3601 S MAY ST 90066

Certificate Information: 3601 S MAY ST 90066

Application / Permit
22010-10000-06002
Plan Check / Job No.
B22LA24825
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New Construction - 2 story SFD w/ Attached Garage
Permit Issued
Issued on 7/10/2023
Issuing Office
Current Status
CofO Issued on 8/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/13/2022 APPLICANT
Assigned to Plan Check Engineer 12/23/2022 JOE VO
Corrections Issued 12/27/2022 JOE VO
Quality Review Completed 12/27/2022 GARO TELMI
Applicant returned to address corrections 2/27/2023 JOE VO
Plan Check Approved 6/30/2023 JOE VO
Issued 7/10/2023 APPLICANT
CofO in Progress 8/27/2024 JESUS PINEDA
Permit Finaled 8/30/2024 RICHARD STEINBACH
CofO Issued 8/30/2024 RICHARD STEINBACH
Permit Finaled 8/30/2024 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/3/2023 RAYMOND MUGAMBWA
Hydrant and Access approval Cleared 1/28/2023 KURT CORRAL
Permit Cleared 3/9/2023 JASON NG
Specific Plan Cleared 3/14/2023 FREDDY GARCIA
Sewer availability Cleared 4/3/2023 JASON NG
Low Impact Development Cleared 5/30/2023 LUIS LUVANO
Roof/Waste drainage to street Cleared 6/2/2023 JASON NG
Grading Pre-Inspection Cleared 6/30/2023 JOE VO

Contact Information

Architect Niemerski,, Kenneth Chester; Lic. No.: NA23971       ,
Contractor Gaudenti & Sons Corporation; Lic. No.: 283650-B 20331 MAIN ST      CARSON, CA 90745
Engineer Nguyen,, Huan; Lic. No.: NA64238       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/20/2023 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 7/20/2023 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 7/20/2023 Corrections Issued JESUS RODRIGUEZ
Sewer 7/20/2023 Corrections Issued JESUS RODRIGUEZ
Underground Mechanical 7/20/2023 Corrections Issued JESUS RODRIGUEZ
Excavation/Setback/Form/Re-Bar 7/25/2023 Not Ready for Inspection JESUS RODRIGUEZ
Footing/Foundation/Slab 7/25/2023 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 7/25/2023 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 8/28/2023 Partial Approval JESUS RODRIGUEZ
Deputy Reinf. Concrete 8/30/2023 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 9/6/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 11/1/2023 Not Ready for Inspection HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 11/1/2023 Partial Approval HERBERT GIRON
Green Building Rough 11/1/2023 Not Ready for Inspection HERBERT GIRON
Verify Sprinkler Sign Off 11/1/2023 Not Ready for Inspection HERBERT GIRON
ELECTRICAL-Rough 11/20/2023 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 11/20/2023 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 11/29/2023 Corrections Issued TEMISTOCLES CAAL
PLUMBING-Rough 11/29/2023 Not Ready for Inspection TEMISTOCLES CAAL
Interior/Exterior Lathing 12/20/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 1/26/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 1/26/2024 Conditional Approval JESUS RODRIGUEZ
HVAC-Rough 1/26/2024 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 1/26/2024 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Rough 1/30/2024 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 1/30/2024 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Rough 2/6/2024 Approved JESUS RODRIGUEZ
HVAC-Rough 2/6/2024 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 2/6/2024 Corrections Issued JESUS RODRIGUEZ
HVAC-Rough 2/8/2024 Conditional Approval JESUS RODRIGUEZ
PLUMBING-Rough 2/8/2024 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 2/12/2024 Conditional Approval HERBERT GIRON
Green Building Rough 2/12/2024 Approved HERBERT GIRON
Insulation 2/12/2024 Approved HERBERT GIRON
Verify Sprinkler Sign Off 2/12/2024 Approved HERBERT GIRON
Drywall Nailing 2/21/2024 Approved JESUS RODRIGUEZ
Shower Pan 2/21/2024 Approved JESUS RODRIGUEZ
Drywall Nailing 2/28/2024 Approved JESUS RODRIGUEZ
Underground Mechanical 4/3/2024 Partial Approval JESUS RODRIGUEZ
BUILDING-Rough-Frame 7/16/2024 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 8/16/2024 Approved JESUS RODRIGUEZ
Final 8/16/2024 Not Ready for Inspection JESUS RODRIGUEZ
Green Building Final 8/16/2024 Not Ready for Inspection JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 8/16/2024 SGSOV Not Ready JESUS RODRIGUEZ
Service/Power Release 8/16/2024 Approved JESUS RODRIGUEZ
Smoke Detectors 8/16/2024 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Final 8/22/2024 Corrections Issued HERBERT GIRON
PLUMBING-Final 8/22/2024 Not Ready for Inspection HERBERT GIRON
Service/Power Release 8/22/2024 Not Ready for Inspection HERBERT GIRON
Final 8/23/2024 Corrections Issued JESUS PINEDA
Green Building Final 8/23/2024 Approved JESUS PINEDA
HVAC-Final 8/23/2024 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 8/23/2024 SGSOV Not Ready JESUS PINEDA
Smoke Detectors 8/23/2024 Corrections Issued JESUS PINEDA
PLUMBING-Final 8/26/2024 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 8/26/2024 SGSOV Approved JESUS PINEDA
Final 8/27/2024 OK to Issue CofO JESUS PINEDA
Smoke Detectors 8/27/2024 Approved JESUS PINEDA