4445 E MERCURY AVE 1-8 90032

Certificate Information: 4445 E MERCURY AVE 1-8 90032

Application / Permit
22010-10000-06142
Plan Check / Job No.
B22LA25172
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 3-STORY 100% AFFORDABLE APARTMENT BUILDING WITH GARAGE (BUILDINGS E).
Permit Issued
Issued on 3/19/2025
Issuing Office
Metro
Current Status
Issued on 3/19/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/13/2022 APPLICANT
Assigned to Plan Check Engineer 12/29/2022 FARSHAD ALIMOHAMADI
Corrections Issued 1/10/2023 FARSHAD ALIMOHAMADI
Quality Review Completed 1/11/2023 KEN GILL
Building Plans Picked Up 1/23/2023 APPLICANT
Disabled Access Plans Picked Up 3/29/2023 APPLICANT
Green Plans Picked Up 6/1/2023 APPLICANT
Applicant returned to address corrections 4/9/2024 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 7/12/2024 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 7/24/2024 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 10/23/2024 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 10/24/2024 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 10/25/2024 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 10/29/2024 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 1/22/2025 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 2/21/2025 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 3/11/2025 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 3/18/2025 FARSHAD ALIMOHAMADI
Plan Check Approved 3/19/2025 FARSHAD ALIMOHAMADI
Issued 3/19/2025 APPLICANT

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 1/16/2024 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 1/16/2024 ADRIAN SANCHEZ
BHO/Hillside ordinance Cleared 1/16/2024 ADRIAN SANCHEZ
Address approval Cleared 1/18/2024 CHRISTINA BRACO
Building over 36-ft Cleared 4/9/2024 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 4/9/2024 CALOSHA APPROVED
Public Housing Cleared 4/25/2024 GLEN OLIVER
Hydrant and Access approval Cleared 5/31/2024 LAVEON RIDER
Driveway location Cleared 6/3/2024 JIMMY VIVAR
Internal circulation Cleared 6/3/2024 JIMMY VIVAR
Green Code Cleared 7/16/2024 FARSHAD ALIMOHAMADI
GPI Written Notices Cleared 10/24/2024 FARSHAD ALIMOHAMADI
Grading Pre-Inspection Cleared 10/24/2024 FARSHAD ALIMOHAMADI
Sewer availability Cleared 11/5/2024 JUSTIN BICOL
Highway dedication Cleared 11/18/2024 STEVE MELGAR
Permit Cleared 11/18/2024 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 11/22/2024 STEVE MELGAR
Fire Marshal Fire Life Safety Cleared 1/12/2025 ANDREW KO
ZI Cleared 1/22/2025 JAZMIN ROQUE
DAS Clearance Cleared 1/28/2025 FARSHAD ALIMOHAMADI
"D" conditions Cleared 2/4/2025 JAZMIN ROQUE
Frnt yard landscape/Water mgmt Cleared 2/4/2025 JAZMIN ROQUE
Opn space landscape/Water mgmt Cleared 2/4/2025 JAZMIN ROQUE
Construction near power lines Cleared 2/19/2025 RIDWAN HARDY
Stormwater Pollution Mitigatn Cleared 2/23/2025 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 2/25/2025 MATIAS FARFAN
DCP conditions approval Cleared 2/27/2025 KE ZHANG
Density Bonus Cleared 2/27/2025 KE ZHANG
SB8 RUD Cleared 2/27/2025 KE ZHANG
"Q" conditions Cleared 3/6/2025 JAZMIN ROQUE
Disturb/Remove Protected Trees Cleared 3/11/2025 ADALBERTO VERA
Trees in Parkway Cleared 3/11/2025 PEDRO ZUNIGA

Contact Information

Architect Swift,, Daniel R; Lic. No.: C32860 4601 WESTOWN PARKWAY SUITE 208      WEST DES MOINES, IA 50266
Contractor Olson R D Construction Inc; Lic. No.: 953845-B 400 SPECTRUM CENTER DR   STE 1200    IRVINE, CA 92618
Engineer Clandening,, Kurtis James; Lic. No.: S3926 1518 18TH STREET #1      SANTA MONICA, CA 90404

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/21/2025 Approved RAFAEL CORTES
Footing/Foundation/Slab 9/26/2025 Partial Approval RAFAEL CORTES
Footing/Foundation/Slab 10/8/2025 Partial Approval RAFAEL CORTES
Excavation/Setback/Form/Re-Bar 11/13/2025 Partial Approval RAFAEL CORTES
Special/Order Compliance 11/13/2025 Partial Approval SCOTT SOBEL
Floor/Roof Diaphrgm/Shear Wall 12/4/2025 Not Ready for Inspection RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 12/8/2025 Partial Approval RAFAEL CORTES
Deputy Fireproofing 12/18/2025 Conditional Approval RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 12/18/2025 Partial Inspection RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 1/6/2026 Not Ready for Inspection RAFAEL CORTES
Floor/Roof Diaphrgm/Shear Wall 1/21/2026 Partial Approval RAFAEL CORTES
Insulation 2/27/2026 Partial Approval RAFAEL CORTES
Insulation 3/9/2026 Partial Approval RAFAEL CORTES
Wood Frame 3/23/2026 Partial Approval RAFAEL CORTES
Wood Frame 3/26/2026 Partial Approval RAFAEL CORTES
Interior/Exterior Lathing 4/1/2026 Partial Approval RAFAEL CORTES
Insulation 4/2/2026 Partial Approval RAFAEL CORTES
Light Gage Steel Frame 4/2/2026 Not Ready for Inspection RAFAEL CORTES
Light Gage Steel Frame 4/6/2026 Partial Approval RONALD JIMENEZ
Insulation 4/13/2026 Partial Approval RAFAEL CORTES
Insulation 4/17/2026 Partial Approval RAFAEL CORTES
Wood Frame 4/21/2026 Partial Approval RAFAEL CORTES
Insulation 4/27/2026 Partial Approval RAFAEL CORTES
Drywall Nailing 4/30/2026 Partial Approval RAFAEL CORTES
Insulation 4/30/2026 Not Ready for Inspection RAFAEL CORTES
Insulation 5/5/2026 Not Ready for Inspection RAFAEL CORTES
Light Gage Steel Frame 5/5/2026 Not Ready for Inspection RAFAEL CORTES
Light Gage Steel Frame 5/7/2026 Partial Approval RAFAEL CORTES
Drywall Nailing 5/12/2026 Approved RAFAEL CORTES
Light Gage Steel Frame 5/15/2026 Partial Approval RAFAEL CORTES
Interior/Exterior Lathing 5/26/2026 Partial Approval RAFAEL CORTES