110 N MAPLETON DR 90077

Certificate Information: 110 N MAPLETON DR 90077

Application / Permit
22010-10000-05949
Plan Check / Job No.
B22LA24589
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
ePlan (N) Detached 2-Story Accessory Living Quarter
Permit Issued
Issued on 10/30/2023
Issuing Office
Current Status
Issued on 10/30/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/6/2022 APPLICANT
Assigned to Plan Check Engineer 1/5/2023 MAHNAZ NOURHASHEMI
Corrections Issued 1/11/2023 MAHNAZ NOURHASHEMI
Quality Review Completed 1/19/2023 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 9/19/2023 MAHNAZ NOURHASHEMI
Plan Check Approved 10/24/2023 MAHNAZ NOURHASHEMI
Issued 10/30/2023 APPLICANT

Permit Application Clearance Information

GPI Written Notices Cleared 1/11/2023 MAHNAZ NOURHASHEMI
Grading Pre-Inspection Cleared 1/11/2023 MAHNAZ NOURHASHEMI
Eng Process Fee Ord 176,300 Cleared 3/9/2023 JENSON LEE
Sewer availability Cleared 3/9/2023 JENSON LEE
ZA Case Cleared 3/13/2023 SPENCER WEJROWSKI
ZA Case Cleared 3/13/2023 SPENCER WEJROWSKI
Low Impact Development Cleared 8/29/2023 VICTOR MENDOZA
Roof/Waste drainage to street Cleared 9/1/2023 ANTHONY MAINEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Ilasin,, John Lacebal; Lic. No.: C67469 1011 OARFISH LN      OXNARD, CA 93035

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/15/2024 Corrections Issued STEPHANIE SWANSON
Underground Mechanical 2/16/2024 Partial Approval STEPHANIE SWANSON
Verify Sprinkler Sign Off 2/16/2024 Corrections Issued STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 2/23/2024 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 2/27/2024 Conditional Approval CHRISTOPHER WILSON
Underground Mechanical 3/29/2024 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 4/11/2024 Approved CHRISTOPHER WILSON
Special/Order Compliance 4/11/2024 Corrections Issued CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 5/2/2024 Approved SEAN HAUPT
Verify Sprinkler Sign Off 5/2/2024 Not Ready for Inspection SEAN HAUPT
Floor/Roof Diaphrgm/Shear Wall 5/14/2024 Partial Approval SEAN HAUPT
Reinforced Masonry Frame 5/14/2024 Not Ready for Inspection SEAN HAUPT
Wood Frame 5/14/2024 Partial Approval SEAN HAUPT
HVAC-Rough 6/21/2024 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 6/21/2024 Approved CHRISTOPHER WILSON
ELECTRICAL-Rough 8/15/2024 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 8/15/2024 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 8/20/2024 Conditional Approval STEPHANIE SWANSON
ELECTRICAL-Rough 8/20/2024 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 8/20/2024 Approved STEPHANIE SWANSON
Green Building Rough 8/20/2024 Not Ready for Inspection STEPHANIE SWANSON
Smoke Detectors 8/20/2024 Not Ready for Inspection STEPHANIE SWANSON
Verify Sprinkler Sign Off 8/20/2024 Approved STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 8/28/2024 Not Ready for Inspection SEAN HAUPT
Shower Pan 9/23/2024 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 10/21/2024 Approved CHRISTOPHER WILSON
Green Building Rough 10/21/2024 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 10/21/2024 Approved CHRISTOPHER WILSON
Insulation 10/31/2024 Approved CHRISTOPHER WILSON
Drywall Nailing 11/8/2024 Approved CHRISTOPHER WILSON
Masonry Wall/Backfill 5/14/2025 Approved CHRISTOPHER WILSON
Underground Mechanical 7/29/2025 Partial Approval SEAN HAUPT
Underground Mechanical 8/6/2025 Corrections Issued DANIEL VERA
Underground Mechanical 8/12/2025 Partial Approval CHRISTOPHER WILSON
Sewer 5/4/2026 Corrections Issued ANDREW NAVE
Sewer 5/8/2026 Approved CARLOS MATAMOROS