1230 N LA COLLINA DR 90069
Certificate Information: 1230 N LA COLLINA DR 90069
- Application / Permit
- 22010-10000-06239
- Plan Check / Job No.
- B22LA25520
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- ePLAN- New Detached Garage per ZA-2021-10251-ZAA.
- Permit Issued
- Issued on 3/2/2023
- Issuing Office
- Current Status
- CofO Issued on 12/22/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/5/2023 | JAD BASMA |
| Corrections Issued | 1/7/2023 | JAD BASMA |
| Quality Review Completed | 1/13/2023 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 2/9/2023 | JAD BASMA |
| Applicant returned to address corrections | 2/16/2023 | JAD BASMA |
| Plan Check Approved | 2/27/2023 | JAD BASMA |
| Issued | 3/2/2023 | APPLICANT |
| CofO in Progress | 12/8/2023 | RAUL BARAJAS |
| Permit Finaled | 12/22/2023 | DEROLD HAUFF |
| CofO Issued | 12/22/2023 | DEROLD HAUFF |
| Permit Finaled | 12/22/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2023 | TREVOR QUAN |
| Permit | Cleared | 1/10/2023 | TREVOR QUAN |
| GPI Written Notices | Cleared | 2/15/2023 | JAD BASMA |
| Grading Pre-Inspection | Cleared | 2/15/2023 | JAD BASMA |
| Private street | Cleared | 2/16/2023 | MAYELA VILLA |
| ZA Case | Cleared | 2/16/2023 | MAYELA VILLA |
| Low Impact Development | Cleared | 2/27/2023 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 2/27/2023 | JEANIE LAM |
Contact Information
| Contractor | J R C Group Inc; Lic. No.: 980658-B | 8981 SUNSET BLVD STE 505 LOS ANGELES, CA 90069 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/24/2023 | Approved | RAUL BARAJAS |
| Piling/Pier/Caisson | 3/24/2023 | Partial Approval | RAUL BARAJAS |
| Underground Mechanical | 3/24/2023 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 4/5/2023 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 5/11/2023 | Approved | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2023 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 7/31/2023 | Approved | STUART CHAPMAN |
| HVAC-Rough | 7/31/2023 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 8/8/2023 | Not Ready for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 8/15/2023 | Approved | RAUL BARAJAS |
| Drywall Nailing | 8/29/2023 | Approved | RAUL BARAJAS |
| Final | 10/4/2023 | Corrections Issued | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 10/4/2023 | SGSOV Approved | RAUL BARAJAS |
| Service/Power Release | 10/4/2023 | Not Required | RAUL BARAJAS |
| Smoke Detectors | 10/4/2023 | Approved | RAUL BARAJAS |
| Final | 11/21/2023 | Corrections Issued | RAUL BARAJAS |
| Final | 12/1/2023 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 12/8/2023 | OK to Issue CofO | RAUL BARAJAS |