD HAUFF
Permit Finaled 7/9/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/6/2023 CINDY QI
Eng Process Fee Ord 176,300 Cleared 1/9/2023 CINDY QI
Sewer availability Cleared 1/9/2023 CINDY QI
Miscellaneous Cleared 1/12/2023 KIRK LINKLATER
Grading Pre-Inspection Cleared 1/20/2023 KIRK LINKLATER
GPI Written Notices Cleared 5/4/2023 DANIEL YIP
Low Impact Development (LID) Cleared 5/9/2023 MELINEH AGHAKHABIAN
Roof/Waste drainage to street Cleared 5/10/2023 JEREMY CHOK

Contact Information

Architect Hizon,, Vicente Ruiz; Lic. No.: C18744 16736 ALMADEN DRIVE      FONTANA, CA 92336
Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/19/2023 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 8/30/2023 Not Ready for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 9/6/2023 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 9/15/2023 No Access for Inspection ROY SPAULDING
Green Building Rough 9/15/2023 No Access for Inspection ROY SPAULDING
Verify Sprinkler Sign Off 9/15/2023 No Access for Inspection ROY SPAULDING
BUILDING-Rough-Frame 9/20/2023 Partial Approval ROY SPAULDING
Green Building Rough 9/20/2023 Not Ready for Inspection ROY SPAULDING
Verify Sprinkler Sign Off 9/20/2023 Approved ROY SPAULDING
BUILDING-Rough-Frame 10/10/2023 Corrections Issued ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 10/10/2023 Approved ROY SPAULDING
Green Building Rough 10/10/2023 Not Ready for Inspection ROY SPAULDING
BUILDING-Rough-Frame 10/17/2023 Not Ready for Inspection ROY SPAULDING
Green Building Rough 10/17/2023 Corrections Issued ROY SPAULDING
BUILDING-Rough-Frame 10/24/2023 Corrections Issued SCOTT FINNILA
Green Building Rough 10/24/2023 Not Ready for Inspection SCOTT FINNILA
Rough-Elec/Plmb/HVAC 10/24/2023 Corrections Issued SCOTT FINNILA
BUILDING-Rough-Frame 10/31/2023 Not Ready for Inspection ROY SPAULDING
Green Building Rough 10/31/2023 Corrections Issued ROY SPAULDING
BUILDING-Rough-Frame 11/3/2023 Corrections Issued ROY SPAULDING
Green Building Rough 11/3/2023 Not Ready for Inspection ROY SPAULDING
PLUMBING-Rough 11/3/2023 Partial Approval ROY SPAULDING
ELECTRICAL-Rough 11/7/2023 Approved ROY SPAULDING
Insulation 11/17/2023 Approved CRAIG VAUGHAN
Interior/Exterior Lathing 11/17/2023 Approved CRAIG VAUGHAN
Drywall Nailing 11/21/2023 Approved ROY SPAULDING
Gas Test 11/21/2023 Approved ROY SPAULDING
Green Building Rough 11/21/2023 Approved ROY SPAULDING
PLUMBING-Rough 11/21/2023 Approved ROY SPAULDING
Sewer 11/21/2023 Approved ROY SPAULDING
Underground Mechanical 11/21/2023 Approved ROY SPAULDING
Underground Mechanical 11/28/2023 Approved ROY SPAULDING
ELECTRICAL-Final 1/19/2024 Approved ROY SPAULDING
PLUMBING-Final 1/19/2024 Corrections Issued ROY SPAULDING
BUILDING-Rough-Frame 1/25/2024 Partial Approval ROY SPAULDING
Final 1/25/2024 Corrections Issued ROY SPAULDING
Green Building Final 1/25/2024 Corrections Issued ROY SPAULDING
PLUMBING-Final 1/25/2024 Partial Approval ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 1/25/2024 SGSOV Not Ready ROY SPAULDING
Service/Power Release 1/25/2024 Not Ready for Inspection ROY SPAULDING
Smoke Detectors 1/25/2024 Approved ROY SPAULDING
BUILDING-Rough-Frame 6/16/2026 Approved RONNIE MEDINA
Final 6/16/2026 Corrections Issued RONNIE MEDINA
Green Building Final 6/16/2026 Not Ready for Inspection RONNIE MEDINA
SGSOV-Seismic Gas S/O Valve 6/16/2026 SGSOV Approved RONNIE MEDINA
Service/Power Release 6/16/2026 Not Ready for Inspection RONNIE MEDINA
Final 7/8/2026 OK to Issue CofO RONNIE MEDINA
Green Building Final 7/8/2026 Approved RONNIE MEDINA
Service/Power Release 7/8/2026 Approved RONNIE MEDINA