2220-2222 S MALCOLM AVE 90064

Certificate Information: 2220-2222 S MALCOLM AVE 90064

Application / Permit
22010-10000-06193
Plan Check / Job No.
B22LA25318
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2 STORY SFD WITH ATTACHED ADU AND ATTACHED GARAGE ADU PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 5/31/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 9/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/14/2022 APPLICANT
Assigned to Plan Check Engineer 12/29/2022 JAD BASMA
Corrections Issued 1/2/2023 JAD BASMA
Quality Review Completed 1/10/2023 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 1/12/2023 APPLICANT
Plan Check Approved 5/26/2023 JAD BASMA
Issued 5/31/2023 APPLICANT
CofO in Progress 9/16/2025 DANIEL VERA
Permit Finaled 9/18/2025 RICHARD STEINBACH
CofO Issued 9/18/2025 RICHARD STEINBACH
Permit Finaled 9/18/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 3/14/2023 CATHERINE ADROVER
Permit Cleared 3/14/2023 CATHERINE ADROVER
Specific Plan Cleared 3/17/2023 EDUARDO HERMOSO
Eng Process Fee Ord 176,300 Cleared 3/20/2023 CATHERINE ADROVER
Sewer availability Cleared 3/20/2023 CATHERINE ADROVER
Hydrant and Access approval Cleared 3/24/2023 MATTHEW CRAIG
Trees in Parkway Cleared 4/29/2023 ADALBERTO VERA
Low Impact Development Cleared 5/4/2023 TOMMY YIN
Roof/Waste drainage to street Cleared 5/11/2023 LIAM ODONOVAN
GPI Written Notices Cleared 5/26/2023 JAD BASMA
Grading Pre-Inspection Cleared 5/26/2023 JAD BASMA

Contact Information

Contractor Dorin Development; Lic. No.: 309855-B 4214 IRVING PLACE      CULVER CITY, CA 90232

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/5/2023 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 10/4/2023 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 10/13/2023 Partial Approval JESUS PINEDA
BUILDING-Rough-Frame 10/27/2023 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 10/27/2023 Partial Approval STEPHANIE SWANSON
PLUMBING-Rough 10/27/2023 Corrections Issued STEPHANIE SWANSON
PLUMBING-Rough 10/31/2023 Partial Approval BEN MOLSTAD
Footing/Foundation/Slab 11/14/2023 Approved MEL KHACHATOURIAN
Deputy Drilled-In Anchors 1/9/2024 Conditional Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 1/17/2024 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 3/28/2024 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 4/15/2024 Approved JESUS PINEDA
PLUMBING-Rough 4/19/2024 Approved STEPHANIE SWANSON
ELECTRICAL-Rough 5/8/2024 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 5/8/2024 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 5/9/2024 Corrections Issued JESUS PINEDA
HVAC-Rough 5/17/2024 Not Ready for Inspection JESUS PINEDA
ELECTRICAL-Rough 5/24/2024 Approved TEMISTOCLES CAAL
HVAC-Rough 5/24/2024 Approved TEMISTOCLES CAAL
BUILDING-Rough-Frame 6/11/2024 Approved JESUS PINEDA
Green Building Rough 6/11/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 6/11/2024 Partial Approval JESUS PINEDA
Verify Sprinkler Sign Off 6/11/2024 Approved JESUS PINEDA
Insulation 6/28/2024 Approved CARLOS MATAMOROS
Drywall Nailing 7/12/2024 Approved KIRK SANDERS
Interior/Exterior Lathing 8/7/2024 Approved CHRISTOPHER WILSON
Shower Pan 8/7/2024 Approved CHRISTOPHER WILSON
PLUMBING-Rough 10/11/2024 Approved REGINA MENDEZ
PLUMBING-Rough 12/17/2024 Partial Approval ARAM AVEDISIAN
Gas Test 2/7/2025 Approved DANIEL VERA
HVAC-Final 2/12/2025 Approved EVAN COOPER
ELECTRICAL-Final 2/19/2025 Corrections Issued KIRK SANDERS
PLUMBING-Final 2/19/2025 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Final 3/12/2025 Approved WILBER ROSALES
HVAC-Final 3/12/2025 Approved WILBER ROSALES
Special/Order Compliance 3/12/2025 Partial Inspection STEPHANIE SWANSON
ELECTRICAL-Final 3/26/2025 Approved CARLOS MATAMOROS
PLUMBING-Final 3/26/2025 Approved CARLOS MATAMOROS
Service/Power Release 3/26/2025 Approved CARLOS MATAMOROS
Service/Power Release 4/9/2025 Approved MICHAEL PELHAM
Final 5/13/2025 Corrections Issued WILBER ROSALES
Green Building Final 5/13/2025 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 5/13/2025 SGSOV Not Ready WILBER ROSALES
Smoke Detectors 5/13/2025 Approved WILBER ROSALES
Final 9/15/2025 OK to Issue CofO DANIEL VERA
SGSOV-Seismic Gas S/O Valve 9/15/2025 SGSOV Approved DANIEL VERA