728 N LAGOON AVE 1-40 90744
Certificate Information: 728 N LAGOON AVE 1-40 90744
- Application / Permit
- 22010-10000-06052
- Plan Check / Job No.
- B22LA25038
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- (N) 100% AFFORDABLE, QUALIFIED PERMANENT SUPPORTIVE HOUSING APARTMENT BUILDING WITH 40 TOTAL UNITS
- Permit Issued
- Issued on 12/12/2025
- Issuing Office
- Current Status
- Issued on 12/12/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/14/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2022 | HERNAN ARREOLA |
| Corrections Issued | 1/15/2023 | HERNAN ARREOLA |
| Quality Review Completed | 1/18/2023 | TEODORO DIAZ RODRIGUEZ |
| Disabled Access Plans Picked Up | 3/29/2023 | APPLICANT |
| Plan Check Approved | 12/12/2025 | HERNAN ARREOLA |
| Issued | 12/12/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/9/2023 | ADRIAN SANCHEZ |
| Highway dedication | Cleared | 5/9/2023 | ADRIAN SANCHEZ |
| Permit | Cleared | 5/16/2023 | ADRIAN SANCHEZ |
| Green Code | Cleared | 5/23/2023 | AARON COSTA |
| Construction near power lines | Cleared | 5/24/2023 | TINA MIRANDA |
| "Q" conditions | Cleared | 6/20/2023 | MIGUEL GAMBOA |
| Eng Process Fee Ord 176,300 | Cleared | 6/20/2023 | ANA SORIANO |
| Frnt yard landscape/Water mgmt | Cleared | 6/20/2023 | MIGUEL GAMBOA |
| Opn space landscape/Water mgmt | Cleared | 6/20/2023 | MIGUEL GAMBOA |
| Clean Up Green Up | Cleared | 7/3/2023 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 7/26/2023 | GISELLE CORELLA |
| Permanent Supportive Housing | Cleared | 8/14/2023 | MIGUEL GAMBOA |
| Hydrant and Access approval | Cleared | 5/14/2024 | LAVEON RIDER |
| Fire Marshal Fire Life Safety | Cleared | 11/3/2025 | MENOA AGHAJANI |
| Sewer availability | Cleared | 11/24/2025 | ERIK BEASLEY |
| Low Impact Development | Cleared | 11/25/2025 | ORVAL HERNANDEZ-MARCI |
| SB8 RUD | Cleared | 12/9/2025 | SAMANTHA RIVERA |
| DAS Clearance | Cleared | 12/10/2025 | HERNAN ARREOLA |
| Roof/Waste drainage to street | Cleared | 12/10/2025 | ARMEN MEHRABIAN |
| Public Housing | Cleared | 12/11/2025 | LUIS ALVAREZ |
Contact Information
| Architect | O'Herlihy,, Lorcan Patrick; Lic. No.: C24245 | 4106 W JEFFERSON BLVD LOS ANGELES, CA 90016 |
| Contractor | G B Construction Inc; Lic. No.: 424458-B | 18032 LEMON DRIVE STE C-344 YORBA LINDA, CA 92886 |
| Engineer | Cann,, Stephen Garth; Lic. No.: C78041 | 1081 CRIMSON DR SAN MARCOS, CA 92069 |
| Engineer | Hicks,, Joseph M; Lic. No.: C93183 | 500 N VICTORY BLVD BURBANK, CA 91502 |
| Engineer | Mahlow,, Elizabeth Joy Johnson; Lic. No.: C80463 | 5050 EAGLE ROCK BOULEVARD LOS ANGELES, CA 90041 |
Inspector Information
| No Data Available. |
Pending Inspections
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2026 Time Frame: 12-2 |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2026 |
Inspection Request History
| Pre-Inspection | 2/18/2026 | Approved | DAVID TSAU |
| Pre-Inspection | 3/12/2026 | Partial Approval | DAVID TSAU |
| Excavation/Setback/Form/Re-Bar | 3/16/2026 | Partial Inspection | DAVID TSAU |
| Pre-Inspection | 4/3/2026 | Partial Inspection | DAVID TSAU |
| Pre-Inspection | 4/20/2026 | Partial Inspection | DAVID TSAU |
| Excavation/Setback/Form/Re-Bar | 5/11/2026 | Partial Inspection | DAVID TSAU |
| METHANE-Barrier | 5/26/2026 | Partial Approval | DAVID TSAU |
| METHANE-Subgrade | 5/27/2026 | Conditional Approval | DAVID TSAU |
| METHANE-Subgrade | 5/29/2026 | Partial Approval | DAVID TSAU |
| METHANE-Barrier | 6/5/2026 | Approved | DAVID TSAU |
| Footing/Foundation/Slab | 6/11/2026 | Partial Approval | DAVID TSAU |
| METHANE-Subgrade | 6/11/2026 | Partial Approval | DAVID TSAU |
| Deputy Reinf. Concrete | 6/29/2026 | Conditional Approval | MICHAEL PETRUSKO |
| Reinforced Concrete Frame | 6/30/2026 | Partial Approval | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 7/1/2026 | Conditional Approval | MICHAEL PETRUSKO |
| Footing/Foundation/Slab | 7/10/2026 | Partial Inspection | DAVID TSAU |
| METHANE-Subgrade | 7/10/2026 | Conditional Approval | DAVID TSAU |
| Reinforced Concrete Frame | 7/17/2026 | Not Ready for Inspection | DAVID TSAU |
| Green Building Rough | 7/20/2026 | Not Ready for Inspection | DAVID TSAU |
| METHANE-Rough | 7/20/2026 | Not Ready for Inspection | DAVID TSAU |
| Reinforced Concrete Frame | 7/20/2026 | Partial Approval | DAVID TSAU |
| Reinforced Masonry Frame | 7/20/2026 | Not Ready for Inspection | DAVID TSAU |
| Verify Sprinkler Sign Off | 7/20/2026 | Not Ready for Inspection | DAVID TSAU |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2026 | Partial Approval | DAVID TSAU |