526 W 84TH ST C-D 90044
Certificate Information: 526 W 84TH ST C-D 90044
- Application / Permit
- 22010-10000-05987
- Plan Check / Job No.
- B22LA22663
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW THREE STORY DUPLEX IN THE MIDDLE OF THE LOT. NFPA 13 D FIRE SPRINKLERS REQUIRED THROUGHOUT. ZERO PARKING REQUIRED PER AB 2097
- Permit Issued
- Issued on 4/15/2025
- Issuing Office
- Current Status
- Issued on 4/15/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/8/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 12/1/2022 | TSE MING HUANG |
| Corrections Issued | 12/9/2022 | TSE MING HUANG |
| Quality Review Completed | 12/13/2022 | EUGENE BARBEAU |
| Applicant returned to address corrections | 8/19/2024 | SERGIO GUTIERREZ |
| Plan Check Approved | 9/26/2024 | SERGIO GUTIERREZ |
| Issued | 4/15/2025 | APPLICANT |
| Building Plans Picked Up | 9/1/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 11/20/2023 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 12/13/2023 | WALLIE JONG |
| Low Impact Development | Cleared | 2/16/2024 | JORGE MEJIA LEMUS |
| Hydrant and Access approval | Cleared | 2/24/2024 | GILBERT URREA |
| Roof/Waste drainage to street | Cleared | 5/16/2024 | WALLIE JONG |
| Sewer availability | Cleared | 7/30/2024 | WALLIE JONG |
| Frnt yard landscape/Water mgmt | Cleared | 9/27/2024 | FIPE LEILUA |
| Opn space landscape/Water mgmt | Cleared | 9/27/2024 | FIPE LEILUA |
Contact Information
| Contractor | Socal Supreme Home Builders Inc; Lic. No.: 1133905-B | 3654 E 60TH STREET HUNTINGTON PARK, CA 90255 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/12/2025 | Corrections Issued | JOHN QUINTANILLA |
| Underground Mechanical | 5/12/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Excavation/Setback/Form/Re-Bar | 5/15/2025 | Partial Approval | LUIS CASTRO |
| PLUMBING-Rough | 5/15/2025 | Partial Approval | LUIS CASTRO |
| Sewer | 5/15/2025 | Partial Approval | LUIS CASTRO |
| Excavation/Setback/Form/Re-Bar | 5/23/2025 | Approved | JOHN QUINTANILLA |
| Sewer | 5/23/2025 | Approved | JOHN QUINTANILLA |
| Underground Mechanical | 5/23/2025 | Approved | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 5/29/2025 | Corrections Issued | JOHN QUINTANILLA |
| Excavation/Setback/Form/Re-Bar | 6/2/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 6/5/2025 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/26/2025 | Partial Approval | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2025 | Partial Approval | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2025 | Corrections Issued | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2025 | Corrections Issued | JOHN QUINTANILLA |
| Rough-Elec/Plmb/HVAC | 10/24/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 10/29/2025 | Corrections Issued | JOHN QUINTANILLA |
| PLUMBING-Rough | 10/29/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 12/2/2025 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 12/2/2025 | Approved | JOHN QUINTANILLA |
| HVAC-Rough | 12/4/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| PLUMBING-Rough | 12/4/2025 | Corrections Issued | JOHN QUINTANILLA |
| HVAC-Rough | 12/29/2025 | Corrections Issued | LUIS CASTRO |
| PLUMBING-Rough | 12/29/2025 | Approved | LUIS CASTRO |
| BUILDING-Rough-Frame | 12/31/2025 | Corrections Issued | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 12/31/2025 | Partial Inspection | JOHN QUINTANILLA |
| Green Building Rough | 12/31/2025 | Approved | JOHN QUINTANILLA |
| MERV13>=Rough | 12/31/2025 | Approved | JOHN QUINTANILLA |
| Verify Sprinkler Sign Off | 12/31/2025 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 1/6/2026 | Approved | JOHN QUINTANILLA |
| HVAC-Rough | 1/6/2026 | Approved | JOHN QUINTANILLA |
| Insulation | 1/8/2026 | Corrections Issued | JOHN QUINTANILLA |
| Insulation | 1/14/2026 | Corrections Issued | GEM DE OCAMPO |
| Interior/Exterior Lathing | 1/15/2026 | Approved | GEM DE OCAMPO |
| Drywall Nailing | 1/21/2026 | Approved | MICHAEL LEWIS |
| Shower Pan | 1/21/2026 | Approved | MICHAEL LEWIS |
| Underground Mechanical | 4/6/2026 | Corrections Issued | JOHN QUINTANILLA |
| Underground Mechanical | 4/21/2026 | Corrections Issued | JOHN QUINTANILLA |
| Underground Mechanical | 4/27/2026 | Not Ready for Inspection | JOHN QUINTANILLA |
| Underground Mechanical | 5/6/2026 | Partial Inspection | JOHN QUINTANILLA |
| Underground Mechanical | 5/8/2026 | Approved | JOHN QUINTANILLA |