- Permit Issued
- Issued on 7/5/2023
- Issuing Office
- Current Status
- CofO Issued on 11/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/13/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/12/2023 | DANIEL YIP |
| Corrections Issued | 1/15/2023 | DANIEL YIP |
| Quality Review Completed | 1/17/2023 | GARO TELMI |
| Applicant returned to address corrections | 6/1/2023 | DANIEL YIP |
| Plan Check Approved | 6/22/2023 | DANIEL YIP |
| Issued | 7/5/2023 | APPLICANT |
| CofO in Progress | 10/28/2024 | TEMISTOCLES CAAL |
| CofO in Progress | 11/1/2024 | TEMISTOCLES CAAL |
| CofO in Progress | 11/19/2024 | TEMISTOCLES CAAL |
| Permit Finaled | 11/19/2024 | RICHARD STEINBACH |
| CofO Issued | 11/19/2024 | RICHARD STEINBACH |
| Permit Finaled | 11/19/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 3/22/2023 | JASON NG |
| Eng Process Fee Ord 176,300 | Cleared | 3/28/2023 | JASON NG |
| Sewer availability | Cleared | 3/28/2023 | JASON NG |
| Low Impact Development | Cleared | 3/31/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 4/3/2023 | JASON NG |
| Specific Plan | Cleared | 5/2/2023 | ROBERT SANCHEZ |
| Construction near power lines | Cleared | 5/12/2023 | RIDWAN HARDY |
Contact Information
| Contractor | Axiom Properties Inc; Lic. No.: 1091838-B | , |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 2999 OVERLAND AVE STE 103 LOS ANGELES, CA 90064 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/31/2023 | Partial Inspection | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 8/17/2023 | Approved | KENNETH NAGLE |
| Footing/Foundation/Slab | 8/17/2023 | Approved | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2023 | Partial Approval | RICHARD STEINBACH |
| Green Building Rough | 9/20/2023 | Not Ready for Inspection | RICHARD STEINBACH |
| PLUMBING-Rough | 9/20/2023 | Partial Approval | RICHARD STEINBACH |
| Deputy Wood Construction | 9/22/2023 | Conditional Approval | HERBERT GIRON |
| Wood Frame | 9/22/2023 | Conditional Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2023 | Conditional Approval | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 12/19/2023 | Approved | TEMISTOCLES CAAL |
| HVAC-Rough | 12/19/2023 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 12/19/2023 | Partial Approval | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2024 | Approved | TEMISTOCLES CAAL |
| Rough-Elec/Plmb/HVAC | 1/11/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Underground Mechanical | 1/26/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 2/22/2024 | Corrections Issued | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 2/27/2024 | Approved | TEMISTOCLES CAAL |
| Green Building Rough | 2/27/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Rough | 2/27/2024 | Approved | TEMISTOCLES CAAL |
| Pre-Inspection | 3/1/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2024 | Approved | TEMISTOCLES CAAL |
| Insulation | 3/7/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 3/11/2024 | Approved | TEMISTOCLES CAAL |
| Gas Test | 3/22/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 4/30/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 6/11/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Final | 6/11/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Green Building Final | 6/11/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Final | 6/11/2024 | Corrections Issued | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 6/11/2024 | SGSOV Approved | TEMISTOCLES CAAL |
| Service/Power Release | 6/11/2024 | Not Required | TEMISTOCLES CAAL |
| Smoke Detectors | 6/11/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 6/28/2024 | Approved | TEMISTOCLES CAAL |
| Final | 6/28/2024 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Final | 6/28/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Final | 6/28/2024 | Approved | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 6/28/2024 | SGSOV Approved | TEMISTOCLES CAAL |
| Green Building Final | 7/1/2024 | Approved | TEMISTOCLES CAAL |
| Final | 10/25/2024 | OK to Issue CofO | TEMISTOCLES CAAL |